Home > NRC Library > ADAMS Public Documents
Third response to FOIA request for documents re SER on operation of plant.App documents available in PDR.Review of addl documents continuing.
Accession Number: ML20105B784
Date Released: Sunday, November 8, 2020
Package Contents
The following links on this page are to Adobe Portable Document Format (PDF) files. To obtain a free viewer for displaying this format, see our Plugins, Viewers, and Other Tools.
- ML20113D233 - Third response to FOIA request for documents re SER on operation of plant.App documents available in PDR.Review of addl documents continuing. (3 page(s), 6/27/1984)
- ML20105C345 - Forwards R Lipinski evaluation of util response to anonymous Allegation 6.Response acceptable pending review of two confirmatory items re test programs of matl & demonstration by util that tornado parameters upper bound. (7 page(s), 10/21/1983)
- ML20113D281 - Forwards Auxiliary Sys Branch SSER re util proposed Tech Spec for assuring operable UHS.Tech Specs adequate. (1 page(s), 7/14/1983)
- ML20105B779 - Lists 830428 teleconference recommendations on Superstrut allegations.NRC concerns re util proposed test program to be submitted on 830617 listed. (2 page(s), 5/27/1983)
- ML20113D295 - SSER supporting util proposed Tech Specs re UHS. (11 page(s), 7/14/1983)
- ML20105C285 - Provides Equipment Qualification Branch assessment of seismic capability of emergency diesel generator intake & exhaust sys.Any loss of efficiency in operation of diesel generators due to large earthquake unlikely. (8 page(s), 9/29/1983)
- ML20113D266 - Safety evaluation re component cooling water sys.Applicant satisfied original FSAR commitments & regulations. (21 page(s), 6/20/1983)
- ML20105C142 - Summarizes findings on anonymous allegations re IDVP activities identified in D Fleischaker 830328 ltr. (3 page(s), 8/10/1983)
- ML20113D251 - Forwards div response to allegations identified in G Knighton 831129 memo. (27 page(s), 12/9/1983)
- ML20105B820 - Forwards Auxiliary Sys Branch SER on reevaluation of component cooling water sys,in response to 830218 memo. Licensee has satisfied original FSAR commitments & applicable regulations. (3 page(s), 6/20/1983)
- ML20113D327 - Rev 0 to "Outline for Sampling,Preparation & Testing of Spot-Welded Superstrut Members for Diablo Canyon Power Plant." (9 page(s), 5/21/1983)
- ML20113D238 - Transcript of C Strokes 831207 interview re seismic restraints. (121 page(s), 12/7/1983)
- ML20113D319 - "Final Rept on Evaluation of Spot-Welded Matls Used in Support Sys for Electrical Conduit & Cable Trays at Diablo Canyon Power Plant." (19 page(s), 7/1/1983)