Final response to FOIA request re Comanche Peak response team activities.App A documents already in PDR.Forwards App B documents.
Accession Number: ML20209E570
Date Released: Wednesday, August 12, 2020
Package Contents
The following links on this page are to Adobe Portable Document Format (PDF) files. To obtain a free viewer for displaying this format, see our Plugins, Viewers, and Other Tools.
- ML20210C318 - Final response to FOIA request re Comanche Peak response team activities.App A documents already in PDR.Forwards App B documents. (3 page(s), 1/29/1987)
- ML20210R211 - Forwards preliminary comments on May 1986 draft SSER 13, Sections 1 & 3.Sentence on Pages 1-4,1-7,3-1 & 3-5 most appropriately worded on Page 1-7.Last word in paragraph on Page 1-6 re generic implications should be "deficiencies." (4 page(s), 5/14/1986)
- ML20210E104 - Responds to 860613 memo re review of three new or revised ISAPs concerning hot functional testing data packages, receipt & storage of purchased matl & equipment & onsite fabrication. (2 page(s), 7/13/1986)
- ML20210D459 - "NRC Plan for Review & Audit of Applicants Program For Assuring Design & Const Adequacy of Comanche Peak Steam Electric Station." (8 page(s), 7/31/1985)
- ML20210A774 - Submits list of portions of draft SER transmitted to date by Teledyne.Portions focus on Comanche Peak Review Team program plan,design adequacy program plan & const adequacy program plan.Listed info will be provided later. (1 page(s), 12/23/1985)
- ML20210D880 - Forwards addl comments re draft SSER 13 sent on 860514. (9 page(s), 5/16/1986)
- ML20210C077 - Trip Rept 2200 of 860117 site visit re HVAC hanger program audit.Status of licensee steam electric station seismic qualification rept of seismic Category 1 duct work & hangers changed from "approved" to "not approved" on 860121. (3 page(s), 1/17/1986)
- ML20210B978 - Trip rept of 851202-03 visit to TERA ofcs in Bethesda,MD to audit documentation supporting initial level of homogeneity for design activities review Procedure DAP-21 that will be implemented to validate homogeneity. (11 page(s), 1/16/1986)
- ML20210D403 - Forwards preliminary comments on Comanche Peak response team program plan & recommends series of working meetings arranged w/various technical groups prior to meeting w/mgt to clarify plan approach to resolution of issues. (8 page(s), 7/15/1985)
- ML20211H073 - Forwards review of safety-significant evaluations (SSE) of const deviations in civil/structural populations.Tentative schedule for SSE & App P issues deemed inappropriate based on current contractual requirements. (4 page(s), 6/18/1986)
- ML20210C696 - "Executive Summary Technical Evaluation Rept on Comanche Peak Response Team Program Plan & Issue-Specific Action Plans,Rev 2," Books 1 & 2. (107 page(s), 7/29/1985)
- ML20210D123 - Requests review of Comanche Peak response team plan,for resolution of concerns in NUREG-0797,Suppl 11,App P. Lead engineer should be assigned to task by 851223. (24 page(s), 12/16/1985)
- ML20210S437 - Trip rept of 860505-07 site visit to attend civil/structural issues audit meetings.Audit attendee list & agenda encl. (96 page(s), 5/21/1986)
- ML20210D374 - Forwards staff evaluation of Comanche Peak response team plan providing detailed comments/concerns on Section 3.0, main rept (Sections I to VIII & Attachments 1-5),Item 1. (2 page(s), 8/16/1985)
- ML20210B207 - Forwards early inputs for next rev to SSER on facility program plan.Encls do not fully reflect evaluation due to late receipt of Rev 3 to program plan.More input will be provided at 860303 meeting. (76 page(s), 1/30/1986)
- ML20210C513 - Discusses review of util 851122 responses including QA/QC ISAPS.Comanche Peak Review Team program plan consistent w/ 10CFR50,App B. (2 page(s), 12/18/1985)
- ML20210A660 - Forwards final schedule for review of Comanche Peak Review Team Program Plan.Efforts should be focused toward meeting schedule as item of high priority.Written evaluation should be provided to A Vietti-Cook. (2 page(s), 11/26/1985)
- ML20210C590 - Forwards Teledyne Engineering Svcs Technical Rept TR-6410-1, "Executive Summary Technical Evaluation Rept on Comanche Peak Response Team Program Plan & Issue-Specific Action Plans,Rev 2," Books 1 & 2. (1 page(s), 7/29/1985)
- ML20209F940 - Forwards organization chart & roster for sys/operations group of Comanche Peak Task Force to be used for meeting objectives of encl NRC 850702 plan for review & audit of util design & const adequacy program plan. (4 page(s), 7/8/1985)
- ML20209G005 - Responds to request for comments on Comanche Peak response team program plan.Plan contains most elements required for adequate implementation of action plans for review of design & const.Detailed comments encl. (4 page(s), 7/31/1985)
- ML20209J318 - Trip rept of attendance at 860821 meeting in Arlington,TX re util plans for plant issues.Summaries of observations listed. (12 page(s), 9/3/1986)
- ML20209F945 - Forwards NRC plan for review of util design & const adequacy review program.Organization chart also encl. (1 page(s), 7/2/1985)
- ML20209E567 - Advises of meetings scheduled for 850701,10,17 & 31 in Bethesda,MD to discuss util program plan.NRC response will be sent to util by 850807. (1 page(s), 6/27/1985)
- ML20210A729 - Requests that util response to CYGNA findings be included in review & evaluation of Comanche Peak Review Team (CPRT) Program Plan & incorporated into CPRT Program Plan SSER. Draft SSER still due on 851223. (2 page(s), 12/5/1985)