Event Notification Report for June 28, 2008
U.S. Nuclear Regulatory Commission
Operations Center
EVENT REPORTS FOR
06/27/2008 - 06/28/2008
Power Reactor
Event Number: 44326
Facility: MILLSTONE
Region: 1 State: CT
Unit: [] [2] []
RX Type: [1] GE-3,[2] CE,[3] W-4-LP
NRC Notified By: MARIA GHARAKHANIAN
HQ OPS Officer: JEFF ROTTON
Region: 1 State: CT
Unit: [] [2] []
RX Type: [1] GE-3,[2] CE,[3] W-4-LP
NRC Notified By: MARIA GHARAKHANIAN
HQ OPS Officer: JEFF ROTTON
Notification Date: 06/28/2008
Notification Time: 12:54 [ET]
Event Date: 06/28/2008
Event Time: 11:46 [EDT]
Last Update Date: 06/28/2008
Notification Time: 12:54 [ET]
Event Date: 06/28/2008
Event Time: 11:46 [EDT]
Last Update Date: 06/28/2008
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(iv)(B) - RPS ACTUATION - CRITICAL
10 CFR Section:
50.72(b)(2)(iv)(B) - RPS ACTUATION - CRITICAL
Person (Organization):
HAROLD GRAY (R1)
HAROLD GRAY (R1)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 2 | M/R | Y | 100 | Power Operation | 0 | Hot Standby |
MANUAL REACTOR TRIP DUE TO LOSS OF BOTH FEEDWATER PUMPS
At 1146, the reactor was manually tripped due to a feedwater transient that was caused by a loss of both feedwater pumps. The exact cause of the loss of both feedwater pumps is still being investigated. Prior to the reactor trip, the licensee was performing main turbine stop valve testing and during that testing received an isolation of extraction steam.
On the manual reactor trip, all control rods fully inserted. No RCS PORVs or reactor safety valves lifted. The steam generator atmospheric dump valves did lift and reseat. Decay heat is being removed to the condenser via the turbine dump valves. Auxiliary Feedwater (AFW) initiated and fed the steam generators after the loss of both main feedwater (MFW) pumps. MFW was restored and is controlling steam generator levels. AFW has been secured. The electric plant is in a normal shutdown lineup and the EDGs are available. There was no effect on Unit 3.
The licensee has notified the NRC Resident Inspector, Connecticut Department of Environmental Protection, and all local emergency response organizations.
At 1146, the reactor was manually tripped due to a feedwater transient that was caused by a loss of both feedwater pumps. The exact cause of the loss of both feedwater pumps is still being investigated. Prior to the reactor trip, the licensee was performing main turbine stop valve testing and during that testing received an isolation of extraction steam.
On the manual reactor trip, all control rods fully inserted. No RCS PORVs or reactor safety valves lifted. The steam generator atmospheric dump valves did lift and reseat. Decay heat is being removed to the condenser via the turbine dump valves. Auxiliary Feedwater (AFW) initiated and fed the steam generators after the loss of both main feedwater (MFW) pumps. MFW was restored and is controlling steam generator levels. AFW has been secured. The electric plant is in a normal shutdown lineup and the EDGs are available. There was no effect on Unit 3.
The licensee has notified the NRC Resident Inspector, Connecticut Department of Environmental Protection, and all local emergency response organizations.
Power Reactor
Event Number: 44327
Facility: FARLEY
Region: 2 State: AL
Unit: [1] [2] []
RX Type: [1] W-3-LP,[2] W-3-LP
NRC Notified By: FOREST LERO
HQ OPS Officer: JEFF ROTTON
Region: 2 State: AL
Unit: [1] [2] []
RX Type: [1] W-3-LP,[2] W-3-LP
NRC Notified By: FOREST LERO
HQ OPS Officer: JEFF ROTTON
Notification Date: 06/28/2008
Notification Time: 16:59 [ET]
Event Date: 06/28/2008
Event Time: 00:29 [CDT]
Last Update Date: 06/28/2008
Notification Time: 16:59 [ET]
Event Date: 06/28/2008
Event Time: 00:29 [CDT]
Last Update Date: 06/28/2008
Emergency Class: NON EMERGENCY
10 CFR Section:
26.719 - FITNESS FOR DUTY
10 CFR Section:
26.719 - FITNESS FOR DUTY
Person (Organization):
KATHLEEN O'DONOHUE (R2)
KATHLEEN O'DONOHUE (R2)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 1 | N | Y | 100 | Power Operation | 100 | Power Operation |
| 2 | N | Y | 100 | Power Operation | 100 | Power Operation |
POSITIVE FOR CAUSE FITNESS FOR DUTY TEST
A non-licensed employee had a confirmed positive for alcohol during a for cause fitness-for-duty test. The employee's access to the plant has been placed on hold. Contact the Headquarters Operations Officer for additional details.
The licensee notified the NRC Resident Inspector.
A non-licensed employee had a confirmed positive for alcohol during a for cause fitness-for-duty test. The employee's access to the plant has been placed on hold. Contact the Headquarters Operations Officer for additional details.
The licensee notified the NRC Resident Inspector.
Power Reactor
Event Number: 44439
Facility: COMANCHE PEAK
Region: 4 State: TX
Unit: [1] [] []
RX Type: [1] W-4-LP,[2] W-4-LP
NRC Notified By: GARY MERKA
HQ OPS Officer: HOWIE CROUCH
Region: 4 State: TX
Unit: [1] [] []
RX Type: [1] W-4-LP,[2] W-4-LP
NRC Notified By: GARY MERKA
HQ OPS Officer: HOWIE CROUCH
Notification Date: 08/25/2008
Notification Time: 16:27 [ET]
Event Date: 06/28/2008
Event Time: 19:04 [CDT]
Last Update Date: 08/25/2008
Notification Time: 16:27 [ET]
Event Date: 06/28/2008
Event Time: 19:04 [CDT]
Last Update Date: 08/25/2008
Emergency Class: NON EMERGENCY
10 CFR Section:
50.73(a)(1) - INVALID SPECIF SYSTEM ACTUATION
10 CFR Section:
50.73(a)(1) - INVALID SPECIF SYSTEM ACTUATION
Person (Organization):
VIVIAN CAMPBELL (R4)
VIVIAN CAMPBELL (R4)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 1 | N | Y | 100 | Power Operation | 95 | Power Operation |
60-DAY OPTIONAL REPORT FOR AN INVALID ACTUATION OF UNIT 1 TDAFW PUMP
"This report describes an invalid actuation of the Unit 1 Turbine Driven Auxiliary Feedwater (TDAFW) pump that occurred on June 28, 2008. This report is being made in accordance with 10CFR50.73(a)(1), which states, in part, 'In the case of an invalid actuation reported under 10CFR50.73(a)(2)(iv), other than actuation of the Reactor Protection System (RPS) when the reactor is critical, the licensee may, at its option, provide a telephone notification to the NRC Operations Center within 60 days after discovery of the event instead of submitting a written LER.'
"On June 28, 2008, Comanche Peak Nuclear Power Plant Unit 1 was in Mode 1 operating at 100% power. At 1904 CDT, the steam supply valve from Main Steam Line 1-04 to the TDAFW pump opened due to a failed diaphragm. Turbine load was subsequently reduced from 1207MWe to 1150MWe per Operations procedures. The upstream isolation valve for the steam supply to the TDAFW pump was closed and the TDAFW pump was stopped. Unit 1 was returned to full power at 2120 CDT and the failed diaphragm was subsequently replaced.
"The specific train and system that actuated was the third AFW train on Unit 1. The train actuation was complete and during the TDAFW start the system started and functioned correctly."
The licensee has notified the NRC Resident Inspector.
"This report describes an invalid actuation of the Unit 1 Turbine Driven Auxiliary Feedwater (TDAFW) pump that occurred on June 28, 2008. This report is being made in accordance with 10CFR50.73(a)(1), which states, in part, 'In the case of an invalid actuation reported under 10CFR50.73(a)(2)(iv), other than actuation of the Reactor Protection System (RPS) when the reactor is critical, the licensee may, at its option, provide a telephone notification to the NRC Operations Center within 60 days after discovery of the event instead of submitting a written LER.'
"On June 28, 2008, Comanche Peak Nuclear Power Plant Unit 1 was in Mode 1 operating at 100% power. At 1904 CDT, the steam supply valve from Main Steam Line 1-04 to the TDAFW pump opened due to a failed diaphragm. Turbine load was subsequently reduced from 1207MWe to 1150MWe per Operations procedures. The upstream isolation valve for the steam supply to the TDAFW pump was closed and the TDAFW pump was stopped. Unit 1 was returned to full power at 2120 CDT and the failed diaphragm was subsequently replaced.
"The specific train and system that actuated was the third AFW train on Unit 1. The train actuation was complete and during the TDAFW start the system started and functioned correctly."
The licensee has notified the NRC Resident Inspector.