Hospital
Event Number: 36690
Rep Org: LESTER E. COX MEDICAL CENTER
Licensee: LESTER E. COX MEDICAL CENTER
Region: 3
City: Springfield   State: MO
County:
License #: 24-01143-06
Agreement: N
Docket:
NRC Notified By: Dr.TIM LESS
HQ OPS Officer: JOHN MacKINNON
Notification Date: 02/14/2000
Notification Time: 12:35 [ET]
Event Date: 02/03/2000
Event Time: 12:00 [CST]
Last Update Date: 02/14/2000
Emergency Class: NON EMERGENCY
10 CFR Section:
20.2201(a)(1)(ii) - LOST/STOLEN LNM>10X
Person (Organization):
BRUCE JORGENSEN (R3)
JOSEPHINE PICCONE (NMSS)
Event Text
15 MILLICUIRE NICKEL-63 SOURCE USED IN A HP GAS CHROMATOGRAPHY MISSING

Today at 0930 CT the Radiation Safety Officer for Cox Health System was informed by the Chief of Safety for Lester E. Cox Medical Center - North, located in Springfield, Mo., that a 15 millicurie Ni-63 source for a HP Gas Chromatography was missing and is now believed to be buried in a local land fill. The source was initially purchased on July 30. 1982 and it was last used in 1990. Since 1990 the source had been in a storage room located in the toxicology lab at Lester E. Cox Medical Center - North, Springfield, Mo. The items stored in the storage room were moved earlier this year to another location in the Lester E. Cox Medical Center - North. The left over items in the storage room were discarded into a BFI Dumpster at their facility and it is believed that the Ni-63 source was discarded to the BFI Dumpster. On 02/03/00 BFI hauled the contents of the dumpster to a local land fill. At this time the licensee is trying to find out if it is necessary to recover the Ni-63 source.
Ni-63 is a pure Beta emitter and the energy of the Beta particles is 17 Kev. HP registry number for the Gas Chromatography is NR-348-D-804-B.

Call the Headquarters Operation Officer for address and phone number.


!!!!! THIS EVENT HAS BEEN RETRACTED !!!!!
!!!!! THIS EVENT HAS BEEN RETRACTED !!!!!
Power Reactor
Event Number: 36657
Facility: RIVER BEND
Region: 4     State: LA
Unit: [1] [] []
RX Type: [1] GE-6
NRC Notified By: VERN CARLSON
HQ OPS Officer: JOHN MacKINNON
Notification Date: 02/03/2000
Notification Time: 16:08 [ET]
Event Date: 02/03/2000
Event Time: 11:14 [CST]
Last Update Date: 03/01/2000
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(ii) - ESF ACTUATION
Person (Organization):
CLAUDE JOHNSON (R4)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
1 N Y 100 Power Operation 100 Power Operation
Event Text
BOTH TRAINS OF POST ACCIDENT H2 ANALYZERS DECLARED ADMINISTRATIVELY INOPERABLE.

During an ongoing review of calculations for "Normal and Accident Gamma and Beta Doses for Mechanical Equipment Qualifications" it was discovered that an inaccurate assumption was made concerning the operation of the Containment and Drywell post accident hydrogen monitoring system. This inaccurate assumption could lead to the sample isolation valves receiving more radiation exposure than assumed in the calculations curing a design bases accident. This extra radiation exposure could cause deterioration of the valve seats and prevent them from sealing properly. With the valves leaking the indicated hydrogen concentrations could be non-conservatively low leading to improper actions during an accident. This condition affects both safety trains of the post accident hydrogen analyzers. The actual affect is still indeterminate however both trains have been conservatively declared administratively inoperable. The system is still in a standby lineup and is expected to continue to perform its function during the early stages of an accident. Engineering is continuing to evaluate the actual affect of the increased radiation exposure on the equipment. The NRC Resident Inspector will be informed of this event by the licensee.

* * * UPDATE AT 1713 ON 3/1/2000, BY FELTNER RECEIVED BY WEAVER * * *

On 2/3/2000, (event notification 36657), River Bend Station reported that the Containment and Drywell hydrogen monitor system had been conservatively declared inoperable. The inoperability was based on the impact of an inadequate assumption in a post accident dose calculation for the system sample valves. This could have lead to more post accident radiation exposure than determined in the original calculation, which may have lead to failure of the sample valves to properly seat. At the time of the original report. the actual affect of the condition on the valves was indeterminate and the system was declared inoperable. Engineering re-evaluated the condition as documented in a revision to calculation PR(c) 547. This calculation found that the original assumption in the calculation did not impact system operability. The calculation states that the potential doses due to plateout in the system would be negligible when compared to the airborne beta doses, and therefore the doses presented in the original calculation conservatively represent dose expected following a design basis accident. Based on this the system it was determined to be operable, and the condition not reportable. The licensee notified the NRC resident inspector. The NRC Operations Center notified the RDO (Cain).


Power Reactor
Event Number: 36658
Facility: POINT BEACH
Region: 3     State: WI
Unit: [1] [2] []
RX Type: [1] W-2-LP,[2] W-2-LP
NRC Notified By: ROB HARRSCH
HQ OPS Officer: JOHN MacKINNON
Notification Date: 02/03/2000
Notification Time: 17:18 [ET]
Event Date: 02/03/2000
Event Time: 15:45 [CST]
Last Update Date: 02/03/2000
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(1)(v) - EMERGENCY SIREN INOP
Person (Organization):
GARY SHEAR (R3)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
1 N Y 100 Power Operation 100 Power Operation
2 N Y 100 Power Operation 100 Power Operation
Event Text
ALL ALERT AND NOTIFICATION SYSTEM SIRENS INOPERABLE AFTER INSTALLING A SIREN STATUS FEEDBACK SYSTEM.

Loss of all 14 offsite Alert and Notification System after installation of a siren status feedback system. A common failure has resulted in the inability to activate any sirens. The vendor and plant staff are actively troubleshooting. The licensee will notify state and local officials of this event.

The NRC Resident Inspector was notified of this event by the licensee.

* * * UPDATE ON 02/03/00 AT 1923 HOURS BY HARRSCH TAKEN BY MACKINNON * * *

All Alert and Notification System sirens were returned to service at 1745 CT. A software problem caused the loss of the Alert and Notification system. State and Local officials were notified by the licensee of this update.
R3DO (Tony Vegel) notified.

The NRC Resident Inspector was notified of this update by the licensee.


Power Reactor
Event Number: 36656
Facility: QUAD CITIES
Region: 3     State: IL
Unit: [1] [2] []
RX Type: [1] GE-3,[2] GE-3
NRC Notified By: M MacLENNAN
HQ OPS Officer: JOHN MacKINNON
Notification Date: 02/03/2000
Notification Time: 15:12 [ET]
Event Date: 02/03/2000
Event Time: 10:21 [CST]
Last Update Date: 02/03/2000
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(ii) - ESF ACTUATION
Person (Organization):
TONY VEGEL (R3)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
1 N Y 100 Power Operation 100 Power Operation
2 N N 0 Refueling 0 Refueling
Event Text
INADVERTENT START OF EMERGENCY DIESEL GENERATOR (EDG) DURING SURVEILLANCE TESTING

On 02/03/00 at 1021 CST while performing surveillance test QCOS 0203-06 (ADS Logic Test) the Unit-1/2 EDG received an inadvertent autostart signal from Unit 2 Core Spray Logic system. The Unit 1/2 EDG autostart occurred during the installation of relay finger block being placed as part of the surveillance test. The finger block was being placed on the correct relay finger. However, during the installation, and due to the small contact clearances, a momentary relay actuation occurred and caused the EDG start. A Heightened Level of Awareness Briefing was conducted prior to the logic test, and discussed the potential for equipment actuations to occur during performance of the test. In addition, Limitations and Actions step F.7 of QCOS 0203-06 states that inadvertent actuations may occur during the performance of this test, including the EDG autostart, and requires immediate work stoppage and notification of the Unit Supervisor and a Shift Manager review for reportability. The EDG and associated plant systems responded as expected. This report is being made pending further review of the UFSAR and the stated design ESF systems contained in the UFSAR.

The NRC Resident Inspector was notified of this event by the licensee.