Responds to FOIA request for ten categories of documents. Forwards Documents 1-8 & 10.Documents also available in PDR. Document 9 not located.
Accession Number: ML20028D960
Date Released: Sunday, November 8, 2020
Package Contents
The following links on this page are to Adobe Portable Document Format (PDF) files. To obtain a free viewer for displaying this format, see our Plugins, Viewers, and Other Tools.
- ML20028D959 - Responds to FOIA request for ten categories of documents. Forwards Documents 1-8 & 10.Documents also available in PDR. Document 9 not located. (1 page(s), 12/13/1982)
- ML20028D976 - Notifies of extension of latest completion date of facilities due to listed const delays. (2 page(s), 10/28/1975)
- ML20028D966 - Forwards application to amend CPPR-39 & CPPR-69,extending const completion date to 760701 & 770731,respectively. (1 page(s), 5/19/1975)
- ML20028D978 - Notifies that schedule for fuel loading revised due to listed delays. (2 page(s), 8/30/1973)
- ML20028D982 - Application to amend CPPR-83 & CPPR-84,extending time for const completion to 760201 & 0301,respectively,due to increased delivery time of matls & components. (3 page(s), 12/30/1975)
- ML20028D971 - Notifies that const completion schedule for facilities updated.Fuel loading will be Mar & Nov 1978,respectively. (1 page(s), 2/24/1977)
- ML20028D987 - Responds to 771013 request for addl info re 770922 application to extend CPPR-99 & CPPR-100.Bar graph schedule indicating interrelation of various schedule factors encl. (4 page(s), 2/2/1978)
- ML20028D984 - Application to amend CPPR-83 & CPPR-84,extending time for const completion until 780801 & 790801,respectively,due to increased delivery time of matls & components. (3 page(s), 7/1/1976)
- ML20028D967 - Application to amend CPPR-39 & CPPR-69 extending const completion date to 760701 & 770731,respectively. (2 page(s), 5/19/1975)