Home > NRC Library > ADAMS Public Documents
Third partial response to FOIA request for documents.App C documents encl & available in PDR.Addl records referred to Dept of Commerce & DOI for review & direct response.
Accession Number: ML20151W779
Date Released: Saturday, June 13, 2020
Package Contents
The following links on this page are to Adobe Portable Document Format (PDF) files. To obtain a free viewer for displaying this format, see our Plugins, Viewers, and Other Tools.
- ML20151X358 - Forwards request for addl info re application for CP & facility license for nuclear power plant at Diablo Canyon site,including seismic design in terms of criteria for Class I sys & components considering load combinations. (5 page(s), 10/26/1967)
- ML20151X612 - Requests permission for EJ Legan to make limited appearance on behalf of Intl Brotherhood of Electrical Workers for making statement supporting PG&E application for provisional CP for plant. (1 page(s), 1/22/1968)
- ML20151X306 - Forwards US Fish & Wildlife Svc rept containing comments & recommendations on radiological & non-radiological effects of proposed reactor facility for info,in ref to application for CP & facility license.W/o encl. (2 page(s), 9/15/1967)
- ML20151X022 - Forwards request for addl info re instrumentation,control & power sys to support 670116 applicatiion for CP & license. (5 page(s), 5/18/1967)
- ML20151X057 - Reports on completion of review of application by util for authorization to construct plant & informs that ACRS believes that proposed reactor can be constructed w/ reasonable assurance of operation w/o risk to public safety. (4 page(s), 6/15/1967)
- ML20151X798 - Forwards draft rept transmitted on 671206 to ACRS & Amends 8 & 9 (Suppls 7 & 8) for plant.Final AEC safety evaluation w/ recipient rept need completion by 671231 in event that ACRS will furnish rept in early Dec.W/o encl. (1 page(s), 12/12/1967)
- ML20151X037 - Forwards request for addl info re site,plant layout, containment structural design,instrumentation,control,power sys,plant sys,ESFs & accident analysis. (19 page(s), 6/30/1967)
- ML20151W834 - Forwards Vols I & II of PSAR filed bu PG&E for proposed const & operation of PWR at util site & requests rept re features of proposed reactor operation likely to cause radiological effects on fish & shellfish by 670415.W/o encl. (1 page(s), 2/6/1967)
- ML20151W945 - Forwards Vols I & II of PSAR filed by PG&E for proposed const & operation of PWR at Diablo Canyon site & requests rept on meteorological aspects of proposed reactor location which might have bearing on agency safety review.W/o encl. (1 page(s), 2/6/1967)
- ML20151X882 - Informs of review completion of & provides additions to proposed findings of fact & conclusions of law submitted by PG&E,dtd 680222. (18 page(s), 2/28/1968)
- ML20151X125 - Suppl draft "Adequacy of Structural Criteria for Diablo Canyon Site Nuclear Plant." (13 page(s), 9/7/1967)
- ML20151X719 - AEC safety evaluation in matter of licensee plant. (55 page(s), 1/23/1968)
- ML20151X436 - "US AEC Div of Reactor Licensing Rept to ACRS in matter of PG&E Diablo Canyon Nuclear Plant,Rept 2," for use by ACRS at Dec 1967 meeting. (23 page(s), 11/23/1967)
- ML20151X405 - Forwards US AEC Div of Licensing Rept to ACRS in matter of PG&E Diablo Canyon Nuclear Plant,Rept 2. (1 page(s), 11/23/1967)
- ML20151X585 - Forwards AEC safety evaluation in captioned proceeding, including repts of ACRS & consultants & notices of appearance for staff counsel. (2 page(s), 1/23/1968)
- ML20151W976 - Requests listed svc for Commission per conditions of Contract AT(49-5)2667 re proposed const of PWR by PG&E at Diablo Canyon site,including rept on analyses of engineering factors by 670415. (1 page(s), 2/14/1967)
- ML20151X076 - Forwards preliminary statement from State of CA re granting of Certificate of Public Convenience & Necessity to PG&E for info. (11 page(s), 7/14/1967)
- ML20151X067 - Requests addl info on applicant financial qualifications re re application for authorization to construct & operate PWR at Diablo Canyon site. (2 page(s), 7/11/1967)
- ML20151X821 - Forwards topical index to application & amends.W/o encl. (73 page(s), 1/26/1968)
- ML20151X755 - Submits NM Newmark & WJ Hall formulated questions resulting from 671003-05 meetings in Bethesda,MD & Washington,DC re plant reactor internals,piping & vessels.Requests answers to subj questions to finalize rept on util license application. (2 page(s), 10/6/1967)
- ML20151X087 - Requests for listed supplemental info re 670116 application for CP & facility license,including conformance of proposed design to Commission 670711 GDC & objectives of R&D programs. (2 page(s), 8/31/1967)
- ML20151X119 - Transmits suppl draft rept to AEC, "Adequacy of Structural Criteria for Diablo Canyon Site Nuclear Plant," dtd 670907 for ACRS review. (1 page(s), 9/15/1967)
- ML20151X381 - Requests responses to encl ACRS questions re application for CP & facility license for nuclear power plant at Diablo Canyon site. (3 page(s), 11/1/1967)
- ML20151X466 - Forwards PG&E 671206 & 671130 ltrs transmitting Amends 9 & 8 to Diablo Canyon PSAR,respectively for ACRS review.Amends 9 & 8 include Suppls 8 & 7,respectively.W/o encl. (1 page(s), 12/7/1967)
- ML20151X322 - Informs of forwarding agency rept containing comments & recommendations on both radiological & non-radiological effects of proposed operation of nuclear power reactor at Diablo Canyon site. (1 page(s), 9/19/1967)
- ML20151X461 - Forwards div 671128 rept on instrumentation for Diablo Canyon for ACRS review. (16 page(s), 11/30/1967)
- ML20151W807 - Forwards licensee 670116 ltr transmitting license application for plant & Vols I & II, "PSAR." W/o encl. (1 page(s), 1/20/1967)