Home > NRC Library > ADAMS Public Documents
North Anna Power Station, Units 1 & 2, Revision 56 to Updated Final Safety Analysis Report
Accession Number: ML20309A590
Date Released: Tuesday, March 23, 2021
Package Contents
The following links on this page are to Adobe Portable Document Format (PDF) files. To obtain a free viewer for displaying this format, see our Plugins, Viewers, and Other Tools.
- ML20309A588 - North Anna Power Station, Units 1 & 2, Revision 56 to Updated Final Safety Analysis Report (7 page(s), 9/30/2020)
- ML20309A594 - North Anna Power Station, Units 1 & 2, Revision 56 to Updated Final Safety Analysis Report, Frontmatter (124 page(s), 9/30/2020)
- ML20309A597 - North Anna Power Station, Units 1 & 2, Revision 56 to Updated Final Safety Analysis Report, Chapter 1, Introduction and General Description of Plant (86 page(s), 9/30/2020)
- ML20309A602 - North Anna Power Station, Units 1 & 2, Revision 56 to Updated Final Safety Analysis Report, Chapter 2, Site Characteristics (526 page(s), 9/30/2020)
- ML20309A605 - North Anna Power Station, Units 1 & 2, Revision 56 to Updated Final Safety Analysis Report, Chapter 3, Design Criteria - Structures, Components, Equipment, and Systems (1438 page(s), 9/30/2020)
- ML20309A607 - North Anna Power Station, Units 1 & 2, Revision 56 to Updated Final Safety Analysis Report, Chapter 4, Reactor (356 page(s), 9/30/2020)
- ML20309A596 - North Anna Power Station, Units 1 & 2, Revision 56 to Updated Final Safety Analysis Report, Chapter 5, Reactor Coolant System (438 page(s), 9/30/2020)
- ML20309A608 - North Anna Power Station, Units 1 & 2, Revision 56 to Updated Final Safety Analysis Report, Chapter 6, Engineered Safety Features (404 page(s), 9/30/2020)
- ML20309A613 - North Anna Power Station, Units 1 & 2, Revision 56 to Updated Final Safety Analysis Report, Chapter 7, Instrumentation and Control (232 page(s), 9/30/2020)
- ML20309A612 - North Anna Power Station, Units 1 & 2, Revision 56 to Updated Final Safety Analysis Report, Chapter 8, Electric Power System (84 page(s), 9/30/2020)
- ML20309A593 - North Anna Power Station, Units 1 & 2, Revision 56 to Updated Final Safety Analysis Report, Chapter 9, Auxiliary Systems (430 page(s), 9/30/2020)
- ML20309A606 - North Anna Power Station, Units 1 & 2, Revision 56 to Updated Final Safety Analysis Report, Chapter 10, Steam and Power Conversion System (110 page(s), 9/30/2020)
- ML20309A595 - North Anna Power Station, Units 1 & 2, Revision 56 to Updated Final Safety Analysis Report, Chapter 11, Radioactive Waste Management (362 page(s), 9/30/2020)
- ML20309A598 - North Anna Power Station, Units 1 & 2, Revision 56 to Updated Final Safety Analysis Report, Chapter 12, Radiation Protection (104 page(s), 9/30/2020)
- ML20309A610 - North Anna Power Station, Units 1 & 2, Revision 56 to Updated Final Safety Analysis Report, Chapter 13, Conduct of Operations (20 page(s), 9/30/2020)
- ML20309A600 - North Anna Power Station, Units 1 & 2, Revision 56 to Updated Final Safety Analysis Report, Chapter 14, Initial Tests and Operation (76 page(s), 9/30/2020)
- ML20309A603 - North Anna Power Station, Units 1 & 2, Revision 56 to Updated Final Safety Analysis Report, Chapter 15, Accident Analyses (494 page(s), 9/30/2020)
- ML20309A609 - North Anna Power Station, Units 1 & 2, Revision 56 to Updated Final Safety Analysis Report, Chapter 16, Technical Specifications and Requirements (10 page(s), 9/30/2020)
- ML20309A601 - North Anna Power Station, Units 1 & 2, Revision 56 to Updated Final Safety Analysis Report, Chapter 17, Quality Assurance Program (4 page(s), 9/30/2020)
- ML20309A599 - North Anna Power Station, Units 1 & 2, Revision 56 to Updated Final Safety Analysis Report, Chapter 18, Programs and Activities That Manage the Effects of Aging (48 page(s), 9/30/2020)