Event Notification Report for October 30, 1999
U.S. Nuclear Regulatory Commission
Operations Center
EVENT REPORTS FOR
10/29/1999 - 10/30/1999
General Information or Other
Event Number: 36380
Rep Org: CRMI
Licensee: LAS PIEDRAS CONSTRUCTION
Region: 2
City: UTUADO State: PR
County:
License #: 52-25125-01
Agreement: N
Docket:
NRC Notified By: RHOE (CONSULTANT)
HQ OPS Officer: CHAUNCEY GOULD
Licensee: LAS PIEDRAS CONSTRUCTION
Region: 2
City: UTUADO State: PR
County:
License #: 52-25125-01
Agreement: N
Docket:
NRC Notified By: RHOE (CONSULTANT)
HQ OPS Officer: CHAUNCEY GOULD
Notification Date: 11/01/1999
Notification Time: 08:55 [ET]
Event Date: 10/30/1999
Event Time: 09:00 [EST]
Last Update Date: 11/01/1999
Notification Time: 08:55 [ET]
Event Date: 10/30/1999
Event Time: 09:00 [EST]
Last Update Date: 11/01/1999
Emergency Class: NON EMERGENCY
10 CFR Section:
20.2201(a)(1)(i) - LOST/STOLEN LNM>1000X
10 CFR Section:
20.2201(a)(1)(i) - LOST/STOLEN LNM>1000X
Person (Organization):
MARK LESSER (R2)
FRITZ STURZ EO (NMSS)
MARK LESSER (R2)
FRITZ STURZ EO (NMSS)
STOLEN MOISTURE DENSITY GAUGE
A CPN MODEL MC-3 SERIAL NUMBER M-351102935 CONTAINING 10 MILLICURIES OF CS-137 AND 50 MILLICURIES OF AM-241 WAS STOLEN FROM LAS PIEDRAS CONSTRUCTION COMPANY'S FACILITIES IN UTUADO, PR. THE LOCAL POLICE DEPARTMENT WAS NOTIFIED AND THERE WILL BE A PRESS RELEASE.
A CPN MODEL MC-3 SERIAL NUMBER M-351102935 CONTAINING 10 MILLICURIES OF CS-137 AND 50 MILLICURIES OF AM-241 WAS STOLEN FROM LAS PIEDRAS CONSTRUCTION COMPANY'S FACILITIES IN UTUADO, PR. THE LOCAL POLICE DEPARTMENT WAS NOTIFIED AND THERE WILL BE A PRESS RELEASE.
Power Reactor
Event Number: 36375
Facility: SAINT LUCIE
Region: 2 State: FL
Unit: [1] [] []
RX Type: [1] CE,[2] CE
NRC Notified By: FIELDS
HQ OPS Officer: CHAUNCEY GOULD
Region: 2 State: FL
Unit: [1] [] []
RX Type: [1] CE,[2] CE
NRC Notified By: FIELDS
HQ OPS Officer: CHAUNCEY GOULD
Notification Date: 10/30/1999
Notification Time: 07:28 [ET]
Event Date: 10/30/1999
Event Time: 06:42 [EDT]
Last Update Date: 10/30/1999
Notification Time: 07:28 [ET]
Event Date: 10/30/1999
Event Time: 06:42 [EDT]
Last Update Date: 10/30/1999
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(ii) - RPS ACTUATION
10 CFR Section:
50.72(b)(2)(ii) - RPS ACTUATION
Person (Organization):
MARK LESSER (R2)
MARK LESSER (R2)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 1 | M/R | Y | 3 | Startup | 0 | Hot Standby |
PLANT HAD A MANUAL TRIP FROM 3% POWER.
DURING PLANT STARTUP WITH THE REACTOR CRITICAL ABOVE THE POINT OF ADDING HEAT, THE "1A" STEAM GENERATOR LEVEL DECREASED WHILE BEING FED WITH THE AUXILIARY FEED SYSTEM. THE REACTOR WAS MANUALLY TRIPPED WHEN THE STEAM GENERATOR LEVEL DECREASED BELOW THE PRE-TRIP SETPOINT. ALL RODS FULLY INSERTED, NO ECCS INJECTION OCCURRED AND NO RELIEF VALVES LIFTED. THE CAUSE OF THE DECREASE IN STEAM GENERATOR LEVEL IS BEING INVESTIGATED. THE HEAT SINK IS THE ATMOSPHERIC DUMP VALVES.
THE RESIDENT INSPECTOR WAS NOTIFIED.
DURING PLANT STARTUP WITH THE REACTOR CRITICAL ABOVE THE POINT OF ADDING HEAT, THE "1A" STEAM GENERATOR LEVEL DECREASED WHILE BEING FED WITH THE AUXILIARY FEED SYSTEM. THE REACTOR WAS MANUALLY TRIPPED WHEN THE STEAM GENERATOR LEVEL DECREASED BELOW THE PRE-TRIP SETPOINT. ALL RODS FULLY INSERTED, NO ECCS INJECTION OCCURRED AND NO RELIEF VALVES LIFTED. THE CAUSE OF THE DECREASE IN STEAM GENERATOR LEVEL IS BEING INVESTIGATED. THE HEAT SINK IS THE ATMOSPHERIC DUMP VALVES.
THE RESIDENT INSPECTOR WAS NOTIFIED.