Skip to main content

Event Notification Report for July 06, 1999

U.S. Nuclear Regulatory Commission
Operations Center

EVENT REPORTS FOR
07/05/1999 - 07/06/1999

EVENT NUMBERS
359333589735898

Other Nuclear Material
Event Number: 35933
Rep Org: ANHEUSER BUSCH
Licensee:
Region: 3
City: COLUMBUS   State: OH
County:
License #: NA
Agreement: N
Docket:
NRC Notified By: JERRY MOESLEIN
HQ OPS Officer: DOUG WEAVER
Notification Date: 07/19/1999
Notification Time: 12:59 [ET]
Event Date: 07/06/1999
Event Time: 12:00 [EDT]
Last Update Date: 07/19/1999
Emergency Class: NON EMERGENCY
10 CFR Section:
20.2201(a)(1)(i) - LOST/STOLEN LNM>1000X
Person (Organization):
PATRICK HILAND (R3)
FRED STURZ (NMSS)
Event Text
LOST TRITIUM EXIT SIGNS

Anheuser Busch reported losing 4 exit signs at their facility located at 700 Schrock Road, Columbus, OH. Three signs had 5.2 Ci and one had 7.9 Ci of tritium, the age of the signs was not available. They were determined to be missing on 7/6/99, and a subsequent search did not find the signs. Anheuser Busch believes the signs were stolen.


!!!!! THIS EVENT HAS BEEN RETRACTED !!!!!
!!!!! THIS EVENT HAS BEEN RETRACTED !!!!!
Power Reactor
Event Number: 35897
Facility: SURRY
Region: 2     State: VA
Unit: [] [2] []
RX Type: [1] W-3-LP,[2] W-3-LP
NRC Notified By: LISA HILBERT-SEMMES
HQ OPS Officer: STEVE SANDIN
Notification Date: 07/06/1999
Notification Time: 02:44 [ET]
Event Date: 07/06/1999
Event Time: 02:04 [EDT]
Last Update Date: 07/23/1999
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(1)(i)(A) - PLANT S/D REQD BY TS
Person (Organization):
PAUL FREDRICKSON (R2)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
2 N N 0 Hot Shutdown 0 Intermediate Shutdown
Event Text
MODE CHANGE INITIATED AS PART OF A TECHNICAL SPECIFICATION REQUIRED SHUTDOWN

"At 1810 hours on 7-5-99, with Surry Power Station Unit 2 at Hot Shutdown (HSD) following a reactor trip, the 'A' Cold Leg Loop Stop Valve (Mark number 2-RC-MOV-2591) was removed from it's backseat in accordance with station procedure 2-GOP-2.4. Upon reopening the valve, full open indication was not received. In accordance with Technical Specification 3.17.1 and 3.0.1, a 30 hour clock to Cold Shutdown (CSD) LCO was started. The valve was de-energized by opening it's breaker. A cooldown to CSD was initiated at 2050 on 7-5-99. At 0204 on 7-6-99, a review of Station procedures and 10CFR50.72 determined that a one hour report was required for commencing the RCS cooldown in accordance with the Technical Specification LCO.

"There were no radiation releases due to this event, nor were there any personnel injuries or contamination events.

"Unit 2 is currently in Intermediate Shutdown with RCS cooldown in progress in accordance with station procedures.

"Unit 1 was not affected by this event and remains stable at 100% power and 824 MWe.

"This event is being reported in accordance with 10CFR50.72(b)(1)(i)(A)."

The Licensee informed the NRC Resident Inspector.

* * * UPDATE AT 0940 ON 07/23/99 FROM RAWLEIGH DILLARD TO JOLLIFFE * * *

A review of NUREG 1022 with respect to 10CFR50.72(b)(1)(i)(A) provides the following clarification: "the phrase 'initiation of any nuclear plant shutdown' includes action to start reducing reactor power, i.e., adding negative reactivity to achieve a nuclear plant shutdown required by Technical Specifications. The 'initiation of any nuclear plant shutdown' does not include mode changes required by Technical Specifications if initiated after the plant is already in a shutdown condition."

Unit 2 achieved Hot Shutdown Mode at 1122 on 07/05/99 after a reactor trip. Based on the information given above in NUREG 1022, a one hour report was not required for commencing the cooldown to Cold Shutdown Mode as this was a mode change after Unit 2 was already in a shutdown condition. The actions taken by the Licensee were prudent and represented a conservative decision by the Licensee.

Thus, the Licensee desires to retract the above report based on the above discussion.

The Licensee informed the NRC Resident Inspector.

The NRC Operations Officer notified the R2DO Ed McAlpine.


Power Reactor
Event Number: 35898
Facility: SUSQUEHANNA
Region: 1     State: PA
Unit: [1] [] []
RX Type: [1] GE-4,[2] GE-4
NRC Notified By: DON ROLAND
HQ OPS Officer: WILLIAM POERTNER
Notification Date: 07/06/1999
Notification Time: 14:37 [ET]
Event Date: 07/06/1999
Event Time: 13:30 [EDT]
Last Update Date: 07/06/1999
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(i) - DEG/UNANALYZED COND
Person (Organization):
JIM TRAPP (R1)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
1 N N 0 Cold Shutdown 0 Cold Shutdown
Event Text
DEGRADED/UNANALYZED CONDITION

During a Unit 1 forced outage, the licensee determined that the 'C' outboard Main Steam Isolation Valve (MSIV) was unable to fully close. Based on the as-found valve configuration, it is believed that the MSIV volume would not reach required test pressure, therefore actual leak rate testing was not performed. This report documents exceeding overall MSIV maximum pathway acceptance criteria of 300 scfh.

The licensee determined that the valve disc had separated from the stem.

See Event 35884 for further information.

The licensee has notified the NRC resident inspector.