Skip to main content

Event Notification Report for July 29, 2006

U.S. Nuclear Regulatory Commission
Operations Center

EVENT REPORTS FOR
07/28/2006 - 07/29/2006

EVENT NUMBERS
42738

Power Reactor
Event Number: 42738
Facility: FERMI
Region: 3     State: MI
Unit: [2] [] []
RX Type: [2] GE-4
NRC Notified By: JIM KONRAD
HQ OPS Officer: MIKE RIPLEY
Notification Date: 07/29/2006
Notification Time: 19:19 [ET]
Event Date: 07/29/2006
Event Time: 15:50 [EDT]
Last Update Date: 07/31/2006
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(iv)(B) - RPS ACTUATION - CRITICAL 50.72(b)(3)(iv)(A) - VALID SPECIF SYS ACTUATION
Person (Organization):
ANNE MARIE STONE (R3)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
2 A/R Y 100 Power Operation 0 Hot Shutdown
Event Text
REACTOR SCRAM AND ECCS INJECTION DUE TO LOSS OF FEEDWATER

"At 15:50 EDT on 7/29/06, a Level 3 reactor scram occurred due to a loss of feedwater. The loss of feedwater was caused by a loss of Division 1 electrical power. All control rods fully inserted into the core. The lowest reactor vessel water level reached was 110 inches. HPCI and RCIC auto initiated on Level 2 and injected into the reactor pressure vessel. The Division 1 Emergency Diesel Generators auto initiated and supplied the Division 1 ESF buses. Level 3 and Level 2 isolations occurred as expected. Reactor water level is now being controlled in the normal water level band using Standby Feedwater. No SRVs lifted and RPV pressure is being controlled by the Turbine Pressure Regulator with the main condenser available as the heat sink.

"At the time of the scram, work was being performed on the 120kV mat which resulted in a loss of Bus 101.

"Group 13 (Drywell Sumps) isolated on Reactor Water Level 3. Group 10 (Reactor Water Cleanup Inboard), Group 11 (Reactor Water Cleanup Outboard), Group 12 (Torus Water Management System), Group 17 ( Reactor Recirc Pump Seals and Primary Containment Radiation Monitoring), and Group 18 (Primary Containment Pneumatic Supply) isolated on Reactor Water Level 2."

The licensee notified the NRC Resident Inspector. The licensee stated that HPCI injected for 2 minutes and was then secured as Standby Feedwater was started. At the time of the notification, Bus 101 had been re-energized, and preparations were being made to restore normal power to the Division 1 buses and return the Emergency Diesel Generators to standby. The licensee is investigating the exact cause of the loss of power.

* * * UPDATE FROM R. JOHNSON TO M. RIPLEY 1821 EDT 07/31/06 * * *

"The purpose of this report is to update the information provided at 19:19 ET on 7/29/2006.

"This event was originally reported under reporting criteria 50.72(b)(2)(iv)(A) as an ECCS injection. It has subsequently been determined that both the HPCI and RCIC systems auto-started in response to a reactor low water level 2 (Level 2) injection signal, however, only the RCIC system injected into the vessel. The Level 2 signal was only present for about 2.7 seconds until reactor water level recovered above Level 2. The HPCI injection logic is such that the Level 2 signal must be present until HPCI startup has completed. This includes time for the hydraulic pressure from the HPCI Auxiliary Oil Pump to develop enough pressure to open the HPCI turbine steam isolation valve (E4100F067) and time to stroke open the motor operated HPCI turbine steam isolation valve (E4100F001). It took about 12 seconds before steam was admitted to the HPCI turbine. Thus, the HPCI main pump outlet valve (E4150F006) did not open due to the short duration of the Level 2 signal. This is consistent with the HPCI system design. Therefore the event was not reportable as an event that resulted in or should have resulted in an ECCS injection into the reactor vessel. The event remains reportable under criteria 50.72(b)(2)(iv)(B) and 50.72(b)(3)(iv)(A).

"Additional clarification of the cause of the scram is also provided. The loss of bus 101 resulted in the loss of power to the operating south reactor feed pump (SRFP) turbine lube oil pump resulting in a loss of feedwater flow from the SRFP. The north reactor feed pump continued to operate. The plant is designed with an automatic runback of the recirculation system to allow continued operation following the loss of a single feed pump. However, the loss of bus 101 also resulted in the locking of the reactor recirculation pump speeds (scoop tube lock), disabling the runback feature. This led to a reactor scram on reactor low water level 3 (Level 3) since a single feed pump is not able to maintain reactor water level at 100% power operation. When south reactor feed pump lubrication pressure recovered, feedwater flow from the SRFP recovered. Recovering feedwater injection from the SRFP following the scram caused a rapid increase in reactor water level and a high reactor water level 8 (Level 8) shutdown of the HPCI, RCIC and reactor feedwater pumps. The standby feedwater system was subsequently started and used to maintain reactor level.

"The plant is restarting, and is in Mode 2 with reactor temperature at approximately 508°F and reactor pressure at approximately 817 psi at the time of this report."

Based on this update, ECCS injection was removed from CFR Section of the report. The licensee notified the NRC Resident Inspector. Notified R3 DO (K. O'Brien)