Discusses Insp Repts 50-269/72-08,50-270/72-07 & 50-287/72-05 on 720822-25.Noncompliance noted:QA for nonconforming items re fuel handling not implemented & cable installed prior to receipt of QA documentation.
Accession Number: ML19322A656
Date Released: Saturday, November 7, 2020
Package Contents
The following links on this page are to Adobe Portable Document Format (PDF) files. To obtain a free viewer for displaying this format, see our Plugins, Viewers, and Other Tools.
- ML19322A655 - Discusses Insp Repts 50-269/72-08,50-270/72-07 & 50-287/72-05 on 720822-25.Noncompliance noted:QA for nonconforming items re fuel handling not implemented & cable installed prior to receipt of QA documentation. (6 page(s), 10/26/1972)
- ML19322A663 - Forwards Insp Repts 50-269/72-08,50-270/72-07 & 50-287/72-05 on 720822-25.Meeting w/util planned to discuss effective QA program implementation. (1 page(s), 10/26/1972)
- ML19322A671 - Insp Repts 50-269/72-08,50-270/72-07 & 50-287/72-05 on 720822-25.Noncompliance noted:failure to provide approved procedures for electrical QC & control of nonconforming items & to obtain proper documentation for installed cable. (40 page(s), 10/1/1972)
- ML19322A677 - Ack receipt of 720727 ltr providing requested info re verification of valve wall thicknesses. (1 page(s), 11/3/1972)
- ML19322A685 - Responds to AEC 720630 ltr requesting verification of min valve wall thicknesses.Unit-1 program of valve wall measurements to be completed 721201.Justification for nonconforming valve walls will be provided. (2 page(s), 7/27/1972)
- ML19322A694 - Forwards Bulletin 72-02, "Simultaneous Actuation of Safety Injection Signal on Both Units of Dual Unit Facility." Action required. (1 page(s), 10/27/1972)