Event Notification Report for September 01, 2000

U.S. Nuclear Regulatory Commission
Operations Center

EVENT REPORTS FOR
08/31/2000 - 09/01/2000

EVENT NUMBERS
37283372843728537328

Power Reactor
Event Number: 37283
Facility: HATCH
Region: 2     State: GA
Unit: [1] [] []
RX Type: [1] GE-4,[2] GE-4
NRC Notified By: UNDERWOOD
HQ OPS Officer: CHAUNCEY GOULD
Notification Date: 09/01/2000
Notification Time: 12:20 [ET]
Event Date: 09/01/2000
Event Time: 11:30 [EDT]
Last Update Date: 09/01/2000
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(ii) - ESF ACTUATION
Person (Organization):
CAUDLE JULIAN (R2)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
1 N Y 100 Power Operation 100 Power Operation
Event Text
PLANT HAD CLOSURE OF THE POST ACCIDENT SAMPLING SYSTEM INBOARD PRIMARY CONTAINMENT ISOLATION VALVE

During performance of Reactor Building Isolation LSFT (34SV-SUV-027-1S), 1E41-F122, Post Accident Sampling System Inboard PCIV, failed closed between approximately 1145 and 1230 on 08/31/00. 1E41-H22 was verified to be open at approximately 1145 following completion of channel A performance test (section 7.2). After returning from lunch break, operators observed 1E41-F122 closed and could not be reopened with control switch.

The isolation has not been reset and they have also isolated the outboard valve by TS requirement. Investigation into cause of closure is continuing.

During discussions with Nuclear Safety and Compliance Department at 1130 on 09/01/00 it was determined that this PCIV failing closed was a reportable ESF actuation.


The NRC Resident Inspector will be notified.


Power Reactor
Event Number: 37284
Facility: LASALLE
Region: 3     State: IL
Unit: [] [2] []
RX Type: [1] GE-5,[2] GE-5
NRC Notified By: HOPMAN
HQ OPS Officer: CHAUNCEY GOULD
Notification Date: 09/01/2000
Notification Time: 18:49 [ET]
Event Date: 09/01/2000
Event Time: 14:19 [CDT]
Last Update Date: 09/01/2000
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(ii) - ESF ACTUATION
Person (Organization):
MELVYN LEACH (R3)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
2 N Y 100 Power Operation 100 Power Operation
Event Text
REACTOR CORE ISOLATION COOLING SYSTEM RECEIVED AN ISOLATION SIGNAL DURING MAINTENANCE.

Unit 2 was operating at 100% power. The Reactor Core Isolation Cooling System was removed from service for scheduled maintenance. Following valve packing adjustment, the Reactor Core Isolation Cooling system steam supply outboard isolation valve was opened per approved procedure. Approximately 10 seconds after the Reactor Core Isolation Cooling system steam inboard isolation bypass valve was throttled open for warming. "Division 2 Reactor Core isolation Cooling system steam line DP hi" and "Reactor Core Isolation Cooling system Steam Line/Turbine isolation" alarms were received. The Reactor Core Isolation Cooling system steam inboard isolation bypass valve automatically closed due to an isolation signal. The Reactor Core Isolation Cooling system remains isolated by the inboard isolation valves. The cause of the isolation signal is unknown at this time. An investigation is in progress to determine the cause of the isolation and initiate actions to restore the Reactor Core Isolation Cooling system to an operable and available status and exit the LCO action statement.

The NRC Resident Inspector was notified.


!!!!! THIS EVENT HAS BEEN RETRACTED !!!!!
!!!!! THIS EVENT HAS BEEN RETRACTED !!!!!
Power Reactor
Event Number: 37285
Facility: PILGRIM
Region: 1     State: MA
Unit: [1] [] []
RX Type: [1] GE-3
NRC Notified By: MCDONNELL
HQ OPS Officer: CHAUNCEY GOULD
Notification Date: 09/01/2000
Notification Time: 21:08 [ET]
Event Date: 09/01/2000
Event Time: 19:40 [EDT]
Last Update Date: 10/12/2000
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(iii)(B) - POT RHR INOP
Person (Organization):
PETE ESELGROTH (R1)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
1 N Y 100 Power Operation 100 Power Operation
Event Text
HIGH PRESSURE COOLANT INJECTION DECLARED INOPERABLE PLACING THE PLANT IN A 14 DAY LCO ACTION STATEMENT.

During the performance of 8.5.4.1 (HPCI operability test), HPCI failed to meet acceptance criteria. The HPCI pump failed to meet the required flow, pressure and rpm requirements. Troubleshooting of the problem is in progress to make HPCI operable within the 14 day LCO action statement requirement.

The NRC Resident Inspector was informed.


* * * UPDATE ON 10/12/00 @ 1736 BY OLSON TO GOULD * * * RETRACTION

After further analysis of this event, it was determined HPCI would have performed its safety function, therefore, this event is not reportable and is being retracted.

The NRC Resident Inspector was notified.
Region 1 RDO(Doerflein) was informed.


General Information or Other
Event Number: 37328
Rep Org: WA DIVISION OF RADIATION PROTECTION
Licensee: WASHINGTON STATE UNIVERSITY
Region: 4
City: PULLMAN   State: WA
County:
License #: WA-C003-1
Agreement: Y
Docket:
NRC Notified By: TERRY FRAZEE
HQ OPS Officer: JOHN MacKINNON
Notification Date: 09/15/2000
Notification Time: 15:38 [ET]
Event Date: 09/01/2000
Event Time: 00:00 [PDT]
Last Update Date: 09/15/2000
Emergency Class: NON EMERGENCY
10 CFR Section:
Person (Organization):
GARY SANBORN (R4)
LARRY CAMPER (NMSS)
Event Text
LEAKING SOURCE, SODIUM-22, DISCOVERED DURING LEAK TEST.

THE FOLLOWING EVENT WAS EVENT WAS E-MAILED TO THE HEADQUARTERS OPERATION CENTER

Washington State University located in Pullman, WA Radiation Safety Officer performed a leak test on a 1.5 millicurie sodium-22 source that was planned to be transferred from one authorized user to another. The source was found to be leaking and will be disposed. Surveys of the storage area and work area were done and decontamination performed on the remote handling tools. The source is one of four custom made by a researcher at Brookhaven National Lab in June 1996 and transferred to Washington State University (WSU) when the researcher moved to WSU. Of the four sources, one was found to be leaking and disposed of several years ago, one is still at WSU, and the last was transferred to another academic institution (WSU has notified the recipient of this event).

Leak test? 0.027 microcuries of removable contamination detected.

Activity and isotope involved: 1.5 millicuries of Na-22 as of June 1996.