Responds to FOIA request for documents re NRC review of Quadrex Corp analysis of South Texas plant.Records listed on encl App A as Items 1-92 being placed in PDR.Forwards App A documents.Addl documents subj to request being reviewed.
Accession Number: ML20137X502
Date Released: Saturday, May 30, 2020
Package Contents
The following links on this page are to Adobe Portable Document Format (PDF) files. To obtain a free viewer for displaying this format, see our Plugins, Viewers, and Other Tools.
- ML20137X497 - Responds to FOIA request for documents re NRC review of Quadrex Corp analysis of South Texas plant.Records listed on encl App A as Items 1-92 being placed in PDR.Forwards App A documents.Addl documents subj to request being reviewed. (8 page(s), 1/6/1986)
- ML20137X545 - Summary of 810908 meeting w/util at Region IV ofc re results of review of Brown & Root engineering performed by Quadrex Corp.Meeting attendees listed.Related info encl. (131 page(s), 9/11/1981)
- ML20137X521 - Procedure STP-DC-021-D, "Engineering Procedure for Engineering Design Deficiencies." (22 page(s), 6/17/1985)
- ML20137X563 - Discusses investigation re Quadrex rept (50-498/82-02 & 50-499/82-02).Rept will be forwarded for referral to Ofc of Inspector & Auditor.Summary of Brown & Root findings on Quadrex engineering review encl. (116 page(s), 4/29/1982)
- ML20137X540 - Rev 1 to Project Engineering Procedure PEP-11, "Reporting Design & Const Deficiencies to NRC." Related info encl. (58 page(s), 5/16/1980)
- ML20137X511 - Testimony of HS Phillips re util sys for reporting design & const deficiencies. (4 page(s), 6/21/1985)
- ML20137X516 - Rev 1 to Project Engineering Procedure PEP-11, "Reporting Design & Const Deficiencies to NRC." (16 page(s), 3/27/1980)
- ML20137X526 - Forwards analysis applying new policy & procedures to current investigation of whether util deliberately withheld Quadrex rept from NRC. (10 page(s), 4/28/1981)
- ML20137X576 - Forwards revised pages to util 820826 submittal of final rept for Work Package EN-619.Tables 2.1.3-1,2 & 3 revised to more accurately reflect resolution action required for dispositioned findings. (22 page(s), 10/15/1982)
- ML20137X552 - Clarifies erroneous statement re minutes of 770419 meeting in author 770420 transmittal & provides addl info re pipe break criteria.Second paragraph of minutes should read as Brammer concurred w/Klapper.Input data & related info encl. (415 page(s), 6/9/1977)
- ML20137X584 - Summarizes review of Quadrex rept issues & Region IV submittal of assessments & conclusions. (2 page(s), 11/5/1982)
- ML20137X503 - Testimony of HS Phillips re discovery of Quadrex rept. Related info encl. (10 page(s), 6/25/1985)
- ML20137X569 - First interim deficiency rept re classification of leak detection sys in safety injection sys (SIS)/containment spray sys pump cubicles.Initially reported on 820701.Next rept will be submitted by 820820.Related info encl. (42 page(s), 7/29/1982)
- ML20137X532 - "Assessment of Findings in Quadrex Corp Rept dtd May 1981." (264 page(s), 3/31/1982)
- ML20137X589 - Rev 1 to Procedure 2744P/0444P, "Transition Procedure - Engineering." Related info encl. (37 page(s), 5/12/1982)