Salem, Units 1 and 2, Quarterly Remedial Action Progress Report, Fourth Quarter 2009 PSEG Nuclear, LLC.
Accession Number: ML102160229
Date Released: Thursday, August 12, 2010
Package Contents
The following links on this page are to Adobe Portable Document Format (PDF) files. To obtain a free viewer for displaying this format, see our Plugins, Viewers, and Other Tools.
- ML102160180 - Salem, Units 1 and 2, Quarterly Remedial Action Progress Report, Fourth Quarter 2009 PSEG Nuclear, LLC. (117 page(s), 6/30/2010)
- ML102160209 - Salem, Units 1 and 2, Figure 1, "Station Layout." (1 page(s), 6/30/2010)
- ML102160223 - Salem, Units 1 and 2, Figure 2, "Groundwater Tritium Results." (1 page(s), 6/30/2010)
- ML102160212 - Salem, Units 1 and 2, Figure 3, "Tritium Results Beyond Unit 1 GRS Area." (1 page(s), 6/30/2010)
- ML102160208 - Salem, Units 1 and 2, Figure 4, "Water Table Elevation Contours During Operation of the Permanent System March 2009." (1 page(s), 6/30/2010)
- ML102160211 - Salem, Units 1 and 2, Figure 5, "Water Table Elevation Contours During Operation of the Permanent System May 2009." (1 page(s), 6/30/2010)
- ML102160213 - Salem, Units 1 and 2, Figure 6, "Water Table Elevation Contours During Operation of the Permanent System September 2009." (1 page(s), 6/30/2010)
- ML102160214 - Salem, Units 1 and 2, Figure 7, "Water Table Elevation Contours During Operations of the Permanent System December 2009." (1 page(s), 6/30/2010)