Event Number: 42685
Facility: DRESDEN
Region: 3 State: IL
Unit: [] [2] []
RX Type: [1] GE-1,[2] GE-3,[3] GE-3
NRC Notified By: PAUL SALGADO
HQ OPS Officer: BILL HUFFMAN
Region: 3 State: IL
Unit: [] [2] []
RX Type: [1] GE-1,[2] GE-3,[3] GE-3
NRC Notified By: PAUL SALGADO
HQ OPS Officer: BILL HUFFMAN
Notification Date: 07/04/2006
Notification Time: 05:21 [ET]
Event Date: 07/04/2006
Event Time: 02:59 [CDT]
Last Update Date: 07/04/2006
Notification Time: 05:21 [ET]
Event Date: 07/04/2006
Event Time: 02:59 [CDT]
Last Update Date: 07/04/2006
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(iv)(B) - RPS ACTUATION - CRITICAL 50.72(b)(3)(iv)(A) - VALID SPECIF SYS ACTUATION
10 CFR Section:
50.72(b)(2)(iv)(B) - RPS ACTUATION - CRITICAL 50.72(b)(3)(iv)(A) - VALID SPECIF SYS ACTUATION
Person (Organization):
KENNETH RIEMER (R3)
KENNETH RIEMER (R3)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 2 | A/R | Y | 98 | Power Operation | 0 | Hot Shutdown |
REACTOR SCRAM ON GROUP 1 ISOLATION
"On 7/04/06 at approximately 0259, Unit 2 received a Group 1 isolation on Main Steam Line High Flow. All Group 1 valves closed as required and the reactor scrammed. The Isolation Condenser was manually initiated to control reactor pressure. Group 2 and 3 Containment Isolations occurred as expected. Investigation into the cause of the Group 1 isolation is in progress. All systems responded as required with no abnormalities noted."
All rods fully inserted. Water level is being maintained with normal feed and reactor heat removal and pressure control is being controlled via the isolation condenser within normal range. The licensee was in no significant tech spec LCO at the time of the event and all safety related equipment was available if needed. The scram had no impact on Unit 3 operation. The licensee stated that there was no evidence of any main steam system leak or actual condition that could account for the main steam high flow signal.
The licensee notified the NRC Resident Inspector. The licensee also notified the State Inspector.
"On 7/04/06 at approximately 0259, Unit 2 received a Group 1 isolation on Main Steam Line High Flow. All Group 1 valves closed as required and the reactor scrammed. The Isolation Condenser was manually initiated to control reactor pressure. Group 2 and 3 Containment Isolations occurred as expected. Investigation into the cause of the Group 1 isolation is in progress. All systems responded as required with no abnormalities noted."
All rods fully inserted. Water level is being maintained with normal feed and reactor heat removal and pressure control is being controlled via the isolation condenser within normal range. The licensee was in no significant tech spec LCO at the time of the event and all safety related equipment was available if needed. The scram had no impact on Unit 3 operation. The licensee stated that there was no evidence of any main steam system leak or actual condition that could account for the main steam high flow signal.
The licensee notified the NRC Resident Inspector. The licensee also notified the State Inspector.