Event Notification Report for October 19, 2001
U.S. Nuclear Regulatory Commission
Operations Center
EVENT REPORTS FOR
10/18/2001 - 10/19/2001
Other Nuclear Material
Event Number: 38407
Rep Org: EASTERN ISOTOPES INC
Licensee: EASTERN ISOTOPES INC
Region: 2
City: DULLES/STERLING State: VA
County:
License #: 45-25221-01MD
Agreement: N
Docket:
NRC Notified By: KOSTKA
HQ OPS Officer: CHAUNCEY GOULD
Licensee: EASTERN ISOTOPES INC
Region: 2
City: DULLES/STERLING State: VA
County:
License #: 45-25221-01MD
Agreement: N
Docket:
NRC Notified By: KOSTKA
HQ OPS Officer: CHAUNCEY GOULD
Notification Date: 10/19/2001
Notification Time: 16:31 [ET]
Event Date: 10/19/2001
Event Time: 15:19 [EDT]
Last Update Date: 10/19/2001
Notification Time: 16:31 [ET]
Event Date: 10/19/2001
Event Time: 15:19 [EDT]
Last Update Date: 10/19/2001
Emergency Class: NON EMERGENCY
10 CFR Section:
20.2202(a)(1) - PERS OVEREXPOSURE/TEDE >= 25 REM
10 CFR Section:
20.2202(a)(1) - PERS OVEREXPOSURE/TEDE >= 25 REM
Person (Organization):
KEN BARR (REG2)
M. WAYNE HODGES (NMSS)
SUSAN FRANT (NMSS)
KEN BARR (REG2)
M. WAYNE HODGES (NMSS)
SUSAN FRANT (NMSS)
POSSIBLE OVEREXPOSURE TO AN EMPLOYEE'S EXTREMITIES
Eastern Isotopes Inc. was notified by the Landauer Company of Chicago, IL that an employee had a reading from her plastic TLD ring for the month of September of 56,350 millirem. From the first of the year to the end of August she already had 15,570 millirem. The employee works in PET Imaging where the suspected isotope is fluorine-18(F-18). However, for one week in September she was operating their dose drawing robot. Normally the operators of that device get about 10-12 millirem/dose, but she may have gotten up to 110 millirem/dose. They are continuing to investigate to determine if overexposure occurred during that one week period or over the whole month period. They will remove the employee from all duties until the investigation is complete.
The licensee will notify the State of Virginia.
Eastern Isotopes Inc. was notified by the Landauer Company of Chicago, IL that an employee had a reading from her plastic TLD ring for the month of September of 56,350 millirem. From the first of the year to the end of August she already had 15,570 millirem. The employee works in PET Imaging where the suspected isotope is fluorine-18(F-18). However, for one week in September she was operating their dose drawing robot. Normally the operators of that device get about 10-12 millirem/dose, but she may have gotten up to 110 millirem/dose. They are continuing to investigate to determine if overexposure occurred during that one week period or over the whole month period. They will remove the employee from all duties until the investigation is complete.
The licensee will notify the State of Virginia.
Power Reactor
Event Number: 38408
Facility: VERMONT YANKEE
Region: 1 State: VT
Unit: [1] [] []
RX Type: [1] GE-4
NRC Notified By: MICHAEL HAMER
HQ OPS Officer: BOB STRANSKY
Region: 1 State: VT
Unit: [1] [] []
RX Type: [1] GE-4
NRC Notified By: MICHAEL HAMER
HQ OPS Officer: BOB STRANSKY
Notification Date: 10/19/2001
Notification Time: 16:39 [ET]
Event Date: 10/19/2001
Event Time: 00:00 [EDT]
Last Update Date: 10/19/2001
Notification Time: 16:39 [ET]
Event Date: 10/19/2001
Event Time: 00:00 [EDT]
Last Update Date: 10/19/2001
Emergency Class: NON EMERGENCY
10 CFR Section:
21.21 - UNSPECIFIED PARAGRAPH
10 CFR Section:
21.21 - UNSPECIFIED PARAGRAPH
Person (Organization):
R1 IRC TEAM MANAGER (R1)
Vernon Hodge (NRR)
R1 IRC TEAM MANAGER (R1)
Vernon Hodge (NRR)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 1 | N | Y | 100 | Power Operation | 100 | Power Operation |
10 CFR PART 21 REPORT
"During RFO-22, Carboline Carbozine CX-11SG paint primer was applied to the drywell shell (inner wall) to the floor joint as part of a qualified seal design. The purpose of this seal is to provide a moisture barrier to mitigate water entering the shell to concrete interface. In preparation for and during subsequent applications of the primer, significant gelling/premature set-up of the paint was exhibited (ref. ER20011169, dated 5/11/01). Within 24 hours of the paint application, the paint began to lift and blister. This paint was supplied under an Appendix B Vendor QA Program in accordance with VY PO 011040. Failure analysis received from Carboline and an independent test lab indicated the paint was defective. Carboline indicates the failure was most likely due to a moisture problem during manufacture. The problem was with part 'A' of the two-part paint. The impact of the failed paint applied in the drywell during the outage was evaluated under ER 20011169. The seal was then coated with a single coat of Carboline 890. Carboline Corporation has verified this to be an acceptable application until a permanent remedy is achieved."
"During RFO-22, Carboline Carbozine CX-11SG paint primer was applied to the drywell shell (inner wall) to the floor joint as part of a qualified seal design. The purpose of this seal is to provide a moisture barrier to mitigate water entering the shell to concrete interface. In preparation for and during subsequent applications of the primer, significant gelling/premature set-up of the paint was exhibited (ref. ER20011169, dated 5/11/01). Within 24 hours of the paint application, the paint began to lift and blister. This paint was supplied under an Appendix B Vendor QA Program in accordance with VY PO 011040. Failure analysis received from Carboline and an independent test lab indicated the paint was defective. Carboline indicates the failure was most likely due to a moisture problem during manufacture. The problem was with part 'A' of the two-part paint. The impact of the failed paint applied in the drywell during the outage was evaluated under ER 20011169. The seal was then coated with a single coat of Carboline 890. Carboline Corporation has verified this to be an acceptable application until a permanent remedy is achieved."