Calvert Cliffs Nuclear Power Plant, Unit 3 - Response to Request for Additional Information for the RAI 330, Ultimate Heat Sink.
Accession Number: ML123620179
Date Released: Tuesday, February 5, 2013
Package Contents
The following links on this page are to Adobe Portable Document Format (PDF) files. To obtain a free viewer for displaying this format, see our Plugins, Viewers, and Other Tools.
- ML12362A149 - Calvert Cliffs Nuclear Power Plant, Unit 3 - Response to Request for Additional Information for the RAI 330, Ultimate Heat Sink. (3 page(s), 12/20/2012)
- ML12362A150 - Enclosures re Response to NRC Request for Additional Information, RAI 330, Question 09.02.05-20, Ultimate Heat Sink and Changes to COLA Associated with the Response. (79 page(s), 12/20/2012)
- ML12362A152 - Enclosures to Calvert Cliffs Nuclear Power Plant, Unit 3, FSAR: Chapter 9.0, "Water Systems," and Table of Changes to COLA. (79 page(s), 12/20/2012)