Skip to main content

Event Notification Report for February 05, 2006

U.S. Nuclear Regulatory Commission
Operations Center

EVENT REPORTS FOR
02/04/2006 - 02/05/2006

EVENT NUMBERS
4231142312

Power Reactor
Event Number: 42311
Facility: CLINTON
Region: 3     State: IL
Unit: [1] [] []
RX Type: [1] GE-6
NRC Notified By: KEN LEFFEL
HQ OPS Officer: BILL HUFFMAN
Notification Date: 02/05/2006
Notification Time: 14:56 [ET]
Event Date: 02/05/2006
Event Time: 10:25 [CST]
Last Update Date: 02/06/2006
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(3)(xiii) - LOSS COMM/ASMT/RESPONSE
Person (Organization):
JULIO LARA (R3)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
1 N N 0 Refueling 0 Refueling
Event Text
LOSS OF SPDS FOR GREATER THAN 8 HOURS

"On February 5, 2006 at 0225 hours, the Clinton Power Station shutdown the Plant Process Computer in preparation for transferring Uninterruptible Power Supply (UPS) 1A to its alternate source to make preps for the upcoming DC MCC 1E outage. This caused the loss of the Safety Parameter Display System (SPDS). The computer would not restart following the power supply transfer.

"This event is reportable due to the major loss of emergency assessment capability per 10CFR50.72(b)(3)(xiii) (when the SPDS has been unavailable for 8 hours or greater). The cause of the failure of the computer is not known at this time.

"The NRC Resident Inspector has been notified."

* * * UPDATE FROM LEFFEL TO HUFFMAN AT 1318 ON 2/6/06 * * *

"Repairs to the plant process computer were completed at 0810 hours on 2/6/06. The SPDS has been fully restored."

The licensee notified the NRC Resident Inspector. R3DO (Lanksbury) notified.


Power Reactor
Event Number: 42312
Facility: PRAIRIE ISLAND
Region: 3     State: MN
Unit: [] [2] []
RX Type: [1] W-2-LP,[2] W-2-LP
NRC Notified By: STEVE SCHMIDT
HQ OPS Officer: ARLON COSTA
Notification Date: 02/05/2006
Notification Time: 14:59 [ET]
Event Date: 02/05/2006
Event Time: 13:36 [CST]
Last Update Date: 02/05/2006
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(i) - PLANT S/D REQD BY TS
Person (Organization):
JULIO LARA (R3)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
2 N Y 100 Power Operation 100 Power Operation
Event Text
REQUIRED T.S. SHUTDOWN DUE TO EMERGENCY DIESEL GENERATOR INOPERABILITY

"Unit 2 Train B emergency diesel generator D6 was removed from service at 2010 CST on 1/29/06 for planned maintenance and Technical Specification (TS) 3.8.1, 'AC Source - Operating,' Condition B, 'One DG inoperable,' was entered. TS Required Action 3.8.1.B.4 requires D6 be restored to operable status with a Completion Time of 7 days. The planned maintenance activities included replacing two sets of two pistons, rings and cylinder liners on Engine 2 of D6 (D6 is a tandem-engine diesel generator). Return-to-service testing was initiated on 2/4/06 and at approximately 0000 CST; the test was halted due to high-indicated crankcase pressure on Engine 1. The test procedure specifies shutting down the diesel generator if crankcase pressure on either engine exceeds 30mm for more than a few minutes (the setpoint for the crankcase pressure trip is 52 mm).

"Investigation of the cause of the high-indicated crankcase pressure on Engine 1 started immediately. Unit 2 Train A emergency diesel generator (D5) was demonstrated operable by completing a surveillance test at 1507 CST on 2/4/06. Evaluation of the scope of work to return D6 to operable status and the schedule for completing the work indicated that repairs could not be completed within the remainder of the 7-day Completion Time. Based on this assessment an orderly shutdown of Unit 2 is being performed.

"Shutdown [to mode 5] of Unit 2 commenced at 1336 CST on 2/5/06. Unit 2 shutdown will continue until D6 is restored to operable status."

The licensee notified the NRC Resident Inspector.