Partial response to FOIA request for documents.Forwards App C & D documents.Documents also available in PDR.
Accession Number: ML20236J368
Date Released: Tuesday, October 6, 2020
Package Contents
The following links on this page are to Adobe Portable Document Format (PDF) files. To obtain a free viewer for displaying this format, see our Plugins, Viewers, and Other Tools.
- ML20236J366 - Partial response to FOIA request for documents.Forwards App C & D documents.Documents also available in PDR. (6 page(s), 7/29/1987)
- ML20236N334 - Responds to 770805 note requesting NRC comments on F Chase concerns re role of NRC in licensing review.No pressure applied upon USGS. (7 page(s), 8/30/1977)
- ML20236J804 - Forwards for filing,amended & consolidated petition to intervene on oru behalf & on behalf of Luigi Marre Land & Cattle Co & San Luis Obispo Bay Properties,Inc. (1 page(s), 4/30/1973)
- ML20236P399 - Informs that NRC issued order extending const completion dates contained in CPPR-39 to 770101.Application for extension of CP,Commission order & staff evaluation encl. (1 page(s), 7/7/1976)
- ML20236L279 - Motion requesting AEC to review ASLAB 710614 decision re PG&E application for CP.Supporting documentation encl. (7 page(s), 6/23/1971)
- ML20236P406 - Forwards application for extension of completion date in CPPR-39 from 760701 to 770101. (1 page(s), 5/25/1976)
- ML20236J587 - Forwards responses to questions raised during 771006 meeting in Bethesda,MD re review of application for Amend 52 to application for OL. (3 page(s), 10/14/1977)
- ML20244B446 - Advises that CA Energy Commission unanimously approved motion re expeditious licensing for facility.Requests info re procedures to be followed by NRC in making final determination. (2 page(s), 3/10/1977)
- ML20236K327 - Amend to 710709 supplemental motion to ASLAB for reconsideration re PG&E application for permit to construct Unit 2. (2 page(s), 7/28/1971)
- ML20237F810 - Summary of 750131 meeting w/USGS in Denver,CO re geology & seismology input to Diablo Canyon SER.Attendees list encl. W/o encl. (3 page(s), 2/24/1975)
- ML20236L689 - Reply to AEC Regulatory Staff 700930 supplemental proposed findings of fact & conclusions of law re field tests & measurements. (2 page(s), 10/16/1970)
- ML20236L986 - Supplemental proposed findings of fact & conclusions of law. Seismic design for unit adequate.Certificate of Svc encl. (12 page(s), 9/4/1970)
- ML20237G186 - Forwards Vols I & II of util PSAR for proposed const & operation of PWR at Duablo Canyon site,per understandings reflected in Chairman Seaborg 631003 ltr to Admiral Karo. Requests results of review re seismology.W/o encl. (1 page(s), 2/6/1967)
- ML20237G013 - Discusses ACRS 92nd meeting on 671207-09.ACRS completed review of PG&E application for const of nuclear unit at Diablo Canyon site.Facility can be constructed w/o risk to public health & safety. (5 page(s), 12/20/1967)
- ML20236N085 - Answer to 760621 interrogatories.Affidavits of B Siegel, R Hofmann,J Sears,J Delaney,D Allison,C Stepp,M Parsont, M Fliegel,K Murphy & M Goldman & Certificate of Svc encl. (42 page(s), 7/8/1976)
- ML20236L420 - Brief opposing exceptions to initial decision of ASLB filed by Scenic Shoreline Preservation Conference,Inc.Request should be denied. (19 page(s), 1/12/1971)
- ML20236M777 - "Diablo Canyon Nuclear Plant Site Preliminary Geologic Investigation." (5 page(s), 1/25/1966)
- ML20236N193 - Responds to recepient 740109 ltr to Ray.May & Dec 1972 hearings limited to environ review.Petitions to intervene re geological & seismological bases filed & pending before ASLB.Safety evaluation to be issued in Jul 1974. (2 page(s), 1/29/1974)
- ML20236N286 - Petition of JJ Forster & L Valentine for leave to intervene. (4 page(s), 11/20/1973)
- ML20237G088 - Summary of 670516 meeting w/util,ACRS & AEC consultants re discussions of seismic design of Diablo Canyon reactor. Meeting attended by listed persons. (2 page(s), 5/25/1967)
- ML20236P275 - Requests info re current status of Diablo Canyon facility & procedural schedule,prospects for licensing & bringing plant on line. (1 page(s), 3/25/1977)
- ML20266J661 - "SURFACE GEOLOGY AT MOUTH OF DIABLO CANYON SAN LUIS OBISPO COUNTY." (1 page(s), 9/27/1965)
- ML20236P438 - Evaluation of applicant 760525 request for extension of CPPR-39 to 770101. (2 page(s), 7/6/1976)
- ML20237F969 - Initial decision authorizing director of regulation to issue CP for facility. (40 page(s), 12/8/1970)
- ML20236L474 - Forwards exceptions to initial decision & briefs to commission, per 10CFR2.762 as appeal of ASLB decision to grant provisional CP for Unit 2.Certificate of Svc encl. (3 page(s), 12/30/1970)
- ML20236L931 - Forwards supplemental proposed findings of fact & conclusions of law submitted by util & Maps A,B,C,F.W/o encls. (1 page(s), 9/4/1970)
- ML20236P463 - Forwards review of geologic & seismologic data relevant to plant,per request. (17 page(s), 4/29/1976)
- ML20237F820 - Forwards track chart & inshore ends of seismic reflection Profiles 10-24,obtained by USGS aboard USNS Bartlett in 1972,per 740722 telcon.Bartlett profiles being used in review if geologic conditions at plant. (1 page(s), 7/22/1974)
- ML20236P423 - Application for extension of CPPR-39 from 760701 to 770101. (2 page(s), 5/25/1976)
- ML20236N032 - Affidavit of D Bridenbaugh re ground acceleration at site near Hosgri fault.Related correspondence. (7 page(s), 9/8/1976)
- ML20237G164 - Discusses 670323 telcon between H Coulter,L Murphy,W Hall, N Newmark,F Schauer,R Tedesco,J Newell & I Spickler re earthquake design considerations for plant. (2 page(s), 3/30/1967)
- ML20236L922 - Supplemental statement by R Vrana re 700807 testimony before ASLB in San Luis Obispo,CA. (8 page(s), 9/5/1970)
- ML20237G039 - Forwards Dept of Commerce rept on seismicity of Diablo Canyon,San Luis Obispo County,CA.Applicant PSAR satisfactory w/respect to distant & nearby earthquakes. earthquakes. (3 page(s), 9/21/1967)
- ML20237G730 - Addl comments of Scenic Shoreline Preservation Conference filed after receipt of applicant proposed findings of fact & conclusions of law & request to reopen hearing. (4 page(s), 4/5/1970)
- ML20236P124 - Responds to 770519 ltr transmitting Righetti ltr,urging immediate issuance of OL on temporary basis for Diablo Canyon Nuclear Power Plant & questioning value of laws that require nearly four years to compile info to issue OL. (3 page(s), 6/13/1977)
- ML20236N139 - Response opposing San Luis Obispo Mothers for Peace 741014 motion to discovery.Motion should be denied.Certificate of Svc encl. (7 page(s), 10/23/1974)
- ML20236K384 - Affidavit of SH Mendes supporting supplemental motion by Scenic Shoreline Preservation Conference,Inc,to ASLAB re PG&E Unit 2. (6 page(s), 7/9/1971)
- ML20236L901 - Forwards for filing supplemental statement by R Vrana re testimony of 700807 hearing before ASLB in San Luis Obispo, CA.Certificate of Svc encl. (3 page(s), 9/6/1970)
- ML20236L706 - Reply of R Vrana to MG Malsch 700930 statement. (2 page(s), 10/16/1970)
- ML20236L806 - Supplemental reply to util findings of fact & conclusions of law. (3 page(s), 9/18/1970)
- ML20236K351 - Forwards supplemental motion for reconsideration including addidavit of memorandum to ASLAB for filing in compliance w/10CFR2.771. (2 page(s), 7/9/1971)
- ML20244B443 - Responds to 770310 telegram to Chairman Rowden re procedures to be followed by NRC in making final determination concerning licensing of facility.Decision to issue interim license could be reached by end of yr pending justification. (3 page(s), 3/18/1977)
- ML20236N315 - Petition of EE Apfelberg & SA Silver as representatives of San Luis Obispo Mothers of Peace for leave to intervene. (3 page(s), 11/15/1973)
- ML20236M065 - Forwards suppl to rept on seismicity of Diablo Canyon,CA area.Recent geological & seismological info re region around Unit 2 reviewed & evaluated. (7 page(s), 6/12/1970)
- ML20236P166 - Forwards E Righetti ltr re concern about plant.E Righetti feels permit should be issued immediately on temporary basis,to operate plant. (1 page(s), 5/19/1977)
- ML20236N115 - Response opposing motion by San Luis Obispo Mothers for Peace seeking stop work order.Motion simply intemperate rehash of similar pleading filed by Scenic Shoreline Preservation Conference,Inc on 731205 & should be denied. (1 page(s), 10/23/1974)
- ML20237F986 - Advises that author reviewed rept to AEC dtd Dec 1967 & compared copy w/draft prepared by author,per RS Boyd 680116 request.Original draft indicates suppl should be added but listed statement may not be important. (1 page(s), 1/22/1968)
- ML20236N015 - Responds to 770614 & 0527 ltrs expressing concern about delays in licensing of plant.Util must complete work on important technical issues before record can be completed. (2 page(s), 6/30/1977)
- ML20236P076 - Forwards FA Chase ltr re concerns about plant. (1 page(s), 8/5/1977)
- ML20237G000 - "Adequacy of Structural Criteria for Diablo Canyon Site Nuclear Plant." (12 page(s), 12/31/1967)
- ML20236L647 - Forwards reply to AEC Regulatory Staff 700930 supplemental proposed findings of fact & conclusions of law & reply of R Vrana to MG Malsch 700930 statement.Certificate of Svc encl. (3 page(s), 10/16/1970)
- ML20236L565 - Exceptions to initial decision & briefs to Commission,per 10CFR2.762.Issuance of provisional CP should be rescinded on grounds that ASLB failed to grant intervenors adequate hearings. (22 page(s), 12/30/1970)
- ML20236N255 - Repsonse opposing Scenic Shoreline Preservation Conference, Inc petition to suspend const of plant.Certificate of Svc encl. (6 page(s), 12/24/1973)
- ML20237G207 - Forwards request for preliminary site review re seismological characteristics of proposed reactor location by Nov 1966,per Seaborg 631003 ltr to Admiral Karo.W/nine oversize drawings. (35 page(s), 10/7/1966)
- ML20236J841 - Amended & consolidated petition for leave to interevene. Affidavit of F Eissler & Certificate of Svc encl. (16 page(s), 5/1/1973)
- ML20236M771 - "PG&E Meteorology Ofc Rept on Diablo Canyon Site,San Luis Obispo County." (18 page(s), 9/29/1966)
- ML20236J622 - Rev 0 to Surveillance Test Procedure V-5, "ECCS Check Valve Leak Test," (53 page(s), 11/24/1976)
- ML20266J660 - "LOCATION GEOLOGIC EXPLORATION TRENCHES DIABLO CANYON." (1 page(s), 8/27/1966)
- ML20236M681 - Forwards AEC Regulatory Staff proposed findings of fact & conclusions of law,including new Paragraghs 29-31 dealing w/ intervenors & mods which include revised ordering paragraphs. (21 page(s), 4/13/1970)
- ML20266J669 - "GEOLOGIC SECTION - SWITCH YARD AREA DIABLO CANYON NUCLEAR PLANT SITE SAN LUIS OBISPO COUNTY." (1 page(s), 12/6/1965)
- ML20236L316 - Decision authorizing issuance of CP to PG&E for pressurized water nuclear power reactor.Initial decision constitutes final action of Commission on 710629. (27 page(s), 6/14/1971)
- ML20236J985 - Answer of PG&E to petition for leave to intervene filed bu Scenic Shoreline Preservation Conference,Inc.Certificate of Svc encl. (6 page(s), 2/9/1973)
- ML20236M007 - Order reopening hearing,per Scenic Shoreline Preservation Confernece,Inc 700405 request. (2 page(s), 7/15/1970)
- ML20236L228 - Forwards motion to AEC. (1 page(s), 6/23/1971)
- ML20236L866 - Forwards Maps D & E depicting location of certain onshore faults in general vicinity of Unit 2 site & location of certain offshore epicenters,respectively.W/o encl. (2 page(s), 9/18/1970)
- ML20236L364 - Brief opposing exceptions of Scenic Shoreline Preservation Conference,Inc. to initial decision.AEC Staff believes relief requested by Conference should be denied & exceptions to initial decision should be rejected. (28 page(s), 1/21/1971)
- ML20236K563 - Petition for reconsideration to ASLAB to recind util CP until util & Commission comply w/NEPA of 1969 & Water Quality Improvement Act of 1970. (2 page(s), 7/2/1971)
- ML20236M024 - Forwards supplemental rept from US Coast & Geodetic Survey. (1 page(s), 6/15/1970)
- ML20236L724 - Motion for reopening of hearing to place data in record & provide opportunity for cross-examination of witnesses on subjs raised in documents. (3 page(s), 10/16/1970)
- ML20266J666 - "SURFACE GEOLOGY - SWITCH YARD AREA DIABLO CANYON NUCLEAR PLANT SITE SAN LUIS OBISPO COUNTY." (1 page(s), 7/29/1987)
- ML20236K057 - Forwards amend to supplemental motion for reconsideration to ASLAB,for filing in compliance w/10CFR2.771 & 2.764. Certificate of Svc encl. (2 page(s), 7/28/1971)
- ML20237F752 - Forwards "Teleseismic Location of 1927 Lompoc Earthquake" & "Aftershocks of 1927 Lompoc Earthquake" technical repts in support of util application for OL for facilities. (1 page(s), 12/1/1975)
- ML20236K008 - Supplemental reply of PG&E to Scenic Shoreline Preservation Conference,Inc.,dtd 710709.San Fernando earthquake not relevant to Diablo Canyon site.Certificate of Svc encl. (9 page(s), 7/28/1971)
- ML20236P524 - Forwards draft review of Amends 31,32 & 34 of FSAR for plant.Draft transmitted to provide basis for discussions at planned 751230 meeting in Bethesda,MD. (12 page(s), 12/24/1975)
- ML20236K422 - Forwards petition for reconsideration to ASLAB for filing. Certificate of Svc encl. (3 page(s), 7/2/1971)
- ML20236M725 - "Rept to ACRS in Matter of PG&E Diablo Canyon Nuclear Plant," Rept 2. (23 page(s), 11/28/1967)
- ML20237F830 - Summary of 740705 meeting w/util & Earth Sciences Assoc in San Francisco re review of progress of offshore geological investigations initiated by util.Attendees list & summary of facility offshore seismic interpretation progress encl. (5 page(s), 7/11/1974)
- ML20236P051 - Advises that encl response to Senator A Cranston late because it took longer than 4 days to draft response & obtain concurrences. (1 page(s), 8/5/1977)
- ML20236M744 - "Preliminary Site Rept." (14 page(s), 9/30/1966)
- ML20236J671 - Forwards proprietary velocity data re Western Geophysical Co offshore geophysical survey records to support application for OL.Encl withheld (ref 10CFR2.790). (2 page(s), 3/26/1976)
- ML20266J663 - "GEOLOGIC SECTIONS DIABLO CANYON NUCLEAR PLANT SITE SAN LUIS OBISPO COUNTY,CALIFORNIA." (1 page(s), 7/31/1965)
- ML20237G067 - Summary of 670815 meeting w/util,Westinghouse,USC&GS, Newmark & Hall,Phillips Petroleum & JA Blume & Assoc re continued review of seismic design bases for plant. Attendees list encl. (3 page(s), 8/17/1967)
- ML20237F794 - Summary of 750828 meeting w/util in Bethesda,MD re forthcoming geology & seismology submital for facilities. Attendees list encl. (3 page(s), 10/30/1975)
- ML20237G106 - Discusses 670406 telcon w/D Kelly re confirmation of meeting on 670420-21 to discuss facility reactor.AEC will submit meeting agenda & items & comments to be discussed during meeting. (1 page(s), 4/17/1967)
- ML20236N208 - Answer to 740114 petition for leave to intervene filed by JJ Forster & L Valentine.Petition should be denied. Certificate of Svc encl. (10 page(s), 1/23/1974)
- ML20236L756 - Forwards reply to P Crane 700904 statement by R Vrana on util findings of fact & conclusions of law & Scenic Shoreline supplemental reply to util findings of fact & conclusions of law.Certificate of Svc encl. (3 page(s), 9/18/1970)
- ML20237G059 - Forwards review of geologic & hydrologic aspects of PG&E license application for Diablo Canyon site,per EG Case 670206 request. (3 page(s), 9/21/1967)
- ML20236P251 - Responds to 770325 ltr requesting info about Diablo Canyon Nuclear Power Plant.Licensing & operation delayed pending resolution of earthquake safety questions in relation to Hosgri fault. (3 page(s), 4/15/1977)
- ML20236L787 - Reply to P Crane 700904 supplemental proposed findings of fact & conclusions of law by R Vrana re epicenters. (6 page(s), 9/16/1970)