- ML20133B565 - Partial response to FOIA request for four categories of documents re facility.Forwards App A documents.Documents also available in PDR.App B documents already available in PDR.Search continuing. (4 page(s), 5/10/1985)
- ML20132C645 - Informs of visit w/Bechtel in Gaithersburg,MD in support of Region IV re structural steel welding at facility. Applicant approach adequate to address most types of defects & should provide reasonable assurance of weld integrity. (4 page(s), 1/7/1985)
- ML20132C715 - Summarizes 850204 discussions re appropriateness of NDT methods for structural steel fillet weldments.Magnetic particle testing only appropriate method other than visual insp for small fillet welds. (2 page(s), 2/14/1985)
- ML20132C719 - Forwards summary of events leading to applicant decision to reinspect 100% of safety-related structural steel weldments, basis for exam of coatings & results of NRC insp of sample paint-stripped joints.Welds & joints adequate. (12 page(s), 2/14/1985)
- ML20132C755 - Approves Regions I & IV final draft insp repts re structural steel welding.Adequate steps taken to insure integrity of weldments.Issue considered resolved. (26 page(s), 3/4/1985)
- ML20132C740 - Discusses differences between insps of structural steel welds at Zimmer & Wolf Creek.Wolf Creek welds inspected,QA program functioning & documentation accurate.Missing welds due to misinterpretation of drawings & human error. (2 page(s), 2/25/1985)
- ML20133B738 - "Structural Steel Welding Presentation." (46 page(s), 2/27/1985)
- ML20132C691 - Forwards technical evaluation of weld overrun responsive to Region IV 841102 request for technical assistance.SB Kim 841119 memo providing review of Bechtel corrective actions re weld deficiencies encl,per visit. (4 page(s), 2/1/1985)
- ML20133B641 - Discusses receipt of clearance from R Herr on 830831 to release summary & cover sheet to facility Investigation 4-83-05 (4-83-a-20).Allegation reviews encl. (4 page(s), 9/2/1983)
- ML20132C638 - Forwards SSER on FSAR rev re structural steel welding.Rev acceptable. (2 page(s), 12/26/1984)