Event Notification Report for March 22, 2004

U.S. Nuclear Regulatory Commission
Operations Center

EVENT REPORTS FOR
03/21/2004 - 03/22/2004

EVENT NUMBERS
40604

Power Reactor
Event Number: 40604
Facility: CLINTON
Region: 3     State: IL
Unit: [1] [] []
RX Type: [1] GE-6
NRC Notified By: EDWARD BECK
HQ OPS Officer: CHAUNCEY GOULD
Notification Date: 03/22/2004
Notification Time: 23:00 [ET]
Event Date: 03/22/2004
Event Time: 19:31 [CST]
Last Update Date: 03/22/2004
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(iv)(B) - RPS ACTUATION - CRITICAL
Person (Organization):
KENNETH O'BRIEN (R3)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
1 A/R Y 93 Power Operation 0 Hot Shutdown
Event Text
REACTOR SCRAM FROM 93% POWER DUE TO GENERATOR TRIP

"The plant had a reactor SCRAM, cause is under investigation with initial indications of a Main Generator over voltage alarm and Generator lockout #2 were indicated on the Generator first hit panel. All plant systems responded as expected to the generator trip and Reactor SCRAM. All rods fully inserted and no ECCS actuations or relief valves lifted. The plant is stable in Mode 3 with the recovery plan being implemented."

The NRC Resident Inspector was notified.