Sequoyah Nuclear Plant 1 and 2 Request for Alternative RV-02 - PIV Leakage (EPID L 2022-LLR-0034
Accession Number: ML22167A167
Date Released: Thursday, September 7, 2023
Package Contents
The following links on this page are to Adobe Portable Document Format (PDF) files. To obtain a free viewer for displaying this format, see our Plugins, Viewers, and Other Tools.
- ML22263A008 - Sequoyah Nuclear Plant, Units 1 and 2, Audit Summary Request for Alternative RV-02 - PIV Leakage (EPID L-2022-LLR-0034) (10 page(s), 9/28/2022)
- ML22151A010 - 2022/05/27 NRR E-mail Capture - Revised Request for Additional Information re Sequoyah Nuclear Plant Alternative Request RV-02 (EPID L-2022-LLR-0034) (6 page(s), 5/27/2022)
- ML22179A357 - Sequoyah Nuclear Plant, Units 1 & 2 - Response to Request for Additional Information Regarding American Society of Mechanical Engineers Operation and Maintenance Code, Request for Alternative RV-02 (EPID L-2022-LLR-0034) (14 page(s), 6/28/2022)
- ML22220A107 - Sequoyah Nuclear Plant, Units 1 And 2 Regulatory Audit In Support Of Review Of The Request For Alternative To American Society Of Mechanical Engineers Operation And Maintenance Code (EPID L 2022 LLR-0034) (7 page(s), 8/9/2022)
- ML22224A035 - Sequoyah Nuclear Plant, Units 1 and 2, Regulatory Audit Questions - Request for Alternative to ASME Operation and Maintenance Code Subsection ISTC-3630 (EPID L-2022-LLR-0034) (2 page(s), 8/12/2022)
- ML22263A375 - Sequoyah Nuclear Plant, Units 1 and 2 - Authorization of Alternative Request RV-02 for Pressure Isolation Valve Seat Leakage (EPID L-2022-LLR-0034) (19 page(s), 9/29/2022)
- ML22074A315 - Sequoyah Nuclear Plant, Units 1 and 2, American Society of Mechanical Engineers Operation and Maintenance Code, Request for Alternative RV-02 (10 page(s), 3/15/2022)
- ML22304A186 - Sequoyah Nuclear Plant, Unit Nos. 1 And 2 - Revised Authorization Of Alternative Request RV-02 For Pressure Isolation Valve Seat Leakage (EPID L-2022-LLR-0034) (12/1/2022)
- ML22312A352 - Sequoyah Nuclear Plant, Units 1 And 2 – Revised - Summary Of Regulatory Audit For Alternative Request RV-02 (EPID L 2021 LLR 0072) (12/1/2022)