Event Number: 40960
Facility: CATAWBA
Region: 2 State: SC
Unit: [1] [2] []
RX Type: [1] W-4-LP,[2] W-4-LP
NRC Notified By: JIMMY BURGESS
HQ OPS Officer: BILL GOTT
Region: 2 State: SC
Unit: [1] [2] []
RX Type: [1] W-4-LP,[2] W-4-LP
NRC Notified By: JIMMY BURGESS
HQ OPS Officer: BILL GOTT
Notification Date: 08/16/2004
Notification Time: 12:18 [ET]
Event Date: 08/16/2004
Event Time: 10:28 [EDT]
Last Update Date: 08/16/2004
Notification Time: 12:18 [ET]
Event Date: 08/16/2004
Event Time: 10:28 [EDT]
Last Update Date: 08/16/2004
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(xi) - OFFSITE NOTIFICATION
10 CFR Section:
50.72(b)(2)(xi) - OFFSITE NOTIFICATION
Person (Organization):
CAUDLE JULIAN (R2)
CAUDLE JULIAN (R2)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 1 | N | Y | 100 | Power Operation | 100 | Power Operation |
| 2 | N | Y | 100 | Power Operation | 100 | Power Operation |
TRANSFER EMPLOYEE OFFSITE DUE TO ELECTRICAL SHOCK
An employee received an electrical shock while working on temporary power on the north side of the unit 2 turbine building. He was transported to the Carolina Medical Center.
The licensee notified the NRC Resident Inspector.
An employee received an electrical shock while working on temporary power on the north side of the unit 2 turbine building. He was transported to the Carolina Medical Center.
The licensee notified the NRC Resident Inspector.
General Information or Other
Event Number: 40962
Rep Org: GENERAL ELECTRIC NUCLEAR ENERGY
Licensee: GENERAL ELECTRIC NUCLEAR ENERGY
Region: 1
City: WILMINGTON State: NC
County:
License #:
Agreement: Y
Docket:
NRC Notified By: JASON S. POST
HQ OPS Officer: BILL GOTT
Licensee: GENERAL ELECTRIC NUCLEAR ENERGY
Region: 1
City: WILMINGTON State: NC
County:
License #:
Agreement: Y
Docket:
NRC Notified By: JASON S. POST
HQ OPS Officer: BILL GOTT
Notification Date: 08/16/2004
Notification Time: 16:04 [ET]
Event Date: 08/16/2004
Event Time: 16:00 [EDT]
Last Update Date: 10/11/2004
Notification Time: 16:04 [ET]
Event Date: 08/16/2004
Event Time: 16:00 [EDT]
Last Update Date: 10/11/2004
Emergency Class: NON EMERGENCY
10 CFR Section:
21.21 - UNSPECIFIED PARAGRAPH
10 CFR Section:
21.21 - UNSPECIFIED PARAGRAPH
Person (Organization):
TODD JACKSON (R1)
CAUDLE JULIAN (R2)
BRENT CLAYTON (R3)
WILLIAM JONES (R4)
VERN HODGE (NRR)
TODD JACKSON (R1)
CAUDLE JULIAN (R2)
BRENT CLAYTON (R3)
WILLIAM JONES (R4)
VERN HODGE (NRR)
PART 21 60-DAY INTERIM NOTIFICATION: NARROW RANGE WATER LEVEL INSTRUMENT LEVEL 3 TRIP
This letter provides a 10 CFR21(a)(2) 60 - Day Interim Report notification regarding a potential issue with the Level 3 trip from the narrow range water level instruments that initiate reactor scram. A conservative evaluation by GE Nuclear Energy (GENE) has determined that water level instruments may indicate high by as much as 8 inches, should the reactor water level drop below the dryer seal skirt. At issue is whether with the actual water level as much as 8 inches lower than indicated, the top of active fuel (TAF) will be uncovered for the limiting loss of feedwater event due to
1. Actual water level being lower than indicated when the Level 3 trip occurs, or
2. Failure of the Level 3 trip to occur if water level drops below the narrow range instrument variable leg tap prior to reaching the Level 3 trip setpoint.
Because TAF is a Technical Specification Safety Limit, TAF uncovery for a loss of feedwater event would be a Reportable Condition. However, it would not lead to a significant safety hazard due to multiple automatic and passive protection features of a BWR.
GENE has completed analysis for BWR 2/3 plants and determined that this is not a reportable condition (i.e., the TAF safety limit is protected). GENE has not completed the analyses for BWR /4-/6 plants. For these plants, GENE has determined that actual water level being lower than indicated by up to 8 inches when the Level 3 trip occurs does not lead to TAF uncovery. However, for these plants GENE has not determined if water level could drop below the narrow range instrument variable leg tap prior to reaching the Level 3 trip setpoint.
Therefore, this letter is issued as a 60 - Day Interim Notification under 10 CFR21.21(a)(2) to the BWR/4-/6 plants listed in Attachment 1. The potentially affected plants are being concurrently notified of this situation by a GENE Safety Communication letter. GENE is committed to complete the evaluation by October 11, 2004.
Attachment 1 Plants List Below: (Affected Plants - Evaluation incomplete)
Clinton, Brunswick Units 1 & 2, Nine Mile Point Unit 2, Fermi Unit 2, Columbia, Fitzpatrick, Grand Gulf, River Bend, La Salle Units 1&2, Limerick Units 1 & 2, Peach Bottom Units 1 & 2, Perry, Cooper, Duane Arnold, Susquehanna Units 1 & 2, Hope Creek, Hatch Units 1 & 2, Browns Ferry Units 1 (plant is in an extended shutdown),2 & 3.
* * * UPDATE TO HUFFMAN FROM B. BAHN (FOR J POST) AT 16:16 EDT ON 10/11/04 * * *
"GENE has now completed the evaluation and has determined that all BWR/2/3/6 and ABWR plants, and most BWR/4-5 plants are not susceptible to the condition that could result in a failure of the Level 3 trip to occur. These plants are identified as Not Reportable in Attachment 1 [of GENE Part 21 final report to the NRC dated October 11, 2004]. However, for some BWR/4-5 plants, GENE does not have sufficient information to determine if the condition exists that could result in a failure of the Level 3 trip to occur. These plants are notified, as a Transfer of Information under 10CFR21.21(b), as identified in Attachment 1 [of GENE Part 21 final report to the NRC dated October 11, 2004]."
The plants where insufficient information for a final determination have been identified by GENE as Columbia, Susquehanna 1 and 2, Browns Ferry 2 and 3.
Notified R1DO (Barkley), R2DO(Ogle), R3DO (Clayton) and R4DO (Bywater) and NRR (Hodge).
This letter provides a 10 CFR21(a)(2) 60 - Day Interim Report notification regarding a potential issue with the Level 3 trip from the narrow range water level instruments that initiate reactor scram. A conservative evaluation by GE Nuclear Energy (GENE) has determined that water level instruments may indicate high by as much as 8 inches, should the reactor water level drop below the dryer seal skirt. At issue is whether with the actual water level as much as 8 inches lower than indicated, the top of active fuel (TAF) will be uncovered for the limiting loss of feedwater event due to
1. Actual water level being lower than indicated when the Level 3 trip occurs, or
2. Failure of the Level 3 trip to occur if water level drops below the narrow range instrument variable leg tap prior to reaching the Level 3 trip setpoint.
Because TAF is a Technical Specification Safety Limit, TAF uncovery for a loss of feedwater event would be a Reportable Condition. However, it would not lead to a significant safety hazard due to multiple automatic and passive protection features of a BWR.
GENE has completed analysis for BWR 2/3 plants and determined that this is not a reportable condition (i.e., the TAF safety limit is protected). GENE has not completed the analyses for BWR /4-/6 plants. For these plants, GENE has determined that actual water level being lower than indicated by up to 8 inches when the Level 3 trip occurs does not lead to TAF uncovery. However, for these plants GENE has not determined if water level could drop below the narrow range instrument variable leg tap prior to reaching the Level 3 trip setpoint.
Therefore, this letter is issued as a 60 - Day Interim Notification under 10 CFR21.21(a)(2) to the BWR/4-/6 plants listed in Attachment 1. The potentially affected plants are being concurrently notified of this situation by a GENE Safety Communication letter. GENE is committed to complete the evaluation by October 11, 2004.
Attachment 1 Plants List Below: (Affected Plants - Evaluation incomplete)
Clinton, Brunswick Units 1 & 2, Nine Mile Point Unit 2, Fermi Unit 2, Columbia, Fitzpatrick, Grand Gulf, River Bend, La Salle Units 1&2, Limerick Units 1 & 2, Peach Bottom Units 1 & 2, Perry, Cooper, Duane Arnold, Susquehanna Units 1 & 2, Hope Creek, Hatch Units 1 & 2, Browns Ferry Units 1 (plant is in an extended shutdown),2 & 3.
* * * UPDATE TO HUFFMAN FROM B. BAHN (FOR J POST) AT 16:16 EDT ON 10/11/04 * * *
"GENE has now completed the evaluation and has determined that all BWR/2/3/6 and ABWR plants, and most BWR/4-5 plants are not susceptible to the condition that could result in a failure of the Level 3 trip to occur. These plants are identified as Not Reportable in Attachment 1 [of GENE Part 21 final report to the NRC dated October 11, 2004]. However, for some BWR/4-5 plants, GENE does not have sufficient information to determine if the condition exists that could result in a failure of the Level 3 trip to occur. These plants are notified, as a Transfer of Information under 10CFR21.21(b), as identified in Attachment 1 [of GENE Part 21 final report to the NRC dated October 11, 2004]."
The plants where insufficient information for a final determination have been identified by GENE as Columbia, Susquehanna 1 and 2, Browns Ferry 2 and 3.