Event Notification Report for August 19, 2007
U.S. Nuclear Regulatory Commission
Operations Center
EVENT REPORTS FOR
08/18/2007 - 08/19/2007
EVENT NUMBERS
43580
Power Reactor
Event Number: 43580
Facility: SAINT LUCIE
Region: 2 State: FL
Unit: [] [2] []
RX Type: [1] CE,[2] CE
NRC Notified By: CALVIN WARD
HQ OPS Officer: JASON KOZAL
Region: 2 State: FL
Unit: [] [2] []
RX Type: [1] CE,[2] CE
NRC Notified By: CALVIN WARD
HQ OPS Officer: JASON KOZAL
Notification Date: 08/19/2007
Notification Time: 22:19 [ET]
Event Date: 08/19/2007
Event Time: 17:00 [EDT]
Last Update Date: 08/19/2007
Notification Time: 22:19 [ET]
Event Date: 08/19/2007
Event Time: 17:00 [EDT]
Last Update Date: 08/19/2007
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(3)(ii)(A) - DEGRADED CONDITION
10 CFR Section:
50.72(b)(3)(ii)(A) - DEGRADED CONDITION
Person (Organization):
CHARLES R. OGLE (R2)
CHARLES R. OGLE (R2)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 2 | N | N | 0 | Cold Shutdown | 0 | Cold Shutdown |
PLANT SHUTDOWN DUE TO UNISOLABLE REACTOR COOLANT SYSTEM LEAKAGE
"On 08/18/2007 at 16:03 EDT a Planned Manual Reactor Trip was initiated on Unit 2 based on increased unidentified RCS leakage. The RCS leakage had increased over a two day period and surpassed the hard limit of 0.28 gpm established by a plant Operational Decision Making (ODM) plan. The downpower was initiated on 08/18/07 at 10:35 EDT from 100% power and proceeded in a controlled manner to 25% power. The Feedwater Control System was maintained in the automatic mode. Station Power was transferred by procedure from the Auxiliary to the Startup Transformers. The reactor was manually tripped at 16:03 EDT. Following the reactor trip, EOP-1, Standard Post Trip Actions, and EOP-2, Reactor Trip Recovery procedures were completed without contingencies and the unit was stabilized in Mode 3. Decay heat was removed by the Steam Bypass Control System (SBCS) to the condenser. The Steam Generators were fed by the MFW System and levels remained above Auxiliary Feedwater Actuation (AFAS) setpoint. There were no significant equipment failures identified post trip. The plant was cooled down and entered Mode 5 on 8/19/07 at 15:09 EDT.
"On 8/19/07 at 17:00 EDT while in Mode 5, a Containment walkdown confirmed the 2B1 RCP Seal injection line to be the only active RCS leakage source. The leak is unisolable from the RCS and is located at or adjacent to a socket weld on the 3/4" Class 1 Schedule 160 seal injection line. Removal of obstructions and insulation must occur before the specific details of the leak can be identified.
"This non-emergency notification is being made pursuant to 10 CFR 50.72(b)(3)(ii)(A). Additional investigation is being perform to determine the detailed configuration of the leak and the root cause."
The licensee notified the NRC Resident Inspector.
"On 08/18/2007 at 16:03 EDT a Planned Manual Reactor Trip was initiated on Unit 2 based on increased unidentified RCS leakage. The RCS leakage had increased over a two day period and surpassed the hard limit of 0.28 gpm established by a plant Operational Decision Making (ODM) plan. The downpower was initiated on 08/18/07 at 10:35 EDT from 100% power and proceeded in a controlled manner to 25% power. The Feedwater Control System was maintained in the automatic mode. Station Power was transferred by procedure from the Auxiliary to the Startup Transformers. The reactor was manually tripped at 16:03 EDT. Following the reactor trip, EOP-1, Standard Post Trip Actions, and EOP-2, Reactor Trip Recovery procedures were completed without contingencies and the unit was stabilized in Mode 3. Decay heat was removed by the Steam Bypass Control System (SBCS) to the condenser. The Steam Generators were fed by the MFW System and levels remained above Auxiliary Feedwater Actuation (AFAS) setpoint. There were no significant equipment failures identified post trip. The plant was cooled down and entered Mode 5 on 8/19/07 at 15:09 EDT.
"On 8/19/07 at 17:00 EDT while in Mode 5, a Containment walkdown confirmed the 2B1 RCP Seal injection line to be the only active RCS leakage source. The leak is unisolable from the RCS and is located at or adjacent to a socket weld on the 3/4" Class 1 Schedule 160 seal injection line. Removal of obstructions and insulation must occur before the specific details of the leak can be identified.
"This non-emergency notification is being made pursuant to 10 CFR 50.72(b)(3)(ii)(A). Additional investigation is being perform to determine the detailed configuration of the leak and the root cause."
The licensee notified the NRC Resident Inspector.