Skip to main content

Event Notification Report for December 07, 1999

U.S. Nuclear Regulatory Commission
Operations Center

EVENT REPORTS FOR
12/06/1999 - 12/07/1999

EVENT NUMBERS
3649336494

Power Reactor
Event Number: 36493
Facility: TURKEY POINT
Region: 2     State: FL
Unit: [3] [] []
RX Type: [3] W-3-LP,[4] W-3-LP
NRC Notified By: ROSS FREW
HQ OPS Officer: LEIGH TROCINE
Notification Date: 12/07/1999
Notification Time: 14:24 [ET]
Event Date: 12/07/1999
Event Time: 13:20 [EST]
Last Update Date: 12/07/1999
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(vi) - OFFSITE NOTIFICATION
Person (Organization):
EDWARD MCALPINE (R2)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
3 N Y 100 Power Operation 100 Power Operation
Event Text
OFFSITE NOTIFICATION REGARDING THE DISCOVERY OF A DEAD FLORIDA CROCODILE (AN ENDANGERED SPECIES) IN THE SITE'S COOLING CANAL SYSTEM

At 1320 on 12/07/99, the Land Utilization Group notified the control room of the discovery of a dead crocodile in the site's cooling canal system. It is currently believed that the dead crocodile lost a fight with a larger crocodile.

The licensee notified the NRC resident inspector. In accordance with an Environmental Permit, the licensee also plans to notify the Florida Game and Freshwater Fish Commission.


!!!!! THIS EVENT HAS BEEN RETRACTED !!!!!
!!!!! THIS EVENT HAS BEEN RETRACTED !!!!!
Power Reactor
Event Number: 36494
Facility: MONTICELLO
Region: 3     State: MN
Unit: [1] [] []
RX Type: [1] GE-3
NRC Notified By: JIM McKAY
HQ OPS Officer: LEIGH TROCINE
Notification Date: 12/07/1999
Notification Time: 20:21 [ET]
Event Date: 12/07/1999
Event Time: 17:55 [CST]
Last Update Date: 01/03/2000
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(iii)(D) - ACCIDENT MITIGATION
Person (Organization):
PATRICK HILAND (R3)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
1 N Y 92 Power Operation 92 Power Operation
Event Text
INOPERABILITY OF HPCI DUE TO A LOOSE PIPE SUPPORT

The following text is a portion of a facsimile received from the licensee:

"During normal plant operation the High Pressure Core Injection (HPCI) system was declared inoperable [in accordance with] Technical Specification section 3.5.A.3.g. HPCI is inoperable due to an inoperable pipe support on the steam supply to the HPCI drive turbine. The support was observed to be loose, and the anchor bolts on the base of the support are pulled out of the wall approximately 3/8". HPCI is in a 14-day [limiting condition for operation]."

The licensee notified the NRC resident inspector.

*** RETRACTION ON 01/03/00 AT 1723ET FROM T. ROGERS TAKEN BY MACKINNON ***

The support was repaired, and the system was returned to its normal standby condition. Subsequent analysis showed that the HPCI system remained operable with the support in the degraded condition. Therefore, the licensee is retracting this event notification. The licensee notified State, Local , and the NRC Resident Inspector of this retraction.

The NRC R3DO (MADERA) was notified of this retraction.