Home > NRC Library > ADAMS Public Documents
Letter forward NRC inspection report 50-219/98-12 re engineering inspection conducted on Dec. 14-189, 1998, Jan. 6-7, 1999 and Jan. 20-22, 1999. No response to this letter is required.
Accession Number: ML993490026
Date Released: Tuesday, March 9, 1999
Package Contents
The following links on this page are to Adobe Portable Document Format (PDF) files. To obtain a free viewer for displaying this format, see our Plugins, Viewers, and Other Tools.
- ML993490022 - Letter forward NRC inspection report 50-219/98-12 re engineering inspection conducted on Dec. 14-189, 1998, Jan. 6-7, 1999 and Jan. 20-22, 1999. No response to this letter is required. (3 page(s), 3/4/1999)
- ML993490024 - Inspection report 50-219/98-12 conducted on Dec. 14-18, 1998, Jan. 6-7, 1999 and Jan. 20-22, 1999. No violations were noted. (21 page(s), 3/4/1999)