Event Notification Report for November 19, 2003
U.S. Nuclear Regulatory Commission
Operations Center
EVENT REPORTS FOR
11/18/2003 - 11/19/2003
Power Reactor
Event Number: 40340
Facility: ROBINSON
Region: 2 State: SC
Unit: [2] [] []
RX Type: [2] W-3-LP
NRC Notified By: CHUCK BAUCOM
HQ OPS Officer: JOHN MacKINNON
Region: 2 State: SC
Unit: [2] [] []
RX Type: [2] W-3-LP
NRC Notified By: CHUCK BAUCOM
HQ OPS Officer: JOHN MacKINNON
Notification Date: 11/19/2003
Notification Time: 14:23 [ET]
Event Date: 11/19/2003
Event Time: 13:30 [EST]
Last Update Date: 11/19/2003
Notification Time: 14:23 [ET]
Event Date: 11/19/2003
Event Time: 13:30 [EST]
Last Update Date: 11/19/2003
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(3)(v)(A) - POT UNABLE TO SAFE SD
10 CFR Section:
50.72(b)(3)(v)(A) - POT UNABLE TO SAFE SD
Person (Organization):
DAVID AYRES (R2)
DAVID AYRES (R2)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 2 | N | Y | 100 | Power Operation | 100 | Power Operation |
TWO FAILURE MODES NOT PREVIOUSLY POSTULATED COULD BE INTRODUCED BY A FIRE IN EITHER FIRE ZONE 19 OR FIRE ZONE 20.
"At approximately 1330 hours (EDT) on November 19, 2003, during reviews being conducted on H. B. Robinson Steam Electric Plant (HBRSEP), Unit 2 No. 2, Appendix R fire scenario safe shutdown circuit analysis, it was concluded that two failure modes not previously postulated could be introduced by a fire in either Fire Zone 19, Cable Spreading Room, or Fire Zone 20, Emergency Switchgear Room. The suction source to the charging pump could spuriously close during a fire in one of these zones, which could cause a loss of Reactor Coolant System (RCS) make-up capability of the "A" Charging Pump were operating at the time if the event. The other failure mode involves spurious operation of both pressurizer power operated relief valves (PORVs), which could cause a loss of RCS inventory. Each of these failure modes could result in loss of safe shutdown capability. Therefore, this condition is being reported in accordance with 10 CFR 50.72(b)(3)(v)(A), any event or condition that at the time of discovery could have prevented the fulfillment of the safety function of structures or systems that are required to shut down the reactor and maintain it in safe shutdown condition.
"Short term corrective actions for this situation include procedure changes to establish preemptive actions that will provide reasonable assurance that safe shutdown can be achieved and maintained. The procedure changes will include rapid verification at the onset of a fire scenario that the "A" Charging Pump is not operating, and will direct closure of the pressurizer PORV block valves. Additionally, the Fire Protection Program (FPP) requirements for loss of detection or suppression in these zones were reviewed. The FPP requires establishment of a continuous fire watch in these areas for loss of detection or suppression capability. Additional administrative controls will be implemented or transient combustibles to further reduce the probability of these failure modes occurring.
"Long term corrective actions are being developed via the Corrective Action Program and will be implemented to further reduce the likelihood of these failure modes"
The NRC Resident Inspector was notified of this event by the licensee.
"At approximately 1330 hours (EDT) on November 19, 2003, during reviews being conducted on H. B. Robinson Steam Electric Plant (HBRSEP), Unit 2 No. 2, Appendix R fire scenario safe shutdown circuit analysis, it was concluded that two failure modes not previously postulated could be introduced by a fire in either Fire Zone 19, Cable Spreading Room, or Fire Zone 20, Emergency Switchgear Room. The suction source to the charging pump could spuriously close during a fire in one of these zones, which could cause a loss of Reactor Coolant System (RCS) make-up capability of the "A" Charging Pump were operating at the time if the event. The other failure mode involves spurious operation of both pressurizer power operated relief valves (PORVs), which could cause a loss of RCS inventory. Each of these failure modes could result in loss of safe shutdown capability. Therefore, this condition is being reported in accordance with 10 CFR 50.72(b)(3)(v)(A), any event or condition that at the time of discovery could have prevented the fulfillment of the safety function of structures or systems that are required to shut down the reactor and maintain it in safe shutdown condition.
"Short term corrective actions for this situation include procedure changes to establish preemptive actions that will provide reasonable assurance that safe shutdown can be achieved and maintained. The procedure changes will include rapid verification at the onset of a fire scenario that the "A" Charging Pump is not operating, and will direct closure of the pressurizer PORV block valves. Additionally, the Fire Protection Program (FPP) requirements for loss of detection or suppression in these zones were reviewed. The FPP requires establishment of a continuous fire watch in these areas for loss of detection or suppression capability. Additional administrative controls will be implemented or transient combustibles to further reduce the probability of these failure modes occurring.
"Long term corrective actions are being developed via the Corrective Action Program and will be implemented to further reduce the likelihood of these failure modes"
The NRC Resident Inspector was notified of this event by the licensee.
Other Nuclear Material
Event Number: 40342
Rep Org: CROW BUTTE RESOURCES, INC
Licensee: CROW BUTTE RESOURCES, INC
Region: 4
City: CRAWFORD State: NE
County:
License #: SUA-1534
Agreement: Y
Docket:
NRC Notified By: MIKE GRIFFIN
HQ OPS Officer: MIKE RIPLEY
Licensee: CROW BUTTE RESOURCES, INC
Region: 4
City: CRAWFORD State: NE
County:
License #: SUA-1534
Agreement: Y
Docket:
NRC Notified By: MIKE GRIFFIN
HQ OPS Officer: MIKE RIPLEY
Notification Date: 11/20/2003
Notification Time: 10:16 [ET]
Event Date: 11/19/2003
Event Time: 14:00 [CST]
Last Update Date: 11/20/2003
Notification Time: 10:16 [ET]
Event Date: 11/19/2003
Event Time: 14:00 [CST]
Last Update Date: 11/20/2003
Emergency Class: NON EMERGENCY
10 CFR Section:
40.60(b)(3) - MED TREAT INVOLVING CONTAM
10 CFR Section:
40.60(b)(3) - MED TREAT INVOLVING CONTAM
Person (Organization):
KRISS KENNEDY (R4)
ROBERTO TORRES (NMSS)
KRISS KENNEDY (R4)
ROBERTO TORRES (NMSS)
MEDICAL TREATMENT INVOLVING CONTAMINATION
On 11/19/03, a contract worker at the licensee's facility fell from a ladder breaking his shoulder while working in a contaminated area. The worker was transported to the hospital with the licensee's RSO while wearing his protective clothing. The protective clothing had removable contamination measured at 1380 dpm/100 cm2 (disintegrations per minute per 100 square-centimeters). The employee was released from the hospital and the contaminated clothing was recovered by the licensee.
On 11/19/03, a contract worker at the licensee's facility fell from a ladder breaking his shoulder while working in a contaminated area. The worker was transported to the hospital with the licensee's RSO while wearing his protective clothing. The protective clothing had removable contamination measured at 1380 dpm/100 cm2 (disintegrations per minute per 100 square-centimeters). The employee was released from the hospital and the contaminated clothing was recovered by the licensee.