Date Description
12/09/10 Updated Ownership Information for the Environmental Report
12/06/10 Input and Output Files for LADTAP and GASPAR for Revision 7 of the Environmental Report
11/12/10 Input and Output Files for MACCS2 for Revision 7 of the Environmental Report
11/01/10 Submittal of Advanced Copy of the Environment Report
09/29/10 Submittal of Tiger Beetle Information and Scope of Work for Phase II Mitigation Plan in Beetle Habitat
09/17/10 Letter from UniStar Regarding the Stay Request by Maryland Department of the Environment for the Coastal Zone Management Act Federal Consistency Review
07/31/10 Baseline Stormwater Monitoring in Selected Stream Locations at Calvert Cliffs Nuclear Power Plant
03/18/10 Revised Phase II Nontidal and Stream Mitigation Plan
03/11/10 Coastal Zone Management Act Submittal