Event Notification Report for December 03, 2006
U.S. Nuclear Regulatory Commission
Operations Center
EVENT REPORTS FOR
12/02/2006 - 12/03/2006
!!!!! THIS EVENT HAS BEEN RETRACTED !!!!!
!!!!! THIS EVENT HAS BEEN RETRACTED !!!!!
Power Reactor
Event Number: 43021
Facility: PERRY
Region: 3 State: OH
Unit: [1] [] []
RX Type: [1] GE-6
NRC Notified By: JIM CASE
HQ OPS Officer: BILL GOTT
Region: 3 State: OH
Unit: [1] [] []
RX Type: [1] GE-6
NRC Notified By: JIM CASE
HQ OPS Officer: BILL GOTT
Notification Date: 12/03/2006
Notification Time: 15:20 [ET]
Event Date: 12/03/2006
Event Time: 08:58 [EST]
Last Update Date: 12/14/2006
Notification Time: 15:20 [ET]
Event Date: 12/03/2006
Event Time: 08:58 [EST]
Last Update Date: 12/14/2006
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(3)(v)(D) - ACCIDENT MITIGATION
10 CFR Section:
50.72(b)(3)(v)(D) - ACCIDENT MITIGATION
Person (Organization):
LAURA KOZAK (R3)
LAURA KOZAK (R3)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 1 | N | Y | 100 | Power Operation | 100 | Power Operation |
ACCIDENT MITIGATION - HIGH PRESSURE CORE SPRAY (DIVISION 3) EMERGENCY DIESEL INOPERABLE
"On December 3, 2006, at 0858 hours, control room operators received a Division 3 Emergency Diesel Generator (EDG) Carbon Dioxide (CO2) (Fire Protection) system initiation signal. The CO2 system for the Division 3 EDG room was out of service at the time and so no CO2 was released into the room. At 0905 hours, a first responder notified the control room operators that there was no indication of a fire in the Division 3 EDG room. A walkdown of the associated EDG room ventilation system confirmed the ventilation system tripped with the CO2 initiation signal locked in. At 0919 hours, the Division 3 EDG was declared inoperable and Technical Specification (TS) LCO 3.8.1 Condition B was entered. The required TS actions were implemented. The Division 3 EDG is available with restoration of the ventilation system using the CO2 Override switch. The CO2 initiation signal is currently locked in, and the Division 3 CO2 Fire Monitoring Panel, with associated equipment has been quarantined for further investigation.
"The Division 3 EDG provides emergency AC electrical power to the High Pressure Core Spray system. This event is being reported as a condition that could have prevented the safety function of structures or systems required to mitigate the consequences of an accident. The Resident Inspector has been notified."
* * * EVENT RETRACTED AT 1324 ON 12/14/06 FROM C. ELBERFELD TO P. SNYDER * * *
"The purpose of this call is to retract Event Number 43021. On December 3, 2006, at 1520 hours, a notification, Event Number 43021, was made to the NRC Operations Center by the Perry Nuclear Power Plant (PNPP) in accordance with 10 CFR 50.72(b)(3)(v)(D) as a condition that at the time of discovery could have prevented the fulfillment of the safety function of a system that is needed to mitigate the consequences of an accident. A spurious Carbon Dioxide (CO2) Fire Protection system initiation signal resulted in a tripped condition for the Division 3 Emergency Diesel Generator (EDG) room ventilation system. Operators declared the Division 3 EDG inoperable and took the appropriate Technical Specification actions. The Division 3 EDG provides emergency AC electrical power to the High Pressure Core Spray system. The High Pressure Core Spray system is a single train safety system.
"After further evaluation, it was determined that operators could promptly restore the ventilation system, with the CO2 initiation signal locked in, if the Division 3 EDG was needed, and that the safety function of the system could still be fulfilled during the time in question. Because the condition reported in Event Number 43021 would not have prevented the fulfillment of the safety function of a system that is needed to mitigate the consequences of an accident, the condition is not reportable, and this notification is retracted. The evaluation (i.e., Reportability Review) for this condition is documented in Condition Report 06-10843.
"The NRC Resident Inspector has been notified."
Notified R3DO (Lara).
"On December 3, 2006, at 0858 hours, control room operators received a Division 3 Emergency Diesel Generator (EDG) Carbon Dioxide (CO2) (Fire Protection) system initiation signal. The CO2 system for the Division 3 EDG room was out of service at the time and so no CO2 was released into the room. At 0905 hours, a first responder notified the control room operators that there was no indication of a fire in the Division 3 EDG room. A walkdown of the associated EDG room ventilation system confirmed the ventilation system tripped with the CO2 initiation signal locked in. At 0919 hours, the Division 3 EDG was declared inoperable and Technical Specification (TS) LCO 3.8.1 Condition B was entered. The required TS actions were implemented. The Division 3 EDG is available with restoration of the ventilation system using the CO2 Override switch. The CO2 initiation signal is currently locked in, and the Division 3 CO2 Fire Monitoring Panel, with associated equipment has been quarantined for further investigation.
"The Division 3 EDG provides emergency AC electrical power to the High Pressure Core Spray system. This event is being reported as a condition that could have prevented the safety function of structures or systems required to mitigate the consequences of an accident. The Resident Inspector has been notified."
* * * EVENT RETRACTED AT 1324 ON 12/14/06 FROM C. ELBERFELD TO P. SNYDER * * *
"The purpose of this call is to retract Event Number 43021. On December 3, 2006, at 1520 hours, a notification, Event Number 43021, was made to the NRC Operations Center by the Perry Nuclear Power Plant (PNPP) in accordance with 10 CFR 50.72(b)(3)(v)(D) as a condition that at the time of discovery could have prevented the fulfillment of the safety function of a system that is needed to mitigate the consequences of an accident. A spurious Carbon Dioxide (CO2) Fire Protection system initiation signal resulted in a tripped condition for the Division 3 Emergency Diesel Generator (EDG) room ventilation system. Operators declared the Division 3 EDG inoperable and took the appropriate Technical Specification actions. The Division 3 EDG provides emergency AC electrical power to the High Pressure Core Spray system. The High Pressure Core Spray system is a single train safety system.
"After further evaluation, it was determined that operators could promptly restore the ventilation system, with the CO2 initiation signal locked in, if the Division 3 EDG was needed, and that the safety function of the system could still be fulfilled during the time in question. Because the condition reported in Event Number 43021 would not have prevented the fulfillment of the safety function of a system that is needed to mitigate the consequences of an accident, the condition is not reportable, and this notification is retracted. The evaluation (i.e., Reportability Review) for this condition is documented in Condition Report 06-10843.
"The NRC Resident Inspector has been notified."
Notified R3DO (Lara).
Power Reactor
Event Number: 43030
Facility: BEAVER VALLEY
Region: 1 State: PA
Unit: [1] [] []
RX Type: [1] W-3-LP,[2] W-3-LP
NRC Notified By: RONALD T. GREEN
HQ OPS Officer: PETE SNYDER
Region: 1 State: PA
Unit: [1] [] []
RX Type: [1] W-3-LP,[2] W-3-LP
NRC Notified By: RONALD T. GREEN
HQ OPS Officer: PETE SNYDER
Notification Date: 12/05/2006
Notification Time: 11:04 [ET]
Event Date: 12/03/2006
Event Time: 18:04 [EST]
Last Update Date: 12/05/2006
Notification Time: 11:04 [ET]
Event Date: 12/03/2006
Event Time: 18:04 [EST]
Last Update Date: 12/05/2006
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(3)(xiii) - LOSS COMM/ASMT/RESPONSE
10 CFR Section:
50.72(b)(3)(xiii) - LOSS COMM/ASMT/RESPONSE
Person (Organization):
MARVIN SYKES (R1)
MARVIN SYKES (R1)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 1 | N | Y | 100 | Power Operation | 100 | Power Operation |
NON-FUNCTIONAL SAFETY PARAMETER DISPLAY SYSTEM
"At 1804 on 12/03/2006, both Safety Parameter Display System (SPDS) displays in the Beaver Valley Power Station (BVPS) Unit 1 control room were identified as not functioning. Initial evaluation indicated that the system would be returned in less than a day. However, subsequent evaluation determined that vendor assistance would be needed to return the system to operation. The vendor is currently performing maintenance, with the system anticipated to be returned to service today (12/05/2006). Thus, this is being reported as a loss of emergency assessment capability pursuant to 10 CFR 50.72(b)(3)(xiii).
"Other BVPS Unit 1 equipment that remain available to adequately address potential emergent events include the Inadequate Core Cooling Monitor (ICCM), the BVPS Unit 1 Plant Computer and the Control Room alarm system."
The licensee notified the NRC Resident Inspector.
* * * UPDATE FROM RONALD T. GREEN TO JOE O'HARA AT 1449 ON 12/5/06 * * *
" At 1401 on 12/05/2006, the Safety Parameter Display System (SPDS) was repaired and returned to service at Beaver Valley Power Station (BVPS) Unit 1."
The licensee notified the NRC Resident Inspector.
Notified R1DO (M. Sykes)
"At 1804 on 12/03/2006, both Safety Parameter Display System (SPDS) displays in the Beaver Valley Power Station (BVPS) Unit 1 control room were identified as not functioning. Initial evaluation indicated that the system would be returned in less than a day. However, subsequent evaluation determined that vendor assistance would be needed to return the system to operation. The vendor is currently performing maintenance, with the system anticipated to be returned to service today (12/05/2006). Thus, this is being reported as a loss of emergency assessment capability pursuant to 10 CFR 50.72(b)(3)(xiii).
"Other BVPS Unit 1 equipment that remain available to adequately address potential emergent events include the Inadequate Core Cooling Monitor (ICCM), the BVPS Unit 1 Plant Computer and the Control Room alarm system."
The licensee notified the NRC Resident Inspector.
* * * UPDATE FROM RONALD T. GREEN TO JOE O'HARA AT 1449 ON 12/5/06 * * *
" At 1401 on 12/05/2006, the Safety Parameter Display System (SPDS) was repaired and returned to service at Beaver Valley Power Station (BVPS) Unit 1."
The licensee notified the NRC Resident Inspector.
Notified R1DO (M. Sykes)