Event Notification Report for November 15, 2007
U.S. Nuclear Regulatory Commission
Operations Center
EVENT REPORTS FOR
11/14/2007 - 11/15/2007
EVENT NUMBERS
43787438424382643784
Fuel Cycle Facility
Event Number: 43787
Facility: PADUCAH GASEOUS DIFFUSION PLANT
Region: 2 State: KY
Unit: [] [] []
RX Type: URANIUM ENRICHMENT FACILITY
Comments: 2 DEMOCRACY CENTER
6903 ROCKLEDGE DRIVE
BETHESDA, MD 20817 (301)564-3200
NRC Notified By: BILLY WALLACE
HQ OPS Officer: JASON KOZAL
Region: 2 State: KY
Unit: [] [] []
RX Type: URANIUM ENRICHMENT FACILITY
Comments: 2 DEMOCRACY CENTER
6903 ROCKLEDGE DRIVE
BETHESDA, MD 20817 (301)564-3200
NRC Notified By: BILLY WALLACE
HQ OPS Officer: JASON KOZAL
Notification Date: 11/16/2007
Notification Time: 10:14 [ET]
Event Date: 11/15/2007
Event Time: 09:15 [CST]
Last Update Date: 11/16/2007
Notification Time: 10:14 [ET]
Event Date: 11/15/2007
Event Time: 09:15 [CST]
Last Update Date: 11/16/2007
Emergency Class: NON EMERGENCY
10 CFR Section:
10 CFR Section:
Person (Organization):
GEORGE HOPPER (R2)
CINDY FLANNERY (FSME)
GEORGE HOPPER (R2)
CINDY FLANNERY (FSME)
SAFETY SYSTEM ACTUATION DUE TO INCIDENTAL UF6 RELEASE
"On 11/15/2007 at 0915 instrument mechanics were performing a cell datum calibration in the C-333 Unit 4 Cell 2 cell panel when a strong odor assumed to be HF was noticed after the stage 1 high side pressure valve was opened. The 1/4" valve is on a manifold which accesses pressure taps in various locations in the cell. When the odor was detected a UF6 leak detection head located in the cell panel ducting also actuated. The mechanic opening the valve, immediately closed the valve when the odor was detected and they immediately left the area. HF samples taken a few minutes later in the area around the cell panel were all negative. Precautionary urine samples have been taken from the individuals involved and analysis are being run on the samples.
"It is believed a small incidental UF6 release occurred when the small high side valve was momentarily opened and actuated the UF6 detection system head which is a Q safety system component. At the time of the incident the cell was in operation in a mode which required the system to be operational. This is being reported based on SAR 6.9 Table 1, J2.
"The NRC Resident Inspector has been notified of this event."
"On 11/15/2007 at 0915 instrument mechanics were performing a cell datum calibration in the C-333 Unit 4 Cell 2 cell panel when a strong odor assumed to be HF was noticed after the stage 1 high side pressure valve was opened. The 1/4" valve is on a manifold which accesses pressure taps in various locations in the cell. When the odor was detected a UF6 leak detection head located in the cell panel ducting also actuated. The mechanic opening the valve, immediately closed the valve when the odor was detected and they immediately left the area. HF samples taken a few minutes later in the area around the cell panel were all negative. Precautionary urine samples have been taken from the individuals involved and analysis are being run on the samples.
"It is believed a small incidental UF6 release occurred when the small high side valve was momentarily opened and actuated the UF6 detection system head which is a Q safety system component. At the time of the incident the cell was in operation in a mode which required the system to be operational. This is being reported based on SAR 6.9 Table 1, J2.
"The NRC Resident Inspector has been notified of this event."
General Information or Other
Event Number: 43842
Rep Org: LOUISIANA RADIATION PROTECTION DIV
Licensee: EUSTIS ENGINEERING
Region: 4
City: State: LA
County: ST. JAMES PARISH
License #: LA-2922-L01
Agreement: Y
Docket:
NRC Notified By: RICHARD PENROD
HQ OPS Officer: JOHN MacKINNON
Licensee: EUSTIS ENGINEERING
Region: 4
City: State: LA
County: ST. JAMES PARISH
License #: LA-2922-L01
Agreement: Y
Docket:
NRC Notified By: RICHARD PENROD
HQ OPS Officer: JOHN MacKINNON
Notification Date: 12/14/2007
Notification Time: 10:49 [ET]
Event Date: 11/15/2007
Event Time: 08:00 [CST]
Last Update Date: 12/14/2007
Notification Time: 10:49 [ET]
Event Date: 11/15/2007
Event Time: 08:00 [CST]
Last Update Date: 12/14/2007
Emergency Class: NON EMERGENCY
10 CFR Section:
10 CFR Section:
Person (Organization):
RUSSELL BYWATER (R4)
GREG MORELL (FSME)
RUSSELL BYWATER (R4)
GREG MORELL (FSME)
LOUISIANA AGREEMENT STATE REPORT - TROXLER MOISTURE DENSITY GAUGE HIT BY A BULLDOZER
This information was received via email
"Eustis Engineering reported an incident that occurred on November 15, 2007. At 8:00AM on this date a Troxler gauge model number 3440 with serial number 25934 was hit by a bulldozer. This gauge has a 8.0 mCi source Cs-137 and a 20 mCi source of Am241:Be. The bulldozer that hit the gauge was operated by James Construction at the Marathon GME Refinery construction site. The technician called the Eustis Engineering office immediately after it occurred. Mr. (deleted), the Eustis RSO, was dispatched to the site. The RSO arrived at 9:30AM and conducted a survey using a Trox Alert survey meter. At 30 feet away the meter reading was 0.1 mR. At 2 feet away the meter reading was 0.2 mR. A leak test was conducted by Gamma Tron on November 15, 2007 after the incident with the results being less than 0.005 uCi (microCuries) of removable contamination."
Event Report ID No.: LA070031.
This information was received via email
"Eustis Engineering reported an incident that occurred on November 15, 2007. At 8:00AM on this date a Troxler gauge model number 3440 with serial number 25934 was hit by a bulldozer. This gauge has a 8.0 mCi source Cs-137 and a 20 mCi source of Am241:Be. The bulldozer that hit the gauge was operated by James Construction at the Marathon GME Refinery construction site. The technician called the Eustis Engineering office immediately after it occurred. Mr. (deleted), the Eustis RSO, was dispatched to the site. The RSO arrived at 9:30AM and conducted a survey using a Trox Alert survey meter. At 30 feet away the meter reading was 0.1 mR. At 2 feet away the meter reading was 0.2 mR. A leak test was conducted by Gamma Tron on November 15, 2007 after the incident with the results being less than 0.005 uCi (microCuries) of removable contamination."
Event Report ID No.: LA070031.
General Information or Other
Event Number: 43826
Rep Org: ROSEMOUNT NUCLEAR
Licensee: ROSEMOUNT NUCLEAR
Region: 3
City: CHANHASSEN State: MN
County:
License #:
Agreement: Y
Docket:
NRC Notified By: DAVID T. ROBERTS
HQ OPS Officer: JASON KOZAL
Licensee: ROSEMOUNT NUCLEAR
Region: 3
City: CHANHASSEN State: MN
County:
License #:
Agreement: Y
Docket:
NRC Notified By: DAVID T. ROBERTS
HQ OPS Officer: JASON KOZAL
Notification Date: 12/06/2007
Notification Time: 14:03 [ET]
Event Date: 11/15/2007
Event Time: 00:00 [CST]
Last Update Date: 12/06/2007
Notification Time: 14:03 [ET]
Event Date: 11/15/2007
Event Time: 00:00 [CST]
Last Update Date: 12/06/2007
Emergency Class: NON EMERGENCY
10 CFR Section:
21.21 - UNSPECIFIED PARAGRAPH
10 CFR Section:
21.21 - UNSPECIFIED PARAGRAPH
Person (Organization):
RICHARD BARKLEY (R1)
RANDY MUSSER (R2)
CHUCK CAIN (R4)
PART 21 GROUP -EMAIL
JULIO LARA (R3)
RICHARD BARKLEY (R1)
RANDY MUSSER (R2)
CHUCK CAIN (R4)
PART 21 GROUP -EMAIL
JULIO LARA (R3)
PART 21 - POTENTIAL INSUFFICIENT THREAD ENGAGEMENT FOR CERTAIN PRESSURE TRANSMITTERS
Rosemount Nuclear Instruments, Inc. (RNII) reported that certain Model 1152, 1153 Series B and D, and 1154, and 1154 Series H Pressure Transmitters may have inadequate thread engagement between the electronics housing and sensor module. Transmitters affected by this notification may not confirm to RNII specifications under accident conditions. Supplier testing has determined that no immediate risk exists, however it is RNII's opinion that two threads of engagement may not be sufficient to assure that the product will perform its intended safety function over the qualified life of the transmitter.
The following are the potentially affected licensees: Oyster Creek, Calvert Cliffs, Kewaunee, North Anna, Millstone, Surry, Turkey Point, Vogtle, Diablo Canyon, Shearon Harris, South Texas Project, Browns Ferry, and Wolf Creek.
Rosemount Nuclear Instruments, Inc. (RNII) reported that certain Model 1152, 1153 Series B and D, and 1154, and 1154 Series H Pressure Transmitters may have inadequate thread engagement between the electronics housing and sensor module. Transmitters affected by this notification may not confirm to RNII specifications under accident conditions. Supplier testing has determined that no immediate risk exists, however it is RNII's opinion that two threads of engagement may not be sufficient to assure that the product will perform its intended safety function over the qualified life of the transmitter.
The following are the potentially affected licensees: Oyster Creek, Calvert Cliffs, Kewaunee, North Anna, Millstone, Surry, Turkey Point, Vogtle, Diablo Canyon, Shearon Harris, South Texas Project, Browns Ferry, and Wolf Creek.
Power Reactor
Event Number: 43784
Facility: FERMI
Region: 3 State: MI
Unit: [2] [] []
RX Type: [2] GE-4
NRC Notified By: GEORGE MILLER
HQ OPS Officer: JOE O'HARA
Region: 3 State: MI
Unit: [2] [] []
RX Type: [2] GE-4
NRC Notified By: GEORGE MILLER
HQ OPS Officer: JOE O'HARA
Notification Date: 11/15/2007
Notification Time: 06:34 [ET]
Event Date: 11/15/2007
Event Time: 03:13 [EST]
Last Update Date: 11/15/2007
Notification Time: 06:34 [ET]
Event Date: 11/15/2007
Event Time: 03:13 [EST]
Last Update Date: 11/15/2007
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(iv)(B) - RPS ACTUATION - CRITICAL
10 CFR Section:
50.72(b)(2)(iv)(B) - RPS ACTUATION - CRITICAL
Person (Organization):
DAVE PASSEHL (R3)
DAVE PASSEHL (R3)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 2 | M/R | Y | 9 | Startup | 0 | Hot Shutdown |
REACTOR SCRAM - INITIATION OF ARI CAUSED BY LEVEL 2 SIGNAL
"At 03:13 EST 11/15/2007, a reactor scram occurred due to initiation of ARI caused by a Level 2 signal from Div 1 level instrumentation. The reactor mode switch was taken to shutdown in response to the trip of the recirc pumps initiated by ARI as directed by our Abnormal Operating procedures. All control rods fully inserted into the core. The lowest reactor vessel water level reached was 183 inches. The MSIV's were manually closed to control cooldown rate. Reactor water level is being controlled by CRD and reactor water cleanup blowdown.
"At the time of the scram, protective tagging was being hung on the Division I Reference Leg Backfill system.
"At the time of the scram all ECCS systems and Emergency Diesel Generators were operable. This report is being made in accordance with 10 CFR 50.72(b)(2)(iv)(B), any event that results in actuation of the reactor protection system (RPS) when the reactor is critical."
The licensee is investigating the cause of the scram. There was no ECCS injection. Primary plant pressure is 400 psig, and primary plant temperature is 335 degrees Fahrenheit. The scram is uncomplicated.
The licensee notified the NRC Resident Inspector.
"At 03:13 EST 11/15/2007, a reactor scram occurred due to initiation of ARI caused by a Level 2 signal from Div 1 level instrumentation. The reactor mode switch was taken to shutdown in response to the trip of the recirc pumps initiated by ARI as directed by our Abnormal Operating procedures. All control rods fully inserted into the core. The lowest reactor vessel water level reached was 183 inches. The MSIV's were manually closed to control cooldown rate. Reactor water level is being controlled by CRD and reactor water cleanup blowdown.
"At the time of the scram, protective tagging was being hung on the Division I Reference Leg Backfill system.
"At the time of the scram all ECCS systems and Emergency Diesel Generators were operable. This report is being made in accordance with 10 CFR 50.72(b)(2)(iv)(B), any event that results in actuation of the reactor protection system (RPS) when the reactor is critical."
The licensee is investigating the cause of the scram. There was no ECCS injection. Primary plant pressure is 400 psig, and primary plant temperature is 335 degrees Fahrenheit. The scram is uncomplicated.
The licensee notified the NRC Resident Inspector.