05/29/2004 - 05/30/2004

EVENT NUMBERS
4078540899

!!!!! THIS EVENT HAS BEEN RETRACTED !!!!!
!!!!! THIS EVENT HAS BEEN RETRACTED !!!!!
Power Reactor
Event Number: 40785
Facility: COLUMBIA GENERATING STATION
Region: 4     State: WA
Unit: [2] [] []
RX Type: [2] GE-5
NRC Notified By: MIKE BRANDON
HQ OPS Officer: MIKE RIPLEY
Notification Date: 05/30/2004
Notification Time: 18:40 [ET]
Event Date: 05/30/2004
Event Time: 11:37 [PDT]
Last Update Date: 06/15/2004
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(3)(v)(D) - ACCIDENT MITIGATION
Person (Organization):
MIKE RUNYAN (R4)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
2 N Y 65 Power Operation 65 Power Operation
Event Text
HIGH PRESSURE CORE SPRAY SYSTEM INOPERABLE

"The High Pressure Core Spray (HPCS) system was declared inoperable due to the pump's failure to meet the flow requirement specified in TS Surveillance Requirement 3.5.1.4. This surveillance is normally performed on a quarterly basis in accordance with the plant's In-service Testing (IST) Program. The flow values measured during the performance of this surveillance were below both the normal and alert ranges. This test had also been run on 5/27/04 with results in the alert range; HPCS system instruments had been vented between the two tests to rule out the possibility that the results were due to measurement errors.

"Upon declaring the HPCS pump inoperable, TS 3.5.1 Action B was entered. In accordance with Action B, the Reactor Core Isolation Cooling (RCIC) system was verified to be operable. With the RCIC system verified operable, Action B provides a 14-day completion time to restore HPCS to an operable status.

"All other Emergency Core Cooling Systems (ECCS) were operable during this event. This event is being reported as an event or condition that could have prevented the fulfillment of a safety function credited for mitigating the consequences of an accident. The HPCS system is a single train system at Columbia."

The licensee notified the NRC Resident Inspector.

* * * UPDATE ON 06/14/04 @1752 BY MIKE BRANDON TO C. GOULD * * * RETRACTION

On May 30, 2004, Energy Northwest provided an 8-hour notification pursuant to 10 CFR50.72(b)(3)(v)(D). This notification reported the apparent failure of the High Pressure Core Spray (HPCS) system's pump to meet the flow requirements of Surveillance Requirement (SR) 3.5.1.4. Upon the apparent failure to satisfy this SR, Energy Northwest entered Action B of Technical Specification (TS) 3.5.1 (14 day completion time) and initiated actions to investigate the cause of this apparent failure.

This investigation determined the cause of this apparent failure was due to an anomaly in the processing of the pressure and flow input signals and the instrumentation used for documenting the results of the surveillance. Additional testing using alternative instrumentation determined the HPCS pump was fully capable of providing flow within the existing acceptance criteria of the plant's In-service Testing (IST) Program and thus capable of satisfying the SR.

This investigation determined that no actual degradation of the pump existed that would have caused a valid failure of the SR. This was an instrumentation issue only. The HPCS system would have been capable of performing its specified safety function in the as-found condition and was capable of fully satisfying the SR. Therefore, this condition would not have prevented the fulfillment of a safety function and is therefore not reportable under 10CFR50.72.

The HPCS system was declared OPERABLE on June 03, 2004 at 22:59 PDT.

The NRC Resident Inspector was notified.


Power Reactor
Event Number: 40899
Facility: FERMI
Region: 3     State: MI
Unit: [2] [] []
RX Type: [2] GE-4
NRC Notified By: JEFF YEAGER
HQ OPS Officer: STEVE SANDIN
Notification Date: 07/27/2004
Notification Time: 14:37 [ET]
Event Date: 05/30/2004
Event Time: 10:40 [EDT]
Last Update Date: 07/27/2004
Emergency Class: NON EMERGENCY
10 CFR Section:
50.73(a)(1) - INVALID SPECIF SYSTEM ACTUATION
Person (Organization):
JOHN MADERA (R3)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
2 N Y 100 Power Operation 100 Power Operation
Event Text
INVALID ACTUATION OF CONTAINMENT ISOLATION VALVES DUE TO PARTIAL LOSS OF 120 VAC MODULAR POWER UNIT 2 LOADS

"This 60-day optional verbal report, as allowed by 10 CFR 50.73(a)(1), is being made to describe an unplanned, invalid actuation of specified systems, specifically the Primary Containment Isolation System. Since this event meets the definition of an invalid actuation, this notification is being made in accordance with 10CFR50.73(a)(2)(iv)(A) in lieu of a Licensee Event Report.

"On May 30, 2004, at approximately 10:40 am EDT, while the plant was operating at 100% power, a voltage regulator failed on Division 2 120 VAC Modular Power Unit No. 2 (MPU-2) which resulted in blown fuses and the loss of a number of loads from one of the three MPU-2 distribution cabinets. Since only one of the three distribution cabinets was lost, the isolations that occurred were only a portion of the isolations that would have occurred if all of the MPU-2 loads had been lost.

"This caused containment isolations by Division 2 Drywell Pneumatic supply valves (Primary Containment Isolation Group 18) and by Torus Water Management system outboard isolation valves (Primary Containment Isolation Group 12). Division 2 Secondary Containment Isolation Logic was also actuated, and the reactor building ventilation isolated. The Division 2 Standby Gas Treatment System automatically started. All equipment controlled by the affected circuits was determined to have responded to the loss of MPU-2 Cabinet 2 power as expected.

"Operators implemented applicable response procedures. The MPU was returned to service, and isolation signals were reset. Reactor power was not affected by this event.

"The NRC Resident Inspector was notified of this event by the licensee."