Skip to main content

Event Notification Report for March 09, 2004

U.S. Nuclear Regulatory Commission
Operations Center

EVENT REPORTS FOR
03/08/2004 - 03/09/2004

EVENT NUMBERS
40581405824057740697

General Information or Other
Event Number: 40581
Rep Org: MARYLAND DEPT OF THE ENVIRONMENT
Licensee: INDEPENDENT CONSULTANTS AND ENGINEERING
Region: 1
City: FRIENDLY   State: MD
County: PRINCE GEORGES
License #: MD-33-154-01
Agreement: Y
Docket:
NRC Notified By: BOB NELSON
HQ OPS Officer: BILL GOTT
Notification Date: 03/10/2004
Notification Time: 15:10 [ET]
Event Date: 03/09/2004
Event Time: 14:00 [EST]
Last Update Date: 03/10/2004
Emergency Class: NON EMERGENCY
10 CFR Section:
Person (Organization):
EUGENE COBEY (R1)
FRED BROWN (NMSS)
Event Text
AGREEMENT STATE REPORT - DAMAGED MOISTURE DENSITY GAUGE

A dump truck ran over a Campbell Pacific Nuclear moisture density gauge at 1400 EST on 3/9/10 in Friendly, MD. The gauge had a 10 millicuries Cs-137 and 40 millicuries Am-241:Be source, serial number AM7147. The sources were intact and were packaged and shipped back to the licensee, Independent Consultants and Engineers of Upper Marlboro, MD. There was no detected leakage. The Gauge serial number is MD-30907147.


General Information or Other
Event Number: 40582
Rep Org: ILLINOIS EMERGENCY MGMT. AGENCY
Licensee: LOYOLA UNIVERSITY OF CHICAGO
Region: 3
City: CHICAGO   State: IL
County:
License #: IL-01695-01
Agreement: Y
Docket:
NRC Notified By: JOE KLINGER
HQ OPS Officer: BILL GOTT
Notification Date: 03/10/2004
Notification Time: 18:32 [ET]
Event Date: 03/09/2004
Event Time: 00:00 [CST]
Last Update Date: 03/10/2004
Emergency Class: NON EMERGENCY
10 CFR Section:
Person (Organization):
KENNETH RIEMER (R3)
EUGENE COBEY (R1)
JOHN GREEVES (NMSS)
Event Text
AGREEMENT STATE REPORT - REMOVABLE CONTAMINATION ON RECEIVED PACKAGE

"Loyola University of Chicago, a broadscope academic licensee, notified the agency that a package containing two vials of Phosphorous-32 was found to contain levels of removable P-32 contamination in excess of the regulatory limits. The package was received on Friday, March 5, 2004 and surveyed on Tuesday, March 9. 315,000 dpm/100 square centimeters was measured using a pancake probe. A swipe of an area on the exterior surface of the package was found to contain 26,000 dpm/100 square centimeters. This exceeds the maximum allowable level of 22,000 dpm/100 sq centimeters removable contamination. Further examination of the package revealed that contamination was also found on a plastic bag containing an inner container and the vials of liquid P-32 (1 vial contained 500 microcuries, the other 250 microcuries) and on the exterior surface of the inner plastic container. The contamination measured on the items on the interior of the package ranged from a maximum of 4,700 dpm to 120 dpm/ 100 sq centimeters. However, the interior of the inner container and the exterior surfaces of the vials were not contaminated. The consultant performed surveys of the area where the package was opened and no additional contamination was noted. The shipper was Perkin-Elmer, Boston, MA. The carrier was Airborne Express.

"The licensee notified the shipper, Perkin Elmer, and Airborne Express. The Hazmat representative for Airborne Express, contacted the Agency and stated that Airborne Express is currently trying to perform radiation surveys of all ground vehicles and the two planes involved in transport of this package. The package was transferred via Airborne Ground transportation from the Perkin Elmer Boston, MA, facility and transferred to a plane at Boston's airport. It was then flown to the Airborne facility in Wilmington, Ohio. The package was later flown to Chicago O'Hare then transported via Airborne Express Ground vehicle to the Illinois licensee's facility.

"The MA radiation control program also contacted the Illinois radiation control program and discussed this matter. The licensee's consultant is currently conducting additional surveys of the Illinois facility to see if any additional P-32 contamination can be found. The Agency will also perform independent surveys and an investigation to try to determine the source of contamination." Illinois report number IL040012.


Power Reactor
Event Number: 40577
Facility: MAINE YANKEE
Region: 1     State: ME
Unit: [1] [] []
RX Type: [1] CE
NRC Notified By: TERRY VOGEL
HQ OPS Officer: CHAUNCEY GOULD
Notification Date: 03/09/2004
Notification Time: 11:32 [ET]
Event Date: 03/09/2004
Event Time: 09:55 [EST]
Last Update Date: 03/09/2004
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(xi) - OFFSITE NOTIFICATION
Person (Organization):
EUGENE COBEY (R1)
TOM ESSIG (NMSS)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
1 N N 0 Decommissioned 0 Decommissioned
Event Text
OFFSITE NOTIFICATIONS TO STATE AGENCIES DUE TO LIQUID RELEASE

The licensee notified the Maine Emergency Management Agency and the Maine Department of Human Services of an unscheduled liquid release of containing 1.35e-6 Curies that occurred on 3/8/04. This release resulted in a minor exposure of 9e-11millirem.

Site has no resident inspector.


Power Reactor
Event Number: 40697
Facility: COOPER
Region: 4     State: NE
Unit: [1] [] []
RX Type: [1] GE-4
NRC Notified By: COY BLAIR
HQ OPS Officer: BILL GOTT
Notification Date: 04/22/2004
Notification Time: 10:58 [ET]
Event Date: 03/09/2004
Event Time: 12:42 [CST]
Last Update Date: 04/22/2004
Emergency Class: NON EMERGENCY
10 CFR Section:
50.73(a)(1) - INVALID SPECIF SYSTEM ACTUATION
Person (Organization):
RUSSELL BYWATER (R4)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
1 N Y 100 Power Operation 100 Power Operation
Event Text
INVALID SYSTEM ACTUATION DUE TO MOMENTARY POWER INTERRUPTION

This report is being made under 10 CFR 50.73(a)(2)(iv)(A).

Actuations occurred on the following systems (System-Actuation Status)
-Primary Containment (Drywell and Suppression Chamber) Atmospheric Control Isolation Valves - Complete
-Drywell Vent Monitor - Partial
-Off-gas Treatment - Partial
-Secondary Containment - Complete
-Control Room Ventilation - Complete
-Standby Gas Treatment - Complete

System response indicated that the cause was a momentary power interruption to a portion of the Primary Containment Isolation System Division 2 logic. Print verification determined that the system functioned as designed on loss of power.

The Licensee will notify the NRC Resident Inspector.