Ack receipt of 821109,830104,0215,0318,0510 & 24 ltrs informing NRC of steps taken to correct violations noted in IE Insp Repts 50-390/82-05 & 50-391/82-03.QA program for heat tracing on safety-related piping adequate.
Accession Number: ML082321693
Date Released: Thursday, October 24, 2024
Package Contents
The following links on this page are to Adobe Portable Document Format (PDF) files. To obtain a free viewer for displaying this format, see our Plugins, Viewers, and Other Tools.
- ML082321692 - Ack receipt of 821109,830104,0215,0318,0510 & 24 ltrs informing NRC of steps taken to correct violations noted in IE Insp Repts 50-390/82-05 & 50-391/82-03.QA program for heat tracing on safety-related piping adequate. (2 page(s), 8/9/1983)
- ML082321694 - Forwards IE Insp Repts 50-390/82-05 & 50-391/82-03 on 820614-25 & notice of violation. (2 page(s), 8/26/1982)
- ML082321695 - Notice of violation from insp on 811221,820129 & 0614-25. (3 page(s), 8/26/1982)
- ML082321698 - IE Insp Repts 50-390/82-05 & 50-391/82-03 on 811221-820129 & 0614-25.Noncompliance noted:inadequate corrective action re QA program controls & failure to identify responsibilites affecting safety-related functions. (16 page(s), 8/24/1982)
- ML082321699 - Forwards addl info per 821109 response to violations noted in IE Insp Repts 50-390/82-05 & 50-391/82-03.Summary of improvements addressing prompt identification of deficiencies & root cause remedy encl. (5 page(s), 1/4/1983)
- ML082321700 - Revises 821109 response to violations noted in IE Insp Repts 50-390/82-05 & 50-391/82-03.Programmatic improvements implemented. (12 page(s), 2/15/1983)
- ML082321702 - Revises 821109 & 830104 & 0215 ltrs addressing operating & monitoring procedure inadequacies identified in IE Insp Repts 50-390/82-05 & 50-391/82-03.Operating logs & SOIs will be reviewed. (3 page(s), 3/18/1983)
- ML082321703 - Advises that because of 830330 closure date for Engineering Change Notice 3182,corrective action per IE Insp Repts 50-390/82-05 & 50-391/82-03 now scheduled for completion by 830715. (1 page(s), 5/10/1983)
- ML082321704 - Suppls/revises 821109 & 830104,0215,0318 & 0510 responses to violations noted in IE Insp Repts 50-390/82-05 & 50-391/82-03.NCR 3898R dispositioned 820217 to require line rework & drawing rev to indicate Class C process piping. (7 page(s), 5/24/1983)
- ML082321705 - Advises that work needed to complete Engineering Change Notice 3182,per IE Insp Repts 50-390/82-05 & 50-391/82-03 delayed until 830930.Delay due to limited access to work area caused by hot functional testing. (2 page(s), 7/14/1983)
- ML082321706 - Forwards response to violations identified in IE Insp Repts 50-390/82-05 & 50-391/82-03.Programmatic QA improvements summarized. (23 page(s), 11/9/1982)