4397143972

Power Reactor
Event Number: 43971
Facility: MCGUIRE
Region: 2     State: NC
Unit: [1] [2] []
RX Type: [1] W-4-LP,[2] W-4-LP
NRC Notified By: RICHARD ELLIOT
HQ OPS Officer: MARK ABRAMOVITZ
Notification Date: 02/08/2008
Notification Time: 14:02 [ET]
Event Date: 02/08/2008
Event Time: 14:02 [EST]
Last Update Date: 02/08/2008
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(xi) - OFFSITE NOTIFICATION
Person (Organization):
RANDY MUSSER (R2)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
1 N Y 100 Power Operation 100 Power Operation
2 N Y 100 Power Operation 100 Power Operation
Event Text
PH MONITORING PROBE EFFLUENT BYPASSES THE WASTE HOLDUP POND

"As part of the on going investigation of the final holdup pond (NRC Notification #43958), McGuire has identified a discharge path from the pH monitoring and adjustment system that has existed since plant startup. This discharge path has been secured. The North Carolina Department of Environmental and Natural Resources will be notified."

The effluent from the pH monitoring probe had been routed to a pit which drains into the river i.e. bypassing the holdup pond.

The licensee notified the NRC Resident Inspector.


Power Reactor
Event Number: 43972
Facility: NORTH ANNA
Region: 2     State: VA
Unit: [] [2] []
RX Type: [1] W-3-LP,[2] W-3-LP
NRC Notified By: PAUL TRENT
HQ OPS Officer: MARK ABRAMOVITZ
Notification Date: 02/08/2008
Notification Time: 19:59 [ET]
Event Date: 02/08/2008
Event Time: 18:12 [EST]
Last Update Date: 02/08/2008
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(3)(iv)(A) - VALID SPECIF SYS ACTUATION
Person (Organization):
JOEL MUNDAY (R2)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
2 N N 0 Hot Standby 0 Hot Standby
Event Text
CONTROL ROD POSITION DEVIATION

"While withdrawing shutdown bank rods in preparation for a North Anna Unit 2 startup, a Rod Control system Urgent Failure alarm was received in the main control room. Further investigation revealed group step counters for Shutdown Bank 'A' deviated by 3 steps from demand. TRM 3.1.3 was entered and the Reactor Trip breakers were opened within the 15 minute requirement."