The NRC is modernizing nrc.gov with an updated design and improved navigation to enhance usability. We are committed to a smooth transition and will work to minimize any disruption. The site may be briefly unavailable at times during launch. Thank you for your patience.
Power Reactor Status Report for October 18, 2015
UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Beaver Valley 1 | 100 | ||||
| Beaver Valley 2 | 0 | 09/25/2015 | REFUELING OUTAGE - CORE RELOAD IN PROGRESS | ||
| Calvert Cliffs 1 | 100 | HIGH SYSTEM VOLTAGE ACTION | |||
| Calvert Cliffs 2 | 100 | HIGH SYSTEM VOLTAGE ACTION | |||
| FitzPatrick | 100 | ||||
| Ginna | 93 | COASTDOWN TO REFUELING OUTAGE | |||
| Hope Creek 1 | 100 | HIGH SYSTEM VOLTAGE ACTION | |||
| Indian Point 2 | 100 | ||||
| Indian Point 3 | 100 | ||||
| Limerick 1 | 100 | ||||
| Limerick 2 | 100 | ||||
| Millstone 2 | 0 | 10/03/2015 | REFUELING OUTAGE | ||
| Millstone 3 | 100 | ||||
| Nine Mile Point 1 | 100 | ||||
| Nine Mile Point 2 | 100 | ||||
| Oyster Creek | 100 | ||||
| Peach Bottom 2 | 100 | MAINTAIN < 100 MVARS ON UNIT 2 | |||
| Peach Bottom 3 | 0 | 09/20/2015 | REFUELING OUTAGE | ||
| Pilgrim 1 | 100 | ||||
| Salem 1 | 100 | ||||
| Salem 2 | 100 | ||||
| Seabrook 1 | 0 | 09/30/2015 | REFUELING OUTAGE | ||
| Susquehanna 1 | 100 | HIGH SYSTEM VOLTAGE ACTION | |||
| Susquehanna 2 | 100 | HIGH SYSTEM VOLTAGE ACTION | |||
| Three Mile Island 1 | 100 | HIGH SYSTEM VOLTAGE ACTION |
Region 2
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Browns Ferry 1 | 100 | ||||
| Browns Ferry 2 | 100 | ||||
| Browns Ferry 3 | 100 | ||||
| Brunswick 1 | 92 | REDUCED POWER FOR ROD PATTERN ADJUSTMENT | * | ||
| Brunswick 2 | 100 | ||||
| Catawba 1 | 100 | ||||
| Catawba 2 | 100 | ||||
| Farley 1 | 100 | ||||
| Farley 2 | 100 | ||||
| Harris 1 | 100 | ||||
| Hatch 1 | 100 | ||||
| Hatch 2 | 100 | ||||
| McGuire 1 | 100 | ||||
| McGuire 2 | 100 | ||||
| North Anna 1 | 100 | ||||
| North Anna 2 | 100 | ||||
| Oconee 1 | 100 | ||||
| Oconee 2 | 0 | 10/16/2015 | REFUELING OUTAGE | * | |
| Oconee 3 | 100 | ||||
| Robinson 2 | 100 | ||||
| Saint Lucie 1 | 100 | ||||
| Saint Lucie 2 | 0 | 09/07/2015 | REFUELING OUTAGE | ||
| Sequoyah 1 | 100 | ||||
| Sequoyah 2 | 97 | COASTDOWN TO REFUELING OUTAGE | * | ||
| Summer | 0 | 10/02/2015 | REFUELING OUTAGE | ||
| Surry 1 | 0 | 10/13/2015 | RX TRIP - EN #51467 | ||
| Surry 2 | 90 | COASTDOWN TO REFUELING OUTAGE | |||
| Turkey Point 3 | 50 | REDUCE POWER FOR REFUELING OUTAGE | * | ||
| Turkey Point 4 | 100 | ||||
| Vogtle 1 | 0 | 09/20/2015 | REFUELING OUTAGE | ||
| Vogtle 2 | 100 | ||||
| Watts Bar 1 | 0 | 09/20/2015 | REFUELING OUTAGE |
Region 3
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Braidwood 1 | 100 | ||||
| Braidwood 2 | 0 | 10/04/2015 | REFUELING OUTAGE - FUEL MOVEMENT IN PROGRESS | ||
| Byron 1 | 100 | ||||
| Byron 2 | 100 | ||||
| Clinton | 99 | 100% ELECTRICAL CAPABILITY | |||
| D.C. Cook 1 | 100 | HIGH SYSTEM VOLTAGE ACTION | |||
| D.C. Cook 2 | 100 | HIGH SYSTEM VOLTAGE ACTION | |||
| Davis-Besse | 100 | HIGH SYSTEM VOLTAGE ACTION | |||
| Dresden 2 | 93 | COASTDOWN TO REFUELING OUTAGE | * | ||
| Dresden 3 | 100 | ||||
| Duane Arnold | 100 | * | |||
| Fermi 2 | 0 | 09/13/2015 | REFUELING OUTAGE | ||
| La Salle 1 | 100 | ||||
| La Salle 2 | 100 | ||||
| Monticello | 100 | ||||
| Palisades | 0 | 09/16/2015 | REFUELING OUTAGE | * | |
| Perry 1 | 100 | HIGH SYSTEM VOLTAGE ACTION | |||
| Point Beach 1 | 100 | SWITCHYARD MAINTENANCE IN PROGRESS - MAINTAIN MINIMUM 72 MVAR OUT | |||
| Point Beach 2 | 0 | 10/02/2015 | REFUELING OUTAGE - FUEL RELOAD IN PROGRESS | * | |
| Prairie Island 1 | 100 | ||||
| Prairie Island 2 | 0 | 10/16/2015 | REFUELING OUTAGE | * | |
| Quad Cities 1 | 100 | ||||
| Quad Cities 2 | 100 |
Region 4
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Arkansas Nuclear 1 | 100 | ||||
| Arkansas Nuclear 2 | 0 | 09/20/2015 | REFUELING OUTAGE | ||
| Callaway | 100 | ||||
| Columbia Generating Station | 100 | ||||
| Comanche Peak 1 | 100 | ||||
| Comanche Peak 2 | 0 | 10/03/2015 | REFUELING OUTAGE | ||
| Cooper | 100 | ||||
| Diablo Canyon 1 | 0 | 10/03/2015 | REFUELING OUTAGE | ||
| Diablo Canyon 2 | 100 | ||||
| Fort Calhoun | 100 | ||||
| Grand Gulf 1 | 100 | ||||
| Palo Verde 1 | 100 | ||||
| Palo Verde 2 | 0 | 10/09/2015 | REFUELING OUTAGE | ||
| Palo Verde 3 | 100 | ||||
| River Bend 1 | 100 | ||||
| South Texas 1 | 0 | 10/17/2015 | REFUELING OUTAGE | * | |
| South Texas 2 | 100 | ||||
| Waterford 3 | 100 | ||||
| Wolf Creek 1 | 100 |
Page Last Reviewed/Updated Tuesday, August 25, 2026
Page Last Reviewed/Updated Tuesday, August 25, 2026