Event Notification Report for October 09, 1999

U.S. Nuclear Regulatory Commission
Operations Center

EVENT REPORTS FOR
10/08/1999 - 10/09/1999

EVENT NUMBERS
3627736278

Power Reactor
Event Number: 36277
Facility: SURRY
Region: 2     State: VA
Unit: [1] [2] []
RX Type: [1] W-3-LP,[2] W-3-LP
NRC Notified By: LISA HILBERT-SEMMES
HQ OPS Officer: BOB STRANSKY
Notification Date: 10/09/1999
Notification Time: 22:13 [ET]
Event Date: 10/09/1999
Event Time: 12:41 [EDT]
Last Update Date: 10/09/1999
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(ii) - ESF ACTUATION
Person (Organization):
BRIAN BONSER (R2)
JOHN ZWOLINSKI (NRR)
CHARLES MILLER (IRO)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
1 N Y 100 Power Operation 100 Power Operation
2 N Y 100 Power Operation 96 Power Operation
Event Text
EDGs START AND LOAD DUE TO LOSS OF ONE RESERVE STATION SERVICE TRANSFORMER

"At 1241 hours, with Surry Power Station Unit 1 and Unit 2 at 100% reactor power, a loss of 'C' Reserve Station Service Transformer (RSST) occurred due to a fire on one of the leads. The #1 Emergency Diesel Generator (EDG) auto started due to an undervoltage signal on the Unit 1 'H' emergency bus and re-energized the Unit 1 'H' emergency bus. Also, the #3 EDG auto started due to an undervoltage signal on the Unit 2 'J' emergency bus and re-energized the Unit 2 'J' emergency bus. The fire team reported that the fire was out at 1243. Unit 1 remained at 100% power. Unit 2 decreased to 96% power due to a perturbation on the semi-vital bus when the 'J' emergency bus was de-energized then re-energized by the #3 EDG. The unit was returned to 100% power at 1400 when all unit conditions were verified stable. All equipment performed as expected during the event and there were no unexplained occurrences other than the loss of 'C' RSST which is under investigation.

"No adverse radiological consequences resulted from this event. There were no radiation releases due to this event, nor were there any personnel injuries or contamination events.

"Unit 1 is currently at 100% power and 845 MWe with #1 EDG supplying the 'H' emergency bus.

"Unit 2 is currently at 100% power and 855 MWe with #3 EDG supplying the 'J' emergency bus.

"This event was initially determined to be not reportable based on the EDG auto start signal being due to an undervoltage signal and not a valid ESF signal. Upon further review of Tech Specs and NUREG 1022, it was determined at 2015 that the EDG auto starts due to an under voltage signal were reportable as an ESF actuation."

The NRC resident inspector has been informed of this event by the licensee.

This is event is being reported in accordance with 10 CFR 50.72(b)(2)(ii).


Research Reactor
Event Number: 36278
Rep Org: STATE UNIV OF NEW YORK AT BUFFALO
Licensee: STATE OF NEW YORK
Region: 1
City: BUFFALO   State: NY
County: ERIE
License #: R-77
Agreement: Y
Docket: 05000057
NRC Notified By: MARK ADAMS
HQ OPS Officer: BOB STRANSKY
Notification Date: 10/10/1999
Notification Time: 11:48 [ET]
Event Date: 10/09/1999
Event Time: 22:00 [EDT]
Last Update Date: 10/10/1999
Emergency Class: NON EMERGENCY
10 CFR Section:
Person (Organization):
JOHN KINNEMAN (R1)
THEODORE MICHAELS (NRR)
Event Text
COURTESY CALL DUE TO POWER OUTAGE

The licensee reported that a transformer failure resulted in a power outage to the reactor facility. The emergency diesel generator started, but was manually stopped due to poor operating performance. Partial power has been restored from another building. The licensee anticipates that replacement of the transformer could take from three to six weeks. This facility has been shut down since 1994. The only required equipment affected by the outage are gaseous radiation monitors, which have an allowed outage time of 10 days.

The caller made this report because of possible press interest in the event. The local media monitors campus radio transmissions, and the caller speculated that transmissions regarding the event could be interpreted by the media as a serious event. The licensee may make a press release.