Power Reactor
Event Number: 37607
Facility: BRAIDWOOD
Region: 3     State: IL
Unit: [1] [2] []
RX Type: [1] W-4-LP,[2] W-4-LP
NRC Notified By: DENNIS HIGINBOTHAM
HQ OPS Officer: FANGIE JONES
Notification Date: 12/16/2000
Notification Time: 13:42 [ET]
Event Date: 12/16/2000
Event Time: 12:03 [CST]
Last Update Date: 12/19/2000
Emergency Class: NON EMERGENCY
10 CFR Section:
73.71(b)(1) - SAFEGUARDS REPORTS
Person (Organization):
RONALD GARDNER (R3)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
1 N Y 100 Power Operation 100 Power Operation
2 N Y 100 Power Operation 100 Power Operation
Event Text
SECURITY REPORT

Safeguard system degradation related to area doors and monitoring. Immediate compensatory measures taken upon discovery. The licensee notified the NRC Resident Inspector.

Refer to HOO Log for additional details.

***** UPDATE AT 1913 EST ON 12/19/00 FROM TERRY D'ORAZIO TO LEIGH TROCINE *****

The licensee is retracting this event notification. The following text is a portion of a facsimile received from the licensee:

"An ENS notification was made on 12/16/00 at 1342 [EST] to report the loss of alarm communication function at the [...]. This report was made pursuant to 10 CFR [Part] 73, Appendix G. The loss was compensated for within 10 minutes of discovery by [...]. After a review of NUREG 1304 and Reg Guide 5.62, [the licensee has] concluded that this event is a loggable occurrence, not a 1-hour reportable event. Therefore, the 12/16/00 notification is being retracted." (Contact the NRC operations officer for additional details.)

The licensee notified the NRC resident inspector. The NRC operations officer notified the R3DO (Kozak).


Power Reactor
Event Number: 37608
Facility: SOUTH TEXAS
Region: 4     State: TX
Unit: [1] [] []
RX Type: [1] W-4-LP,[2] W-4-LP
NRC Notified By: JAMES MERTINK
HQ OPS Officer: BOB STRANSKY
Notification Date: 12/17/2000
Notification Time: 00:57 [ET]
Event Date: 12/16/2000
Event Time: 23:00 [CST]
Last Update Date: 12/18/2000
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(ii) - ESF ACTUATION 50.72(b)(1)(iv) - ECCS INJECTION
Person (Organization):
CHUCK CAIN (R4)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
1 M/R Y 100 Power Operation 0 Hot Standby
Event Text
MANUAL REACTOR TRIP DUE TO CLOSURE OF TURBINE GOVERNOR VALVES

"Unit 1 manually tripped the reactor at 2300 on 12/16/00. The unit was in the process of performing main turbine valve operability testing when all four Governor Valves went closed. The crew manually tripped the reactor and entered emergency operating procedures. Primary pressure continued to lower to the Safety Injection actuation setpoint. All ESF equipment actuated and performed as expected with the exception of one Source Range Nuclear Instrument. The cause of the Safety Injection actuation is not fully understood at this time."

The NRC resident inspector has been informed of this event by the licensee.

***** UPDATE AT 2330 EST ON 12/18/00 FROM JOHN PIERCE TO LEIGH TROCINE *****

The following text is a portion of a facsimile received from the licensee:

"This is a supplemental notification to EVENT #37608 for a [1-hour] report for any event that results or should have resulted in Emergency Core Cooling System (ECCS) discharge into the RCS as a result of a valid signal (10CFR50.72(b)(1)(iv)(B)) and [for a 4-hour] notification [for] RPS actuation and ESF actuation (10CFR50.72(b)(2)(ii))."

"Unit 1 was preparing to [perform] main turbine valve operability testing when all four governor valves went closed. Unit 1 was manually tripped at 2300 [CST] on 12/16/2000, and emergency operating procedures were entered. Safety injection occurred approximately 1 minute and 25 seconds following the reactor trip. All ESF equipment responded normally during the safety injection including initiation of auxiliary feedwater (AFW) flow to the steam generators. RCS pressure lowered to approximately 1470 psig within approximately 6 minutes of safety injection actuation prior to recovering and increasing pressure. Taking manual control to close the pressurizer spray valves, after indicating not fully closed, and throttling AFW flow appeared to stop the pressure decrease. Safety injection termination criteria was met, and the safety injection was terminated by approximately 2348 hours [CST]."

"The highest RCS pressure was 2303 psig. An adequate margin of subcooling was maintained, and the reactor head area indicated it remained water solid during the transient. Maximum pressurizer level during the event was approximately 63.8%. Following termination of the transient, it was noted that RCS temperature did not return to the expected no-load temperature value. Plant walk down found 3 of 12 steam dump valves approximately 10% open which contributed to the initial plant cooldown. These valves were isolated."

"An STP Event Review Team is analyzing plant data to determine the [detailed] sequence of events and cause of event."

The licensee notified the NRC resident inspector. The NRC operations officer notified the R4DO (Bill Jones).