Event Notification Report for March 03, 1999

U.S. Nuclear Regulatory Commission
Operations Center

EVENT REPORTS FOR
03/02/1999 - 03/03/1999

EVENT NUMBERS
354353543635437

Power Reactor
Event Number: 35435
Facility: HARRIS
Region: 2     State: NC
Unit: [1] [] []
RX Type: [1] W-3-LP
NRC Notified By: MACKENZIE
HQ OPS Officer: CHAUNCEY GOULD
Notification Date: 03/03/1999
Notification Time: 17:01 [ET]
Event Date: 03/03/1999
Event Time: 16:13 [EST]
Last Update Date: 03/03/1999
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(1)(v) - OTHER ASMT/COMM INOP
Person (Organization):
CAUDLE JULIAN (R2)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
1 N Y 100 Power Operation 100 Power Operation
Event Text
GREATER THAN 20% OF THE SIRENS ARE OUT OF SERVICE

DUE TO SEVERE WEATHER IN THE AREA OF THE SITE MORE THAN 20% OF THE LICENSEE'S SIRENS ARE INOPERABLE. THE PLANT HAD RECEIVED A SEVERE STORM WARNING WITH HIGH WINDS FROM THE WEATHER SERVICE AT 1400. REPAIR EFFORTS WILL BE INITIATED IMMEDIATELY.

THE RESIDENT INSPECTOR WILL BE NOTIFIED ALONG WITH STATE AND LOCAL AGENCIES.

***UPDATE ON 3/3/99 @ 2006 BY HOLBROOK TO GOULD ***

THE NUMBER OF INOPERABLE SIRENS IS 5 OUT OF 62 WHICH IS WITHIN THE 20% LIMIT AS OF 1813.
THE RESIDENT INSPECTOR WILL BE INFORMED.

REG 2 RDO(JULIAN) WAS NOTIFIED.


General Information or Other
Event Number: 35436
Rep Org: AUTOMATIC SWITCH CO.
Licensee: AUTOMATIC SWITCH CO.
Region: 1
City: FLORHAM PARK   State: NJ
County:
License #:
Agreement: N
Docket:
NRC Notified By: YAOUANC(FAX)
HQ OPS Officer: CHAUNCEY GOULD
Notification Date: 03/03/1999
Notification Time: 15:51 [ET]
Event Date: 03/03/1999
Event Time: 00:00 [EST]
Last Update Date: 03/03/1999
Emergency Class: NON EMERGENCY
10 CFR Section:
21.21 - UNSPECIFIED PARAGRAPH
Person (Organization):
MICHAEL MODES (R1)
VERN HODGES (NRR)
Event Text
AUTOMATIC SWITCH CO (ASCO) REPORTED A MANUFACTURING DEFICIENCY .

CERTAIN PUMP AND AMPLIFIER ASSEMBLIES USED IN ASCO GENERAL CONTROLS HYDRAMOTOR ACTUATORS COULD HAVE A MANUFACTURING DEFICIENCY WHICH MAY AFFECT THE OPERATION OF THE ACTUATORS. ASCO WAS ALERTED TO THIS PROBLEM UPON EXAMINATION OF A HYDRAMOTOR ACTUATOR, THAT WAS RECENTLY RETURNED TO ASCO FROM NINE MILE POINT 2 AFTER IT HAD FAILED DURING THE POST INSTALLATION TESTING. THIS CONDITION MAY RESULT IN THE FAILURE OF THE ACTUATOR PISTON TO RETRACT WHEN THE HYDRAMOTOR IS POWERED, OR THE ACTUATOR PISTON RETURNING TO THE SPRING EXTENDED POSITION WHILE THE HYDRAMOTOR IS POWERED. THEY ARE CONTINUING THE INVESTIGATION AND WILL PROVIDE A COMPLETE LIST OF POTENTIALLY AFFECTED ACTUATORS, ALONG WITH THEIR PURCHASERS.


Power Reactor
Event Number: 35437
Facility: DIABLO CANYON
Region: 4     State: CA
Unit: [1] [] []
RX Type: [1] W-4-LP,[2] W-4-LP
NRC Notified By: MAGRUDER
HQ OPS Officer: CHAUNCEY GOULD
Notification Date: 03/03/1999
Notification Time: 20:31 [ET]
Event Date: 03/03/1999
Event Time: 15:01 [PST]
Last Update Date: 03/03/1999
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(ii) - ESF ACTUATION 50.72(b)(2)(iii)(B) - POT RHR INOP
Person (Organization):
PHIL HARRELL (R4)
ELINOR ADENSAM (NRR)
JOSEPH GIITTER (IRO)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
1 N N 0 Refueling 0 Refueling
Event Text
AUXILIARY OFFSITE POWER TRIPPED DURING MAINTENANCE WORK DUE TO A PROCEDURAL DISCREPANCY.

THE AUXILIARY OFFSITE POWER TRIP RESULTED IN THE AUTO START AND LOADING OF THE 1-2 DIESEL GENERATOR ON A BUS UNDERVOLTAGE SIGNAL. THE OPERATING RHR PUMP TRIPPED, BUT WAS MANUALLY RESTARTED WITHIN 39 SEC, WITHOUT ANY NOTICEABLE TEMPERATURE INCREASE OCCURRING IN THE PRIMARY SYSTEM. THE TRIP OF THE OFFSITE POWER OCCURRED DURING MAIN TURBINE WORK WHICH CAUSED A THRUST BEARING TRIP SIGNAL. THE THRUST BEARING TRIP WAS NOT CUT OUT AT THE TIME, THUS THE INITIATION OF A UNIT TRIP SIGNAL OCCURRED, TRIPPING OFFSITE AUXILIARY POWER.

ONE OF THE THREE VITAL BUSES WAS ALIGNED WITH ITS STARTUP FEEDER BREAKER IN THE TEST POSITION FOR PLANNED TESTING. WHEN AUXILIARY POWER TRIPPED, THE BUS COULD THEREFORE NOT TRANSFER TO OFFSITE STARTUP POWER AND THE DIESEL GENERATOR STARTED ON BUS UNDERVOLTAGE. THE RUNNING RHR PUMP WAS SHED FROM THE BUS DURING THE TRANSFER. THE OTHER TWO BUSES SUCCESSFULLY TRANSFERRED TO THE STARTUP POWER SOURCE.

THE VITAL BUS ON THE DIESEL WAS TRANSFERRED AT 1549 PST TO THE STARTUP POWER SOURCE AND THE DIESEL WAS SECURED AT 1551 PST. ALL OFFSITE POWER SOURCES WERE RESTORED AT 1800 PST.

THE PROCEDURE DISCREPANCY WILL BE CORRECTED.

THE RESIDENT INSPECTOR WAS INFORMED.