Partial response to FOIA request for all records re C Van Vo 841006 affidavit.Forwards App A & B documents.Portions of App B documents withheld & App C documents entirely withheld (ref FOIA Exemptions 6 & 7).
Accession Number: ML20132C567
Date Released: Wednesday, May 27, 2020
Package Contents
The following links on this page are to Adobe Portable Document Format (PDF) files. To obtain a free viewer for displaying this format, see our Plugins, Viewers, and Other Tools.
- ML20134G063 - Partial response to FOIA request for all records re C Van Vo 841006 affidavit.Forwards App A & B documents.Portions of App B documents withheld & App C documents entirely withheld (ref FOIA Exemptions 6 & 7). (12 page(s), 7/12/1985)
- ML20134G188 - Affidavit of AP Cobb re review & investigation of concerns raised in C Van Vo affidavit,particularly mgt response & facility quality check program.Cobb resume encl. (8 page(s), 11/9/1984)
- ML20134G110 - Transcript of C Van Vo 850226 deposition in Raleigh,NC re allegations against CP&L mgt. (371 page(s), 2/26/1985)
- ML20134G098 - Forwards transcript of 850226 interview conducted w/alleger in Raleigh,NC re discrimination & possible hanger deficiencies.Requests review to ascertain if any new technical issues addressed. (3 page(s), 3/12/1985)
- ML20134G149 - Undated,handwritten memo re alleged const deficiencies at facility.Review of 841006 affidavit,841111 Region III/Ofc of Investigation interview & unsigned Nov affidavit completed. Encls detail insp being performed.W/o encls. (2 page(s), 8/14/1985)
- ML20134G075 - Forwards draft affidavit of C Van Vo,providing addl info re alleged discrimination & possible hanger deficiencies, specifically improper cold pulling of steam generator feedwater pump,for use in review of allegations. (7 page(s), 11/28/1984)
- ML20134G095 - Forwards list of perceived allegations re facility const deficiencies & provides recommended lead responsibilities for followup insp,per review of 841006 affidavit,841111 interview & unsigned Nov affidavit,(Case RII-84-A-0143). (9 page(s), 12/12/1984)
- ML20134G165 - Transcript of investigative interview w/C Van Vo on 841101 in Raleigh,NC re const safety concerns,allegations of harassment & intimidation by CP&L & possible fraudulent documentation & matl traceability. (259 page(s), 11/1/1984)
- ML20134G192 - Requests review of encl affidavit re alleged discrimination & possible hanger deficiencies (Case RII-84-A-0143) at facility & encl transcript of interview w/alleger.Systematic problem re handling of QA documentation may exist. (2 page(s), 11/13/1984)
- ML20134G144 - Discusses review of alleged const deficiencies at facility. Technical issues identified for inspector follow up are const activities affecting steam generator feedwater pumps & hanger insp problems.Related info encl. (20 page(s), 10/19/1984)
- ML20132C562 - Responds to B Buckley request that Auxiliary Sys Branch review Sections 5,6 & 7 of C Van Vo Davis affidavit re cold-pulling 24-inch feedwater pump discharge line. Unexecuted affidavit of NH Wagner encl. (4 page(s), 11/20/1984)
- ML20132C580 - Forwards supplemental NH Wagner Auxiliary Sys Branch affidavit re consequences of cold pulling main feedwater pump discharge line & consequent misalignment when line mated to pump.Position in 841120 affidavit maintained. (1 page(s), 12/6/1984)
- ML20134G143 - Forwards C Van Vo 841006 affidavit identifying several const deficiencies at facility.US Dept of Labor investigating Van Vo allegations of discrimination.Requests review of affiant concerns & resolution of issues. (1 page(s), 10/10/1984)
- ML20134G157 - Advises that const deficiencies identified in affidavit forwarded by 841005 ltr being pursued through insp process.Findings will be forwarded upon completion.Assures that every effort will be made toward resolution. (3 page(s), 10/25/1984)
- ML20134G162 - Revised "Rept of Results of Interviews Conducted W/CP&L Personnel re Selected Aspects of Affidavit Submitted by Former CP&L Employee C Van Vo." (30 page(s), 11/9/1984)
- ML20134G117 - Rept of investigation, "Shearon Harris Nuclear Plant - Alleged Harassment/Intimidation & Falsification of Documentation Commitments." (53 page(s), 5/16/1985)
- ML20134G106 - Requests that Van Vo contact Region II re encl 840828 ltr to US Dept of Labor complaining of discrimination by CP&L,to discuss hanger deficiencies identified to licensee in Jul 1983.Record of 841001 telcon encl. (5 page(s), 9/21/1984)
- ML20134G153 - Requests investigative assistance re C Van Vo allegations of harassment,falsification of records,discrimination,const deficiencies & hanger insp deficiencies.Interview should be conducted by Region II personnel w/court reporter present. (8 page(s), 10/24/1984)
- ML20134G196 - Forwards CP&L response to C Van Vo affidavit alleging discrimination & possible hanger deficiencies (Case RII-84-A-0143) for use in conducting inquiry.W/o encl. (3 page(s), 11/19/1984)
- ML20134G090 - Confirms 841211 conversation re Van Vo allegation file, specifically actions required as result of US Dept of Labor investigation.Review of investigation should confirm conclusions & thoroughness of Dept of Labor investigation. (14 page(s), 12/11/1984)
- ML20134G174 - Requests assistance in identifying any insp repts re const activities affecting steam generator feedwater pumps & piping sys & hanger insp problems,in connection w/review of allegations.Info due by 841107. (2 page(s), 11/6/1984)
- ML20134G101 - Discusses investigation of C Van Vo allegations of harassment in light of J Axelrad position on NRC use of Brown & Root decision.Expects approval of continuation of investigations.List of OELD needs re same encl.W/o encl. (1 page(s), 2/6/1985)
- ML20134G135 - Affidavit of C Van Vo re allegations of harassment, intimidation,pressure to resign & ultimate termination due to repts of safety concerns & const deficiencies to CP&L mgt.FR notices encl. (96 page(s), 10/6/1984)
- ML20134G082 - Forwards draft affidavit of C Van Vo,providing addl info re alleged discrimination & possible hanger deficiencies, specifically improper cold pulling of steam generator feedwater pump,for use in conduct of inquiry.W/o encl. (1 page(s), 11/28/1984)
- ML20134G369 - Forwards F Jape 841212 memo re C Van Vo allegations of const deficiencies.Reguests discussion of matter in view of importance in licensing status.W/o encl. (1 page(s), 2/6/1985)
- ML20134G182 - Forwards transcript re alleged discrimination & possible hanger deficiencies,for review.Results of review should be documented in memo to Allegation Case RII-84-A-0143 file. W/o transcript. (1 page(s), 11/7/1984)
- ML20134G105 - Forwards A Herdt 841212 memo re alleged const deficiencies (Case RII-84-A-0143) for review.Several issues indicate Ofc of Investigation study warranted.Requests meeting to coordinate efforts.Related info encl. (97 page(s), 2/6/1985)
- ML20134G177 - Discusses 841101 interview of C Van Vo re allegations, including concerns about pipe support matl,insp,records, cold springing of piping to steam generator feed pump & QA program in general.Van Vo assured of followup. (2 page(s), 11/6/1984)
- ML20134G069 - Forwards 19 pages of corrections to transcript of 841101 interview in Raleigh,NC.Deficiency & Disposition Rept 1875 re weld deficiencies & Deficiency Rept M-403 w/PO-h-40924 also encl.W/o repts. (20 page(s), 11/20/1984)
- ML20134G086 - Rev 9 to Work Procedure WP-110, "Installation of Seismic Pipe Hangers & Supports for Seismically Analyzed Pipe." Incomplete & illegible procedures & related info encl. (200 page(s), 11/28/1983)
- ML20134G184 - Forwards 841023 newspaper article discussing Van Vo concerns re facility.Article indicates some issues looked into & resolved by CP&L. (4 page(s), 11/8/1984)
- ML20134G079 - Rev 1 to Work Procedure WP-141 (title illegible). (28 page(s), 1/28/1985)
- ML20134G066 - Forwards marked-up,incomplete CP&L response to C Van Vo affidavit alleging discrimination & possible hanger deficiencies (Case RII-84-A-0143) for use in review of allegations. (34 page(s), 11/19/1984)
- ML20134G103 - Summary of 830610 exit meeting for Insp Repts 50-400/83-20 & 50-401/83-20.Major areas discussed:previously unresolved item re ground areas on pipe support areas/restraint & post-weld heat for turbine steel. (4 page(s), 6/10/1983)