Event Notification Report for April 22, 2000
U.S. Nuclear Regulatory Commission
Operations Center
EVENT REPORTS FOR
04/21/2000 - 04/22/2000
Power Reactor
Event Number: 36917
Facility: KEWAUNEE
Region: 3 State: WI
Unit: [1] [] []
RX Type: [1] W-2-LP
NRC Notified By: ROY SCOTT
HQ OPS Officer: FANGIE JONES
Region: 3 State: WI
Unit: [1] [] []
RX Type: [1] W-2-LP
NRC Notified By: ROY SCOTT
HQ OPS Officer: FANGIE JONES
Notification Date: 04/22/2000
Notification Time: 11:08 [ET]
Event Date: 04/22/2000
Event Time: 08:03 [CDT]
Last Update Date: 04/22/2000
Notification Time: 11:08 [ET]
Event Date: 04/22/2000
Event Time: 08:03 [CDT]
Last Update Date: 04/22/2000
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(i) - DEG/UNANALYZED COND
10 CFR Section:
50.72(b)(2)(i) - DEG/UNANALYZED COND
Person (Organization):
MARK RING (R3)
MARK RING (R3)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 1 | N | N | 0 | Intermediate Shutdown | 0 | Intermediate Shutdown |
MAIN STEAM ISOLATION VALVE FAILED TIMING TEST
The licensee determined that the 'B' steam generator main steam isolation valve shut in 6 seconds during testing. The requirement is 5 seconds in the surveillance test of technical specifications and in the Updated Safety Analysis Report. The plant will remain shutdown until repairs and testing are complete.
The licensee notified the NRC Resident Inspector.
The licensee determined that the 'B' steam generator main steam isolation valve shut in 6 seconds during testing. The requirement is 5 seconds in the surveillance test of technical specifications and in the Updated Safety Analysis Report. The plant will remain shutdown until repairs and testing are complete.
The licensee notified the NRC Resident Inspector.
Power Reactor
Event Number: 36918
Facility: NINE MILE POINT
Region: 1 State: NY
Unit: [] [2] []
RX Type: [1] GE-2,[2] GE-5
NRC Notified By: STEVE FREGEAU
HQ OPS Officer: DICK JOLLIFFE
Region: 1 State: NY
Unit: [] [2] []
RX Type: [1] GE-2,[2] GE-5
NRC Notified By: STEVE FREGEAU
HQ OPS Officer: DICK JOLLIFFE
Notification Date: 04/22/2000
Notification Time: 16:19 [ET]
Event Date: 04/22/2000
Event Time: 15:06 [EDT]
Last Update Date: 04/22/2000
Notification Time: 16:19 [ET]
Event Date: 04/22/2000
Event Time: 15:06 [EDT]
Last Update Date: 04/22/2000
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(v) - OFFSITE MEDICAL
10 CFR Section:
50.72(b)(2)(v) - OFFSITE MEDICAL
Person (Organization):
JOHN WHITE (R1)
JOHN WHITE (R1)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 2 | N | Y | 54 | Power Operation | 54 | Power Operation |
- POTENTIALLY CONTAMINATED PLANT EMPLOYEE TRANSPORTED TO OFFSITE HOSPITAL -
A potentially contaminated plant employee who sustained a broken leg onsite, was transported offsite to Oswego hospital for treatment accompanied by a plant radiation technician.
The licensee plans to notify the NRC Resident Inspector.
* * * UPDATE AT 1712 ON 04/22/00 BY STEVE FREGEAU TO JOLLIFFE * * *
The plant radiation technician determined that the plant employee was not contaminated.
The licensee plans to notify the NRC Resident Inspector.
The NRC Operations Officer notified the R1DO John White.
A potentially contaminated plant employee who sustained a broken leg onsite, was transported offsite to Oswego hospital for treatment accompanied by a plant radiation technician.
The licensee plans to notify the NRC Resident Inspector.
* * * UPDATE AT 1712 ON 04/22/00 BY STEVE FREGEAU TO JOLLIFFE * * *
The plant radiation technician determined that the plant employee was not contaminated.
The licensee plans to notify the NRC Resident Inspector.
The NRC Operations Officer notified the R1DO John White.
Power Reactor
Event Number: 36919
Facility: FERMI
Region: 3 State: MI
Unit: [2] [] []
RX Type: [2] GE-4
NRC Notified By: SANJEEV ARAB
HQ OPS Officer: DICK JOLLIFFE
Region: 3 State: MI
Unit: [2] [] []
RX Type: [2] GE-4
NRC Notified By: SANJEEV ARAB
HQ OPS Officer: DICK JOLLIFFE
Notification Date: 04/22/2000
Notification Time: 17:05 [ET]
Event Date: 04/22/2000
Event Time: 14:28 [EDT]
Last Update Date: 04/22/2000
Notification Time: 17:05 [ET]
Event Date: 04/22/2000
Event Time: 14:28 [EDT]
Last Update Date: 04/22/2000
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(ii) - ESF ACTUATION
10 CFR Section:
50.72(b)(2)(ii) - ESF ACTUATION
Person (Organization):
MARK RING (R3)
MARK RING (R3)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 2 | N | N | 0 | Refueling | 0 | Refueling |
- SHUTDOWN COOLING LOST FOR 48 MINUTES; NO REACTOR VESSEL TEMPERATURE RISE -
On 04/22/00, Unit 2 was in Condition 5 in a Refueling Outage with the reactor vessel cavity flooded up to higher than 20 feet 6 inches above the reactor vessel flange with the fuel pool gates removed.
At 1428, shutdown cooling was lost due to a technician inadvertently pulling a wrong electrical fuse causing the Residual Heat Removal (RHR) shutdown inboard suction isolation valve #E1150-F009 to auto close. The closure of this valve was in response to an invalid reactor vessel water level three signal causing the 'A' RHR pump to trip due to loss of suction flow.
At 1516, shutdown cooling was restored. No temperature rise in the reactor vessel was noted during the time that shutdown cooling was out of service.
The licensee plans to notify the NRC Resident Inspector.
On 04/22/00, Unit 2 was in Condition 5 in a Refueling Outage with the reactor vessel cavity flooded up to higher than 20 feet 6 inches above the reactor vessel flange with the fuel pool gates removed.
At 1428, shutdown cooling was lost due to a technician inadvertently pulling a wrong electrical fuse causing the Residual Heat Removal (RHR) shutdown inboard suction isolation valve #E1150-F009 to auto close. The closure of this valve was in response to an invalid reactor vessel water level three signal causing the 'A' RHR pump to trip due to loss of suction flow.
At 1516, shutdown cooling was restored. No temperature rise in the reactor vessel was noted during the time that shutdown cooling was out of service.
The licensee plans to notify the NRC Resident Inspector.