475th Advisory Committee on Reactor Safeguards (ACRS) - August 29, 2000

                                                                 1
 1                      UNITED STATES OF AMERICA
 2                    NUCLEAR REGULATORY COMMISSION
 3              ADVISORY COMMITTEE ON REACTOR SAFEGUARDS
 4                                 ***
 5                            475th MEETING
 6                                 ***
 7                            Two White Flint North, Room T2-B3
 8                            11545 Rockville Pike
 9                            Rockville, MD
10                            Tuesday, August 29, 2000
11              The committee met, pursuant to notice, at 8:30
12    a.m.
13    MEMBERS PRESENT:
14         DANA A. POWERS, Chairman
15         GEORGE APOSTOLAKIS, Vice-Chairman
16         MARIO V. BONACA
17         THOMAS S. KRESS
18         GRAHAM M. LEITCH
19         ROBERT L. SEALE
20         WILLIAM J. SHACK
21         JOHN D. SIEBER
22         ROBERT E. UHRIG
23         GRAHAM B. WALLIS
24
25
.                                                                 2
 1                        P R O C E E D I N G S
 2                                                     [8:30 a.m.]
 3              DR. POWERS:  The meeting will now come to order.
 4              This is the first day of the 475th meeting of the
 5    Advisory Committee on Reactor Safeguards.
 6              During today's meeting, the committee will
 7    consider the following:
 8              Proposed risk-informed revisions to 10 CFR Part
 9    50; causes and significance of design-basis issues; proposed
10    final Regulatory Guide 1093 endorsing NEI 9704 document on
11    design basis; and the AP-1000 standard plant design.
12              We will also be examining a variety of proposed
13    ACRS reports.
14              The meeting is being conducted in accordance with
15    the provisions of the Federal Advisory Committee Act.  Dr.
16    John T. Larkins is the designated Federal official for the
17    initial portion of the meeting.
18              We have received no written comments from members
19    of the public regarding today's session.
20              We have received a request from Mr. Bob Christie
21    of Performance Technology, Incorporated, for time to make
22    oral statements regarding risk-informing 10 CFR Part 50.
23              A transcript of portions of the meeting is being
24    kept, and it is requested that speakers use one of the
25    microphones, identify themselves, and speak with sufficient
.                                                                 3
 1    clarity and volume so that they can be readily heard.
 2              I will call your attention to the document
 3    entitled "Items of Current Interest" before you, a speech by
 4    Commissioner Merrifield, and remind you of a trip report
 5    from one of our staff engineers, Noel Dudley, on the same
 6    conference.
 7              I think that makes for interesting reading.
 8              Are there any comments that members want to make
 9    in the opening of the session?
10              [No response.]
11              DR. POWERS:  Seeing none, I'll turn to the first
12    topic of business, which is the risk-informed revisions to
13    10 CFR Part 50, and Dr. Shack, will you take us through
14    this?
15              Oh, excuse me.  I have some introductions I wanted
16    to make that I forgot to do.
17              Let's see.  We have some people joining our staff
18    here.
19              First, I would like to introduce Mrs. Judith
20    Goodwin, who is coming to us from the NMSS.  She's been here
21    for -- at the agency for three years, working as office
22    automation assistant, and now you're joining us in the staff
23    secretarial position.
24              Thank you very much.  Welcome aboard.
25              And I'd like to introduce Undine Shoop.  She's
.                                                                 4
 1    joining us on a rotational assignment, and she'll be working
 2    with us in a variety of positions but most notably in the
 3    area of the resolution of the differing professional
 4    opinion.
 5              And finally, I'll mention that we have a new
 6    member, Graham Leitch, who comes to us with a tremendous
 7    background in the industry, vice president of operations and
 8    vice president at Philadelphia Electric.
 9              Welcome aboard.  Hope you're enjoying the reading.
10              Excuse me, Dr. Shack.  Go ahead.
11              DR. SHACK:  Well, I'm just sort of collecting
12    things here.
13              We were discussing the initiatives on
14    risk-informing Part 50, and there are two major initiatives
15    we're talking about, the one for risk-informing the
16    technical requirements of 10 CFR Part 50, option 3, and then
17    risk-informing the special treatment requirements, option 2.
18              There's essentially an example case of
19    risk-informing a technical requirement involving 10 CFR
20    50.54 on combustion gas control, and I'm a little confused
21    as to how the staff is going to begin the presentations,
22    whether we're going to start with option 2 -- okay, we're
23    going to start with option 2.
24              MR. REED:  I'm Tim Reed.  I'll be leading the
25    presentation today on risk-informing Part 50, option 2. 
.                                                                 5
 1    I'll be supported with Tom Bergman.  He's the lead project
 2    manager on the effort.
 3              Hopefully -- we have a very short period of time
 4    today to get through this, so I'm going to give a high-level
 5    overview of the SECY paper which we transmitted to ACRS last
 6    week, and we'll have to move through these slides pretty
 7    quickly just to get through them in the timeframe we have.
 8              The SECY paper as transmitted to you is basically
 9    a status paper, an information paper for the Commission. 
10    Its purpose to exist really is to support the September 29,
11    2000, Commission briefing that we have.
12              The paper itself is really broken into two pieces,
13    if you will.
14              The first piece addresses the ANPR comments and
15    basically just gives an overview of the comments and the
16    staff's preliminary views as they exist today on those
17    comments, and then the second piece of the SECY paper goes
18    into our conceptual approach to the rulemaking as it stands
19    today.
20              Going to the first part, then, the overview of the
21    NPR comments and our preliminary views, in general we
22    received, I guess, 11 comment letters, I believe it was, and
23    that comprised over 200-plus comments.
24              The comments, in general, were supportive of
25    risk-informing Part 50, risk-informing the special treatment
.                                                                 6
 1    requirements.
 2              In the SECY proper, in the body of the SECY, we
 3    actually go into some detail on eight issues we discuss in
 4    there, and in the attachment to the SECY, you'll see eight
 5    tables that basically take all the comments and categorize
 6    them into the tables, and you can see issues there with
 7    preliminary responses.
 8              So, a lot more detail in the attachment, some
 9    issues up in the SECY paper.
10              This is all preliminary in the SECY, and
11    everything we say today, of course, is preliminary.
12              The final responses to these ANPR comments will go
13    with the proposed rule.
14              Okay.
15              Going to the -- some of the highlights on the
16    issues that we discussed in the SECY paper, I'll touch upon
17    a few of these.
18              Selective implementation was an issue that we got
19    stakeholder comment on, and basically the comment was to --
20    suggested that there be full selectivity in 50, option 2, in
21    50.69, basically, to implement it for any of the special
22    treatment rules and for any parts of the plan in terms of
23    the systems, structures, and components.
24              On the first part, on what I'll call the rule
25    selectivity, the staff agrees, as we stand today, we do
.                                                                 7
 1    agree.  We do also acknowledge that, in fact, there may be
 2    bundles of rules that you'd have to implement, because we
 3    want to do this without exemption, so -- but in general, we
 4    agree.  We should be free to implement it for whatever set
 5    of rules licensees want to implement it for.
 6              On the second part of it, the systems side of it,
 7    we'd like to see all the -- really, this boils down to the
 8    RISC-2 SSCs.  Those would be the non-safety-related,
 9    safety-significant SSCs identified.  So, we'd like to see
10    all those identified.
11              We recognize that licensees are motivated to
12    certainly look at the unnecessary burden reduction.
13              So, they'll definitely, I think, look at
14    identifying all the RISC-3 ones.  We want to see all the
15    RISC-2 SSCs identified.
16              The second bullet here goes to discussing impact
17    on other regulations, and the comments, in fact, reflected
18    that they thought the staff did, in fact, identify the other
19    regulations where there was some impact.
20              I simply note here that probably the biggest one
21    is Part 54, the most important one.
22              We need to make sure that that is risk-informed as
23    part of this option 2 approach.
24              We got some comments on the need for prior NRC
25    review, and this really goes to how we structure the
.                                                                 8
 1    framework.
 2              These were mixed comments.  Some of the comments
 3    suggested, in fact, that there should be some prior review;
 4    others suggested no prior review; some suggested no prior
 5    review, no detail in the regulation.
 6              In fact, where we're going today is where we have
 7    been going, towards a minimal or no prior review regulatory
 8    structure, which tends to force more detail and requirements
 9    into the rule and more of a robust categorization process.
10              We're still heading there, but we certainly aren't
11    locked in.
12              We'll consider other approaches which have more
13    flexibility and less detail.
14              So, that's where we stand on that.
15              George?
16              DR. APOSTOLAKIS:  When you say prior review,
17    review of what?
18              MR. REED:  Prior review would be some submittal,
19    like a submittal to implement 50.69.  It would probably
20    involve, I think, to some extent, something on the --
21    probably in the PRA space.
22              DR. APOSTOLAKIS:  So, it would include the review
23    of the PRA?
24              MR. REED:  To some extent.
25              MR. BERGMAN:  It could.  You could do it on just
.                                                                 9
 1    prior review and approval of categorization, prior review
 2    and approval of treatment, or prior review and approval of
 3    both.
 4              MR. REED:  Yeah.  We're trying to avoid prior
 5    review and approval of either categorization or treatment.
 6              DR. APOSTOLAKIS:  That would presume that you
 7    trust the PRA.
 8              MR. REED:  You would have to, I think, to support
 9    the no prior review, and that's part of the problem.  We
10    recognize there's definitely difficulty with this, and I
11    think you guys are fully aware of the issues on PRA, and I'm
12    sure that's where your question is coming from.  We
13    recognize that, and like I said, it's our objective to
14    strive towards minimal review, but in fact, you know, we
15    have to recognize where PRA stands.
16              DR. APOSTOLAKIS:  Now, the second bullet -- would
17    you tell me again what -- review Part 54?  That's the
18    license renewal, right?
19              MR. REED:  Yes, that's license renewal.
20              DR. APOSTOLAKIS:  Should be risk-informed.  And
21    the staff agreed with that?  Or is that just a comment you
22    got?
23              MR. REED:  That's our preliminary position.
24              MR. BERGMAN:  In other words, we want licensees to
25    be able to do option 2 and then go into license renewal
.                                                                10
 1    without going back and redoing the whole scope as written in
 2    the current Part 54.
 3              DR. SHACK:  It's only the scope that he's talking
 4    about.
 5              MR. BERGMAN:  It's the scope of it that would be
 6    affected.
 7              MR. REED:  We wanted to be seamless, in other
 8    words that you transition into license renewal, that there's
 9    not a big perturbation, that you don't somehow revert to a
10    pre-option 2 scope.  We don't want to have that kind of
11    perturbation.
12              DR. SHACK:  I don't see that that will require a
13    rule change, will it?  Because that will become part of your
14    current licensing basis which you will carry into --
15              MR. REED:  Actually, there's mixed views on it. 
16    It could involve a scope change.  I think it's the 54.4, and
17    in fact, there's some views that you could probably do it
18    with the current Part 54.
19              We're not -- you know, we haven't nailed that down
20    yet.
21              DR. SHACK:  Okay.
22              MR. BERGMAN:  We would have to show that the
23    treatment applied to RISC-3 was sufficient to address the
24    aging management concerns that's currently provided under
25    the scope by the maintenance rule, because under option 2,
.                                                                11
 1    RISC-3 equipment is out of scope of the maintenance rule
 2    now, but all that equipment would still be -- still meets
 3    the scoping provision in Part 54.
 4              So, we have to say what provides that assurance
 5    under Part 54.
 6              DR. APOSTOLAKIS:  I can't see how your objective
 7    can be no prior review.  I mean there is no way.  You'll
 8    have to review something.
 9              I mean even if we were not aware of what's
10    happening with the ASME standard, still, wouldn't you want
11    to know how the expert panel made its decisions?
12              MR. BERGMAN:  But you can do that through
13    post-implementation.
14              MR. REED:  We'll learn some things from the pilot
15    plants, and that will also drive some of this issue, too,
16    you know, how predictable this categorization process is,
17    how repeatable, if you will, and if it's scattered, if the
18    pilots, in fact, owners group pilots get a lot of different
19    answers and a lot of scatter in the results, then I think
20    it's going to force us more into review.
21              DR. APOSTOLAKIS:  So, the key is the word "prior,"
22    not "review."
23              MR. REED:  Yeah, that's right.
24              DR. APOSTOLAKIS:  Okay.
25              MR. REED:  The last issue, then, since we're
.                                                                12
 1    already starting to hit upon it, is PRA quality.  That's a
 2    big deal, of course.
 3              In our NPR that went out, we actually, in the
 4    Appendix T piece of it, we said that you had to apply or
 5    conform to the ASME ANS standard.
 6              What we're indicating here is we will certainly
 7    accept other methods.
 8              In fact, we are currently reviewing the NEI peer
 9    certification as another method.
10              So, we're flexible.  That's all this is saying. 
11    We're not going to lock into a standard.
12              As you're well aware, we are, in fact, reviewing
13    the standard, also.
14              I will also just add a comment.  I think it's
15    obvious, but I suggest the ACRS read the SECY in detail. 
16    This is really very high-level, and you'll get a lot more
17    information out of the SECY than provided here.
18              Some additional highlights here:
19              We got some comments on the overall approach to
20    implementing this rulemaking, suggesting different phases,
21    different pieces of the special treatment requirements in
22    different phases, and currently we believe that -- we still
23    believe that we can do this in one rulemaking, putting aside
24    50.36, and we did agree with the comments on 50.36.  That's
25    the tech spec rule.
.                                                                13
 1              Other than that, we think we can do the rest of it
 2    in a single rulemaking, probably still looks like the most
 3    efficient way.
 4              50.36, though -- that's a separate effort, and
 5    that would probably be more of a configuration risk
 6    management effort, along with 50.65.  That should probably
 7    be done separate.
 8              An important piece to this, by the way, is the
 9    next two bullets, Part 21.
10              From the industry's perspective, there's a lot of
11    potential unnecessary burden reduction there, and so, in
12    this regard, we do agree with the comments that it's
13    probably true that RISC-3 SSCs wouldn't trip or wouldn't
14    exceed the notification requirements in Part 21 in terms of
15    they wouldn't create a substantial safety hazard and they
16    wouldn't exceed the tech spec safety limit, or defect or
17    deviation in one of those components, if you will, under
18    Part 20 wouldn't, in fact, cause those notification
19    requirements to be exceeded, but in fact, we still think the
20    best way to proceed here is to take RISC-33 SSCs out of the
21    scope of Part 21 and make it absolutely clear, consistent
22    with the way we're doing the other special treatment
23    requirements, to remove them from the scope of the special
24    treatment requirements, whatever it is.
25              So, that's the way we, right now, are going to
.                                                                14
 1    proceed on that.
 2              We also agree with the comments that Part 21
 3    should not apply to the non-safety-related piece.  That's
 4    the RISC-2.  These aren't basic components.  They weren't
 5    Appendix B-designed and manufactured.  We agree.
 6              But we also recognize that these are, in fact,
 7    safety significant components, and functional failures of
 8    safety significant components is generally something that
 9    the NRC is interested in.
10              So, we'll be looking at that.  We'll be looking at
11    what our current reporting requirements are, 50.72, 73,
12    whether that, in fact, captures it, whether there's industry
13    reporting like EPICS that might capture it, and if that
14    captures it, fine.
15              If not, then we'd consider whether, in fact, in
16    50.69, we had to have some sort of reporting.
17              That's all I wanted to hit on as far as the
18    high-level view of the ANPR comments, and then I'll just go
19    to the --
20              DR. SHACK:  Tim, just a question.
21              There's not a whole lot out on the treatment that
22    you're going to require for the RISC-3 components, which is
23    an interesting topic.
24              Is this review guidelines you have for the STP
25    exemption request -- is that treatment about as detailed and
.                                                                15
 1    complete as there is, or is it hidden somewhere else?
 2              MR. REED:  That's the most detailed that we have.
 3              DR. SHACK:  And what is the status of this thing? 
 4    I mean it's just sort of appended to the document I got.  Is
 5    it draft?
 6              MR. BERGMAN:  Yeah, those are draft, and we'll
 7    continue to work on them.
 8              I mean right now, that level of detail is more
 9    likely to be in a regulatory guidance document than anything
10    else, but the actual role they'll play in the rulemaking has
11    not been decided.
12              But they were provided to South Texas to aid them
13    in development of their revised exemption request in terms
14    of the information we needed to draft our SER for that
15    exemption.
16              DR. SHACK:  Okay.  So, then we could sort of look
17    at this as like a first draft of a reg guide on treatment
18    requirements?
19              MR. BERGMAN:  Potentially, yes.
20              MR. REED:  Certainly a work in progress, though.
21              DR. APOSTOLAKIS:  The truth is that we still don't
22    know what the impact on CDF and LERF is from all these
23    changes.
24              MR. BERGMAN:  That's correct.
25              DR. APOSTOLAKIS:  And whether I have one SSC in a
.                                                                16
 1    particular category or 1,100, the system is insensitive to
 2    that fact.  The whole scheme is insensitive, and they will
 3    each be treated as individuals, as belonging to that group. 
 4    Is that correct?
 5              MR. BERGMAN:  I think they look at it in a group. 
 6    Maybe Mike can come up and bail us out here.
 7              DR. APOSTOLAKIS:  Do I know what you're going to
 8    say, Mike?
 9              MR. CHEOK:  I think so.
10              What we do, George, is that we do ask them to do a
11    sensitivity study where they do increase the failure
12    probabilities as a group of all the LSSCs so that, I guess,
13    we do get a group effect.
14              DR. APOSTOLAKIS:  This is a little risky, because
15    you may end up with a delta CDF that's higher than allowed. 
16    So, you have to go back and then argue that the sensitivity
17    study was unrealistic.
18              MR. CHEOK:  South Texas is using a factor of 10. 
19    We are proposing a factor of 3 to 5, but you're right, it
20    could be risky.
21              DR. APOSTOLAKIS:  Factor of 3 --
22              MR. CHEOK:  -- for each one, yeah, and do it as a
23    group.
24              DR. APOSTOLAKIS:  But you can find Fussell Veseley
25    and so on for a group, can't you?
.                                                                17
 1              MR. CHEOK:  You can for the Fussell Veseley, not
 2    for the risk achievement.
 3              DR. APOSTOLAKIS:  Right.
 4              MR. REED:  All set, George?
 5              DR. POWERS:  In light of the material that Dr.
 6    Bonaca prepared for us on the experiences and some of the
 7    Swiss work on risk-informing regulations and using risk
 8    metrics, is it clear that delta CDF is the proper metric to
 9    use for these things?
10              The Swiss, I think, found that they would get very
11    modest -- and Dr. Bonaca, please feel free to correct me
12    here -- found that they would get relatively modest changes
13    in both CDF and LERF, but when they looked at the actual
14    magnitude of the release times its frequency, they would get
15    rather substantial changes, and that raises a question in
16    your mind on whether delta CDF and delta LERF are really the
17    right metrics to use.
18              DR. APOSTOLAKIS:  Are you aware of that?
19              MR. CHEOK:  I guess I'm not aware of the study.
20              In our process, what we do is that we like for the
21    expert panel to bring in the consequences and the
22    containment issues as part of the integrated decision-making
23    panel, as opposed to as part of the PRA.
24              DR. POWERS:  That means that you're going to have
25    to have expertise on the panel dealing with radio-nuclide
.                                                                18
 1    release and transport?
 2              MR. CHEOK:  Right now there's no such specific
 3    requirement.
 4              DR. POWERS:  Then how can they answer the
 5    question?
 6              MR. CHEOK:  I guess it's something we need to
 7    think about.
 8              DR. SEALE:  I think we've, in the past, been told
 9    by people from industry, including INPO, that in the more
10    detailed assessments that they've been using, they have come
11    to rely on other measures of success or failure besides core
12    damage frequency or whatever -- that is, things which
13    anticipate more serious problems like core damage and things
14    like that -- and it strikes me that, at least at the very
15    minimum, it would be nice if the staff knew what these were,
16    and I don't think we're really comfortable in knowing
17    exactly what these other success criteria are.  I think it's
18    unfortunate.
19              DR. POWERS:  I think we keep looking for
20    surrogates --
21              DR. SEALE:  Yeah.
22              DR. POWERS:  -- for what we're really interested
23    in, because we know what we're really interested in is
24    really complicated to calculate, and I worry that we don't
25    have somebody checking to see if our surrogates are useful
.                                                                19
 1    surrogates and where the bounds of applicability are.
 2              What we're really interested in is the actual
 3    risk, and that has a product component, and we keep looking
 4    for surrogates for one element of the product.
 5              DR. SEALE:  What the utilities have done is -- I
 6    mean if we really understand -- or if I understand it -- I
 7    won't say about the rest of you, but if I understand what
 8    they've done, they've probably gone a far way toward
 9    identifying some of these surrogates, and we ought to know
10    more about it.
11              DR. POWERS:  Yeah.
12              DR. APOSTOLAKIS:  I'm not sure that the word
13    "surrogates" is the right one.
14              DR. POWERS:  To quote a sage colleague of mine, it
15    was not the product of deep thought.
16              DR. APOSTOLAKIS:  The point I wanted to make --
17    one has to be careful when one opens his mouth.
18              [Laughter.]
19              DR. APOSTOLAKIS:  I wanted to point out -- it's a
20    new thought -- that after the reactor revised oversight
21    process, we have objectives that are cornerstones that
22    really are way before the actual risk, and you know, CDF and
23    LERF are convenient numerical measures, but I'm sure in the
24    integrated decision-making process, protecting the integrity
25    of the primary system, for example, is a consideration, so
.                                                                20
 1    that we are not just talking about surrogates, but other
 2    than that, I agree.
 3              DR. SEALE:  Well, it was in the context of the
 4    evaluation process --
 5              DR. APOSTOLAKIS:  Yeah.
 6              DR. SEALE:  -- that these other measures came up,
 7    at least in one case.
 8              DR. WALLIS:  I'd like to pursue this a bit more.
 9              On this IDP, it's stated that sufficient safety
10    margin should be maintained.
11              Now, how do we know what sufficient safety margin
12    means?
13              MR. CHEOK:  I think what we said in the IDP was
14    sufficient safety margin should be maintained commensurate
15    with the uncertainty in the engineering analyses.
16              DR. WALLIS:  How do we know what that means?  We
17    know that uncertainty has some influence on margin, but the
18    whole concept of margin seems to be a very vague one.
19              DR. SEALE:  And the engineering analysis of what? 
20    CDF?
21              MR. CHEOK:  It could be the probabilistic part of
22    it, which is CDF and LERF, or the parts of the PRA which are
23    uncertain.
24              DR. WALLIS:  How does this panel decide that
25    safety margins are sufficient?
.                                                                21
 1              DR. APOSTOLAKIS:  I guess they compare with the
 2    existing ones.
 3              [Laughter.]
 4              DR. POWERS:  I think this is his point.
 5              MR. CHEOK:  Perhaps I can give an example.
 6              I mean I guess we will see this more in our pilot
 7    studies, which we should have coming up, but in previous
 8    studies, when we are doing in-service testing, again, in
 9    that case, we do one in a lambda-T by two model.
10              We were saying that, since we may not have that
11    much of certainly in this lambda-T by two model, we could
12    make sure that the lambda is -- we have margins in your
13    lambda by saying that -- let's do a better test whereby we
14    can try to trend your failure rates over time so that we
15    will know that we have a more constant lambda with the aging
16    process.
17              So, in that sense, it's saying, look, let's try to
18    be more certain with our model by trying to predict a better
19    failure rate using a better test method.
20              DR. WALLIS:  But does this mean that's sort of an
21    ad hoc process, that every time you come up to a question,
22    you use some -- what you think is a measure of safety margin
23    for that particular question, or is there some more general
24    guideline about what safety margin means?
25              MR. CHEOK:  I am not sure if it's an add-on
.                                                                22
 1    process, but it's a process that we --
 2              DR. WALLIS:  Ad hoc.
 3              MR. CHEOK:  Ad hoc.  Okay.  I'm sorry.
 4              It could be ad hoc in the fact that we will have
 5    to see how the different parameters are being affected and
 6    what we need to be more certain about and where we need to
 7    be more certain of where the margins are.
 8              DR. WALLIS:  Well, this whole topic is
 9    risk-informed, isn't it?
10              So, you've got to say something about what safety
11    margin means in the context of risk, haven't you?
12              Here's a chance to be quantitative about something
13    which has been vague for too long.
14              I seem to have the floor.  Has anyone got a reply?
15              MR. BERGMAN:  We're going to have to actually
16    consider it, obviously, going forward, but if we're going to
17    say we need to quantify these now, I think you would not
18    want to -- you would want to limit your quantification on
19    the risk end of it, rather than do something that hasn't
20    been done to date.
21              I mean there would be no point in making them
22    replicate the safety margin for the whole -- the existing
23    analysis.  I think you just want to look forward at that
24    point.
25              DR. WALLIS:  Would you agree that there is a
.                                                                23
 1    problem, though, with the vagueness about which you mean by
 2    safety margin and perhaps it should be cleared up by tying
 3    it in in some way with risk-informed, which is the umbrella
 4    that's supposed to describe the process you're going
 5    through?
 6              MR. BERGMAN:  I think we need to look at
 7    increasing the specificity there.
 8              MR. CHEOK:  In option 3, we are trying to define
 9    better what safety margins is with respect to risk and also
10    defense-in-depth, and I think we might discuss that a little
11    more later on.
12              DR. SHACK:  We'd better move on.
13              MR. REED:  Yes.  I think we're already out of our
14    time here.
15              So, let me get to the second piece of the
16    presentation, which is also the second part of the SECY, and
17    that goes to the conceptual approach for the rulemaking, as
18    we understand it today.
19              This slide just simply notes that we're still on
20    the same path we were with SECY 99-256.  It involves a --
21    relies on a robust categorization, which, of course,
22    increases the certainty.
23              If you, in fact, bin these things appropriately
24    according to their safety significance, we would expect
25    licensees to be required to maintain functional capability
.                                                                24
 1    of SSCs using either existing or new programs.
 2              For the RISC-2 piece, we would expect the
 3    licensees would be required to control the reliability,
 4    availability, and capability of these SSCs per the
 5    assumptions in the categorization process.
 6              For the RISC-3 piece, they would be required to
 7    maintain their design functions, as described in the UFSAR,
 8    and in fact, there would be an additional requirement that
 9    would describe in your updated FSAR how, in fact, you meet
10    these requirements to maintain functional capability of the
11    RISC-2 and RISC-3 SSCs.
12              I might also mention that there would also be a
13    requirement to take corrective action if, in fact, you found
14    the SSC wasn't functionally capable.
15              That's a necessary thing, since they will now be
16    removed from Appendix B.  So, we'll have a corrective action
17    statement in there, also.
18              That's the way we see it conceptually right now,
19    and that's also discussed in the SECY paper.
20              DR. APOSTOLAKIS:  Now, this whole approach seems
21    to rely heavily on importance measures, and we had a
22    presentation here from Consumer's Energy that follows a
23    different approach, the top-event prevention methodology,
24    which is a success-oriented methodology.
25              I wonder whether you're telling these people to
.                                                                25
 1    abandon that approach and switch back to Veseley and
 2    risk-achievement work or there is room here for another
 3    approach?
 4              MR. CHEOK:  There is room here for another
 5    approach.  As a matter of fact, we did talk to Consumer's
 6    Power about the top-event prevention, and I think the
 7    methodology would allow for such an approach.
 8              I think Consumer's Power also talked to NEI about
 9    adopting this thing as part of the industry approach, and I
10    think the feeling there was that there's not enough people
11    that are doing the TEP for them to formalize the procedure
12    but that Consumer's Power is more than welcome to submit a
13    application using TEP and we would be glad to review it.
14              DR. APOSTOLAKIS:  Well, the problem, though, I see
15    is that -- this is going to be in Appendix T?
16              MR. CHEOK:  Appendix T does not specifically
17    mention the top-event prevention --
18              DR. APOSTOLAKIS:  I know.
19              MR. CHEOK:  -- but I guess Fussell Veseley and
20    risk achievement were mentioned.
21              DR. APOSTOLAKIS:  So, this is part of the rule.
22              So, if those guys come up with something else,
23    then would it take a change in the rule to accommodate them?
24              MR. CHEOK:  I guess at this point we are not quite
25    sure if this will be part of the rule or part of the reg
.                                                                26
 1    guide, and I guess industry's comment is that, if it's part
 2    of the reg guide, it would make it a lot more flexible, so
 3    that more people -- and that's one of the comments that's
 4    made, that if we have less prescription, perhaps then it
 5    will allow for more flexible implementation of the rule.
 6              DR. APOSTOLAKIS:  I mean, using the TEP, I'm not
 7    even sure you can have categories like RISC-1, 2, 3.  At
 8    least in the papers I have seen from those guys, they didn't
 9    categorize.
10              MR. CHEOK:  I think in using TEP you would define
11    your horizontal line, what's safety significant and what you
12    don't take credit for, thereby it becomes less safety
13    significant.
14              So, that defines your horizontal line.  The
15    vertical line is still being defined by whether something is
16    safety-related or not safety-related.
17              DR. APOSTOLAKIS:  So, the ones that would be
18    members of the top-event prevention set -- those would have
19    the full treatment, I suppose, corresponding to RISC-1.
20              MR. CHEOK:  Right, RISC-1 or RISC-2.
21              DR. APOSTOLAKIS:  And then others will have
22    something else.
23              MR. CHEOK:  That's correct.
24              DR. APOSTOLAKIS:  The other thing is I'm not sure
25    I subscribe to the idea that not enough people are doing it,
.                                                                27
 1    therefore it's not going to be included.  The methodology
 2    should be evaluated on its merits.
 3              DR. SHACK:  No, he said the industry felt it
 4    wasn't worth their while to develop it.
 5              DR. APOSTOLAKIS:  I know, and I'm disagreeing with
 6    the industry.
 7              Just because the other measures have been around
 8    longer, that doesn't make them better.
 9              I mean why can't you include something in here to
10    allow for a TEP approach or say something that opens the
11    way?
12              In fact, I do think, myself, that this should be a
13    regulatory guide, rather than appendix to the rule, would
14    have more flexibility, but there ought to be some mention of
15    it somewhere.
16              Is that illegal do or what?
17              MR. BERGMAN:  No, and that's part of the push for
18    a -- do as much as you can through regulatory guides, but
19    the advantage to prior review and approval there is it's
20    basically you must use an approved method, and one method
21    could be underdevelopment, another one that would have to be
22    submitted is different.
23              You just can issue a series of reg guides
24    approving different methods, or individual plant submittals. 
25    I mean you can do it on a plant-by-plant basis.  You can do
.                                                                28
 1    it on a topical basis.
 2              There is flexibility there.
 3              DR. APOSTOLAKIS:  So, what you're saying is that
 4    there may be a regulatory guide with this approach, and then
 5    if you finally convince yourselves that the other approach
 6    is okay, then you will issue a new regulatory guide or
 7    revise the existing one?
 8              MR. BERGMAN:  You can do either.  If you pack too
 9    many methods in one reg guide, it just becomes an unwieldy
10    document.
11              DR. APOSTOLAKIS:  Well, the only thing I would
12    like to see here, I think it would be helpful, is some sort
13    of a statement somewhere that this is a way that right now
14    is relatively mature for doing these things, but you know,
15    we may see others like the TEP in the future.
16              MR. CHEOK:  Or we can write the reg guide to be
17    general enough so that it will accommodate the TEP and any
18    kinds of importance measures.
19              DR. APOSTOLAKIS:  Yeah, whatever, but as long as
20    it doesn't create a precedent that this is it.
21              DR. POWERS:  I have a question.
22              If you write a reg guide that is sufficiently
23    general to encompass a risk metric and a TEP event, is this
24    such a general guide that it's no guide at all?
25              MR. CHEOK:  We have that problem.  I guess we have
.                                                                29
 1    a problem with the PRA standards.  We do have the problem
 2    with a lot of things, how much prescription is enough and
 3    how much is too much.
 4              DR. APOSTOLAKIS:  You can mention some and then
 5    focus on this one.
 6              There's nothing wrong with that.
 7              DR. SHACK:  Your real conflict comes in with your
 8    no prior review.
 9              MR. BERGMAN:  If we're going to require prior
10    review and approval, we can be very flexible, because you're
11    going to review each application on its own merits.  It just
12    becomes -- it's difficult to create a lot of flexibility in
13    a rule and yet not have any sort of review mechanism over
14    what's being done, unless you have very clear performance
15    measures or something that you can tack on, but we're not
16    there yet, I don't think.
17              DR. APOSTOLAKIS:  Have you decided what to do with
18    this?
19              Is this going to be an appendix or is it going to
20    be a regulatory guide?
21              MR. BERGMAN:  We have not.  That decision isn't
22    final.  I mean that will be part of our work through the
23    proposed rule.
24              Next August, we'll have to have made a
25    recommendation, because we're going out with the proposed
.                                                                30
 1    rule.
 2              At that time, we'll know, and we should know
 3    sometime ahead of that, of course, but ultimately, we have
 4    to recommend one approach.
 5              DR. POWERS:  We'd better move on.
 6              MR. REED:  Okay.
 7              Just two more slides.
 8              I'd just point out what's going on.
 9              There's a lot of work going on right now, ongoing
10    tasks.
11              We're working with NEI, reviewing their
12    implementing guidance.
13              There's a certain amount of effort going on right
14    now reviewing the STP exemption request, and in fact, many
15    of these issues that we're discussing today will have to be
16    hammered out on South Texas.
17              There's an effort on in-house looking at
18    commercial processes that will support this entire
19    framework, and of course, we're interacting with
20    stakeholders.
21              We have a meeting with NEI coming up in the middle
22    of September right now, September 13th that's scheduled for,
23    and then the Commission briefing, as I've already mentioned,
24    on September 29th.
25              Just to summarize, then, our overview here, the
.                                                                31
 1    APR comments were, in general, supportive of our effort to
 2    risk-inform the special treatment requirements.
 3              We continue with an approach that's consistent
 4    with SECY 99-256.
 5              The STP exemption review continues, and then we're
 6    continuing to interact and hopefully resolve many of these
 7    issues we're talking about today.
 8              That's all I have.
 9              DR. APOSTOLAKIS:  So, here you're dealing with
10    actual systems, structures, and components, right, that I
11    can go and touch.
12              You're not dealing with events -- human error, for
13    example.  That can belong anywhere.
14              MR. BERGMAN:  Right.  We're really talking
15    equipment performance in option 2.
16              DR. APOSTOLAKIS:  And you are not talking about
17    frequencies of initiating events, are you?
18              MR. BERGMAN:  I think, conceptually, you could say
19    you are if you believe that the equipment performance was
20    going to affect the new equipment.
21              DR. APOSTOLAKIS:  I mean you can find the Fussell
22    Veseley for initiating event, but you cannot find the role
23    for initiating event.
24              So, initiating events are out, also.
25              MR. REED:  In general, when we talk about changes
.                                                                32
 1    in initiating event frequency, we're making an assumption
 2    that, when we change the treatment, in fact, the performance
 3    of the equipment will change, you know, lead to greater
 4    initiating event frequencies.
 5              That remains to be seen.
 6              There certainly isn't data that would indicate
 7    that today.
 8              DR. APOSTOLAKIS:  Is that true, Mike?  What's left
 9    out?
10              This is just hardware?
11              MR. CHEOK:  I guess I wasn't listening to the
12    question.  I'm sorry
13              DR. APOSTOLAKIS:  When we categorize SSCs, we mean
14    actual SSCs that one can touch.  We're not talking about
15    events like human error and we're not talking about
16    initiating events.
17              MR. CHEOK:  In a sense, when you do the
18    categorization using the PRA, you are categorizing based on
19    the basic events.
20              So, if the HEP is a basic event in the PRA or the
21    initiating event is a basic event, that gets ranked with the
22    rest of the list of components, but what you do with these
23    events would be up to the analyst.
24              You might have to break this initiating event up
25    to, if it's a support system event, what causes this
.                                                                33
 1    initiating event and how important is this support system to
 2    this initiating event?
 3              DR. APOSTOLAKIS:  So, you would take the human
 4    error and see what component it affects --
 5              MR. CHEOK:  That's correct.
 6              DR. APOSTOLAKIS:  -- and that would affect the
 7    special treatment of the component.
 8              MR. CHEOK:  That's correct.
 9              DR. APOSTOLAKIS:  Now, how about initiating
10    events?
11              MR. CHEOK:  Like I said before, if it's a support
12    system initiating event, then you might have to -- a lot of
13    -- actually, a lot of IPEs or PRAs actually have fault trees
14    to describe these initiating events if it's a support system
15    initiating event, and you can break it down and see what the
16    importances of the different components are to this
17    initiating event frequency.
18              DR. APOSTOLAKIS:  So, it comes down to hardware.
19              MR. BERGMAN:  If I could, I think we might be able
20    to provide a partial answer to Dr. Wallis' question.
21              In terms of the deterministic analyses, I don't
22    think we expect the safety margins to change under option 2,
23    because we're not changing the design of the facility.  So,
24    from that standpoint, the safety margin should remain the
25    same.
.                                                                34
 1              DR. WALLIS:  Why did you keep writing down,
 2    though, that this IDP should ensure that there is sufficient
 3    safety margin to demonstrate --
 4              MR. BERGMAN:  That's why I think we need to look
 5    at that, but it would be from a risk-informed standpoint.
 6              If we're going to say that the safety margin is
 7    going to change deterministically, there needs to have been
 8    a design change that went along with that, which would still
 9    be evaluated under the current design change processes for
10    option 2.
11              DR. WALLIS:  I guess I'm also, though, asking you
12    what the measure of safety margin is.
13              Saying it hasn't changed, you don't think it's
14    changed, is, again, a sort of vague thing unless you have a
15    measure of what it is.
16              MR. BERGMAN:  Well, it's determined by the same
17    approach as it is today, through design factors.
18              DR. WALLIS:  I know, but I mean it's always talked
19    around.
20              But no one can explain to me how I measure when
21    I've got it and what it is.
22              MR. BERGMAN:  I don't think there is a direct
23    measure of it today.
24              DR. WALLIS:  I think my theme is going to be that
25    you should not use the words "safety margin" because no one
.                                                                35
 1    knows what it is.
 2              It's a convenient thing to reassure people, but if
 3    it doesn't mean anything, don't use the term.
 4              DR. APOSTOLAKIS:  Isn't it true that the PRA --
 5    maybe the experts here can answer -- has quantified
 6    defense-in-depth expressed by redundancy and diversity but
 7    has not quantified safety margins?
 8              Is that true or not?
 9              In a PRA, we do not include the probability that a
10    failure point -- that a stress will be greater than the
11    strength.
12              I think that's a true statement, Mary?
13              MS. DROUIN:  If you say so.
14              [Laughter.]
15              DR. APOSTOLAKIS:  No, really, I mean we take all
16    the redundancies, right, one out of two, two out of three,
17    we quantify those, because that's the easy part, but when it
18    comes to the safety margins, except in rare cases -- I think
19    in the containment analysis, people do that, where you have
20    the spikes in pressure and you have the design pressure and
21    so on, but routinely we don't do it, and I think that's
22    related to Professor Wallis' question, and maybe that will
23    be the next generation of PRA.
24              But we don't do it, and when you say, you know,
25    preserve the safety margins, I agree, it's just, you know,
.                                                                36
 1    look at what you have now and make sure you don't deviate
 2    too much, but you have not quantified it.
 3              I mean if your failure point -- or if you take now
 4    this design point 10, then maybe the change will take you to
 5    9 but not to 6, because that's a big change.
 6              Now, how big is it?  We don't know.  I think
 7    that's the logic, right?
 8              MR. BERGMAN:  Yeah.
 9              DR. APOSTOLAKIS:  Stay close to where you already
10    are.
11              MR. BERGMAN:  You can't show that there's a
12    change.
13              DR. POWERS:  Okay.
14              We're going to have to move on.
15              DR. SHACK:  Which piece are we going to do next? 
16    Option 3 or 50.54 or 50.44?
17              MS. DROUIN:  It's one and the same.
18              DR. SHACK:  Okay, one and the same.
19              MR. KING:  For the record, I'm Tom King from the
20    Office of Research.
21              With me is Mary Drouin, also from the Office of
22    Research.
23              What we're going to talk about today is focus on
24    the changes to 50.44, the combustible gas regulation, which
25    is really the first recommended risk-informed alternative
.                                                                37
 1    coming out of option 3, and as we go through it we can talk
 2    about how we got to these recommendations, which really
 3    applies what we had called the framework document, which
 4    sort of lays out how the staff is approaching looking at the
 5    reactor regulations and making decisions on should there be
 6    a risk-informed alternative and, if so, what should that be,
 7    but we're not going to walk through the whole framework. 
 8    We're just going to use 50.44 as sort of a way to illustrate
 9    how we've approached this.
10              I think you have a package -- we had sent you a
11    copy of the draft SECY paper framework and 50.44 package --
12    I'm not sure -- sometime in the past couple of weeks.  We do
13    owe this package to the Commission.  It's due to the EDO
14    this week, the Commission next week.
15              It would be nice to have a letter from the
16    committee on the package, if the committee is so inclined to
17    write such a letter.
18              So, we can come back and talk about that at the
19    end, but with that, I'm going to let Mary walk through this.
20              DR. SHACK:  Since you're not going to talk about
21    the framework directly, I'm interested in one of the --
22    essentially the issues in the Commission paper, which was
23    the use of the safety goals, and there seemed to me a
24    dichotomy in the way it was treated in the Commission paper
25    and in the framework document.
.                                                                38
 1              In the framework document, I thought you were
 2    arguing that you were using the safety goals because those
 3    are the safety goals and those seemed the logical thing to
 4    design the regulatory system to.
 5              In the Commission paper, there's more a -- you
 6    know, in theory, one could develop and apply a more generous
 7    regulatory framework, one that eliminates the elimination of
 8    all measures not needed for adequate protection, and then
 9    you argue that you don't do that because of PRA limitations
10    and uncertainties, and that's an argument that doesn't
11    appear anywhere in the framework document.
12              MR. KING:  Yeah.  It was put in the SECY paper
13    more to explain to the Commission why we chose the safety
14    goal level of safety to risk-inform to.
15              The framework document is more here's guidance to
16    the staff without some of the rationale.
17              DR. SHACK:  Okay.  So, that really is your
18    argument, then, for going to the safety goal.
19              MR. KING:  Well, it's part of the explanation. 
20    Those words came from Reg. Guide 1.174, which we use the
21    safety goal to develop the metrics and the CDFs and LERFs
22    and so forth in there.
23              We thought the philosophy that was used there
24    really applies here, as well.
25              Maybe I ought to mention there's two changes that
.                                                                39
 1    were made to the SECY paper.
 2              I think the version you have has four policy
 3    issues in it.
 4              The version that's on its way to the EDO's office,
 5    in concurrence -- that's been reduced to two policy issues. 
 6    The two policy issues that are in there are selective
 7    implementation and back-fit.
 8              The one that we called safety goals, we've sort of
 9    reached the conclusion that that really isn't a policy issue
10    anymore, because the Commission decided that back when we
11    were doing 1.174.
12              We used the safety goal to define the level of
13    safety we're trying to achieve, and we build our metrics
14    based upon the QHOs and the subsidiary objectives from the
15    safety goal.
16              So, we don't call that a policy issue anymore in
17    the SECY paper.
18              The other one that we are not calling a policy
19    issue is the definition of defense-in-depth.
20              I think what we want to do is point out to the
21    Commission what we're using, but we're not really calling it
22    a policy issue at this point.
23              DR. APOSTOLAKIS:  I think one of the main reasons
24    that you are not using figures that represent adequate
25    protection is that you don't have them, and I don't know why
.                                                                40
 1    we don't say that.
 2              DR. KRESS:  I don't think that's true, George.  I
 3    think if they had them, they would not use them.  They would
 4    use the safety goals.
 5              MR. KING:  I think that's true, too.
 6              DR. APOSTOLAKIS:  Then why don't we say these
 7    things?
 8              What I'm saying is that we can really say, given a
 9    certain situation, that there is inadequate protection if
10    something is exceeded.
11              In fact, you can have a core damage frequency that
12    is within the goal, and I can see a situation where you guys
13    will say no, you also have to do this, because we don't like
14    the margin you have here or we don't like the redundancy you
15    have there.
16              So, as you've said, you and your colleagues have
17    told us many, many times, adequate protection is something
18    that you decide after you go through a process that looks at
19    many, many things.
20              Now, I think that's a reasonable argument, and I
21    would rather see that here and then go naturally to the use
22    of the safety goals rather than say that we would -- one
23    would apply a more generous framework that permits the
24    elimination and so on.
25              DR. SHACK:  It's apparently gone.  That's one way
.                                                                41
 1    to solve the problem.
 2              DR. APOSTOLAKIS:  I think that's a good
 3    opportunity, since, you know, the agency has been criticized
 4    from outside bodies that it doesn't have a definition of
 5    adequate protection and so on.
 6              This would be an excellent opportunity to say a
 7    few things about it, don't you think, and put it on solid
 8    ground, because when I read this, it left me a little cold. 
 9    I mean it didn't really say anything.
10              It just said that we could be more generous, but
11    we decided not to be, and I think there are more fundamental
12    reasons for doing it this way.  It's not just a matter of
13    being generous.
14              MR. KING:  You could say more, I agree.  We could
15    say more, but we don't have to in this paper, because we
16    don't have to define adequate protection to proceed with
17    option 3.
18              DR. APOSTOLAKIS:  No.  And that's what you should
19    say, that -- again, coming back to what you have told us
20    many times, that adequate protection is just -- it's not
21    just a number.
22              MR. KING:  Exactly.
23              DR. APOSTOLAKIS:  Okay?
24              So, you're working with the goals.  After all, you
25    know, if the agency has goals, we should try to meet them,
.                                                                42
 1    right?
 2              And I think that would be a good place to -- all
 3    I'm saying is revise it.
 4              Now, the other place where I think you should
 5    spend some time revising is the section on the definition of
 6    defense-in-depth.
 7              MR. KING:  Are you in the paper or the framework
 8    now?
 9              DR. APOSTOLAKIS:  In the Commission paper.
10              MR. KING:  The paper.
11              DR. APOSTOLAKIS:  Defense-in-depth -- I mean I'm
12    not sure I see a definition here.  It's a description, but
13    it's not a definition, and I think that -- I mean the
14    Commission itself, in its white paper, has a discussion of
15    defense-in-depth, right?
16              MR. KING:  Yeah.  They have a high-level, sort of
17    like a philosophy-type discussion.
18              DR. APOSTOLAKIS:  What is really relevant to your
19    work here is that defense-in-depth really handles
20    un-quantified uncertainty.
21              We can talk about it forever, but what it comes
22    down to is that if you are uncomfortable with what you have
23    done, which means you have uncertainties, you put an extra
24    barrier.  You have larger margins.
25              That's really what it comes down to.  That's what
.                                                                43
 1    defense-in-depth is.
 2              That's a structuralist interpretation.
 3              DR. KRESS:  George, I have a little problem with
 4    that, because I can conceive of defense-in-depth being
 5    incorporated to compensate for quantified uncertainty just
 6    as well.
 7              DR. APOSTOLAKIS:  Then it's not defense-in-depth.
 8              DR. KRESS:  Well, it depends on your definition of
 9    defense-in-depth.
10              DR. APOSTOLAKIS:  Then you are using standard
11    engineering tools like redundancy and so on to achieve a low
12    frequency and a low uncertainty, but I think
13    defense-in-depth, in the nuclear industry, really means a
14    structuralist approach, where you're using multiple barriers
15    without really quantifying their impact.
16              DR. KRESS:  Of course, if you define it that way,
17    yeah.
18              DR. APOSTOLAKIS:  But don't you think that most
19    people think of it that way?
20              DR. KRESS:  Yeah, I agree most people think of it
21    that way.
22              DR. APOSTOLAKIS:  And in fact, you can say that,
23    most people think of it that way.
24              MR. KING:  Well, the approach we're taking applies
25    both.
.                                                                44
 1              There's some structuralist elements to it that
 2    you're going to have regardless of what your PRA numbers
 3    say, and then there's the quantified uncertainty which will
 4    also help you make decisions on redundancy and diversity and
 5    those kinds of things.
 6              DR. APOSTOLAKIS:  Right.  But I think when say
 7    defense-in-depth, we really mean the structuralist.  In
 8    other words, we mean as a principle rather than as a tool to
 9    work with, but I mean if you feel that's important, you can
10    put that there, as well.  But there is controversy -- not
11    controversy but some question as to what exactly it means,
12    but most people would interpret it this way, and then the
13    strategies are to do what you have here, okay, because the
14    heading is definition of defense-in-depth, and if you say
15    definition, you might as well define it or say that there
16    are many definitions.
17              But other than that, I think the description that
18    you have is fine.  It's just that the conceptual part, I
19    think, should be beefed up a little bit.
20              MR. KING:  Okay.
21              Anything else before Mary talks about 50.44?
22              DR. SHACK:  Yeah.  I have one more question I was
23    interested in in the framework document itself, and that is
24    this notion that you were seeking explicit addressing of
25    safety-significant issues in the regulations.
.                                                                45
 1              When you've done that, what is the point of it?
 2              You know, normally I think of the regulations as
 3    setting up a design envelope that doesn't address everything
 4    explicitly, but it's a performance measure.  When you're all
 5    said and done, you know, does your PRA say that you're okay,
 6    and it's -- there's not a problem if it's not explicitly
 7    addressed.
 8              Is the goal here to recast the regulations so that
 9    they explicitly address the safety concerns?
10              MR. KING:  I think the short answer is yes, and I
11    think you'll see an illustration of that when you look at
12    50.44, because the PRA is saying there's some accident
13    sequence that today's regulations don't deal with.  I think
14    what we want to recommend as part of a risk-informed
15    alternative is a revision to that regulation that does deal
16    with that, you know, significant sequence.
17              DR. SHACK:  Even though the results from the other
18    design processes give you low probabilities, low
19    contributions to CDF, just because it's not explicitly
20    addressed, you're saying it's significant in the sense that
21    it's a large contributor, it's a high value?
22              MR. KING:  Yes.  And we're not talking about
23    putting CDF values in the regulation.  We're talking about
24    revising the deterministic regulation to fill a gap.  As I
25    said, you're going to see that when we get to igniters and
.                                                                46
 1    should they have back-up power to be able to be operable
 2    during a station blackout sequence.
 3              For Mark III's and ice condensers, when we got
 4    into 50.44, we saw that as -- for those containment types --
 5    is a significant safety concern, and our risk-informed
 6    alternative attempts to deal with that.
 7              DR. KRESS:  I was trying to thumb through your
 8    slides.
 9              Are you going to discuss at all your Figure 3.1 of
10    the framework document, which has the quantitative values in
11    it for prevention and mitigation and for the various
12    initiating frequency events?
13              MR. KING:  No, we weren't planning to put that up
14    and talk about it.  If you want to talk about it, we can
15    talk about it.
16              DR. APOSTOLAKIS:  You want us to write a letter on
17    the whole document, not just the 50.44.
18              MR. KING:  Well, the paper to the Commission is
19    providing the framework document.  It's the next -- it's an
20    updated version.  We're not asking for the Commission to
21    approve that at this point.  So, we're not asking the
22    committee to write a letter on it.
23              But we are asking the Commission to approve
24    proceeding with a risk-informed alternative to 50.44, and we
25    would like the committee to write a letter on that piece of
.                                                                47
 1    it.
 2              DR. APOSTOLAKIS:  Okay.  So, we will have another
 3    opportunity to look at the attachment?
 4              MR. KING:  The framework?
 5              DR. APOSTOLAKIS:  Yeah.
 6              MR. KING:  Yeah.
 7              DR. APOSTOLAKIS:  This is a big document.
 8              MR. KING:  The framework's a living document.  I
 9    mean as we apply it --
10              DR. APOSTOLAKIS:  So, we'll have an opportunity to
11    kill it.
12              MR. KING:  You've had that opportunity.
13              DR. APOSTOLAKIS:  Yeah, because I think there are
14    so many ideas here that we really need -- in fact, we may
15    even need a subcommittee meeting.
16              MR. KING:  Yeah, we had talked about, before,
17    having a subcommittee just on the framework document.
18              DR. APOSTOLAKIS:  Yeah, I think we should do that.
19              MR. KING:  Okay.
20              DR. APOSTOLAKIS:  But coming back to the --
21              MS. DROUIN:  And there have been some changes
22    already on the framework document --
23              DR. APOSTOLAKIS:  I noticed that, Mary.
24              MS. DROUIN:  -- than the one you have.
25              DR. APOSTOLAKIS:  I noticed that.
.                                                                48
 1              Just so that you don't think I'm a negative guy,
 2    on the paper to the Commission, I really like the paragraph
 3    on page 5, accordingly the staff recommends that the safety
 4    goals be used, and I really like your section on selective
 5    implementation, okay?  I thought it was great.
 6              MS. DROUIN:  Thank you.
 7              MR. KING:  Thank you.
 8              DR. APOSTOLAKIS:  Just to be fair.
 9              Okay.
10              So, maybe we can discuss with Mr. Markley later
11    about setting up a subcommittee meeting to discuss the
12    framework itself.
13              MR. KING:  Yeah.  And that would be where we could
14    get into the Figure 3.1.
15              DR. APOSTOLAKIS:  Okay.
16              DR. KRESS:  I'll reserve my questions, then, for
17    that.
18              MR. KING:  All right.
19              Why don't we go through 50.44?
20              DR. APOSTOLAKIS:  Good.
21              MS. DROUIN:  Before we start, how much time do we
22    have left?
23              DR. SHACK:  Fifteen minutes.
24              MS. DROUIN:  Okay.  Then why don't we go to page
25    4?
.                                                                49
 1              DR. WALLIS:  Well, on page 2, you have objectives,
 2    and I have to look at what you do in the light of your
 3    objectives, and the first one says enhanced safety and the
 4    last one says without compromising safety.  So, when I look
 5    at what you're proposing, should I apply the criterion of
 6    enhancing or not compromising?
 7              DR. APOSTOLAKIS:  Where is this now, Graham?
 8              DR. WALLIS:  I'm trying to evaluate what they are
 9    proposing, and they're saying I have to do it in the light
10    of some objective.
11              So, should I look at what you're doing in saying
12    these guys are relaxing a bit but it hasn't compromised
13    safety, or shall I look and see if you've enhanced safety? 
14    That's all.  It's a simple question.
15              MS. DROUIN:  If you look at the first bullet, it's
16    enhance it commensurate with their importance to health and
17    safety.
18              I don't think that these are contradictory.  I
19    mean you want to try and enhance safety.
20              DR. WALLIS:  Is this a criterion for what you're
21    doing, though?
22              MR. KING:  These are general words.
23              DR. WALLIS:  Well, I think you ought to be very
24    careful with these general words, because I want to take
25    them seriously, and I want to say is what you're proposing
.                                                                50
 1    here going to enhance safety or not?
 2              MR. KING:  I think there's both components in
 3    50.44.  The enhanced safety part comes where we've talked
 4    about potential gap on back-up power to the igniters that we
 5    saw.  That's an enhanced safety.  But also, as we go through
 6    and risk-inform other pieces and remove unnecessary burden,
 7    we don't want to do that by compromising safety.
 8              So, I don't think they're contradictory.  I think
 9    they're talking about two different aspects of what we're
10    doing.
11              DR. APOSTOLAKIS:  Wouldn't it be better to have
12    the first bullet start as focus NRC and licensee resources
13    in areas, drop "enhance safety by"?
14              MS. DROUIN:  Well, these words are words that
15    appeared -- I mean these are words that --
16              DR. APOSTOLAKIS:  -- the Commission used.
17              MS. DROUIN:  -- I think are directly out of the
18    reg guide.
19              MR. KING:  I think these came directly out of
20    98-300, as I remember, and if we had to write them today,
21    maybe we'd write them --
22              DR. WALLIS:  I'm just trying to keep you in the
23    discipline of checking that what you actually propose does
24    -- is commensurate with your objectives, as stated.
25              MS. DROUIN:  Well, I think that you do enhance
.                                                                51
 1    safety when you re-focus your resources on those areas that
 2    are commensurate with their importance.
 3              When you focus something in areas that are not
 4    important, I think you're taking away from safety.  I think
 5    when you focus on --
 6              DR. WALLIS:  This is a vague idea, though.  Okay. 
 7    Again, I think, if you're going to enhance safety --
 8              MS. DROUIN:  I do think you do enhance safety by
 9    that.
10              DR. WALLIS:  -- you ought to have a measure of
11    safety and not use it as a vague, hopeful term.
12              I'd like to move on now.
13              Just be careful about the use of these words.
14              MS. DROUIN:  When you look at 50.44, it is a
15    regulation that, on the surface, appears rather simple, but
16    it's not as simple as people like to think.
17              It is a fairly prescriptive regulation.  It gets
18    into quite a bit of detail in specifying very particular
19    requirements.
20              It has two sets of requirements.
21              The first one -- I like to refer to them as the
22    analytical requirements.
23              It gets in and specifies the type of accidents
24    that need to be considered when you're looking at
25    combustible gases, what type of combustible gas, it looks at
.                                                                52
 1    where -- the source from that combustible gas and, you know,
 2    the amount.  It's very specific in those areas.
 3              DR. POWERS:  Let me ask about the -- a couple of
 4    things about the type of accident to be considered.
 5              When we think in terms of a risk-informed
 6    approach, we tend to think of those models that are used in
 7    association with risk models for accidents.
 8              They typically have a cut-off time of about 24
 9    hours in their modeling of accidents.  Are you looking at 24
10    hours as a cut-off time?
11              MS. DROUIN:  I'm going to put that off, because we
12    are going to get into the timeframe.
13              DR. POWERS:  Okay.
14              MS. DROUIN:  We look at before and after the 24
15    hours.
16              DR. POWERS:  When we think about those accidents,
17    we tend to think about some fairly classic accident analyses
18    which are limiting cases, maybe a large-break LOCA, but
19    those accidents are stylized in the sense that operator
20    actions that are not proceduralized are not credited in
21    those accident analyses, and so, they stand in some contrast
22    to the accidents that actually occur.
23              I'm think of TMI, where operator actions did
24    occur, even though they were not proceduralized, and those
25    operator actions tend to put water on the core, and water
.                                                                53
 1    tends to turn into hydrogen under these circumstances.
 2              So, when you think about types of accidents, are
 3    you only looking at these fairly stylized accidents, or are
 4    you considering the range of possible operator actions that
 5    are not proceduralized that might change either the timing
 6    or the magnitude of hydrogen generation?
 7              MS. DROUIN:  I would say that we're looking at all
 8    ranges.  We aren't just considering the stylized one.  And
 9    that leads us to some of the recommendations.
10              DR. WALLIS:  If you look at the last part here,
11    there's 75 percent and 5 percent.  These are very arbitrary,
12    prescriptive requirements.  It would seem to be that
13    risk-informing ought first to look at those numbers and say
14    where did they come from, what's the probability of them,
15    what's a more likely, realistic reaction?  Then we know what
16    we're dealing with.
17              MS. DROUIN:  I agree.
18              DR. WALLIS:  But you're going to take them as
19    gospel?
20              MS. DROUIN:  No.
21              DR. WALLIS:  You're going to question them and
22    you're going to look at them.
23              MS. DROUIN:  Yes.
24              DR. WALLIS:  Okay.
25              MR. KING:  This is what's in there today.
.                                                                54
 1              DR. WALLIS:  All right.  That's good.
 2              MS. DROUIN:  When you look at the analytical
 3    requirements that are in the regulation, there's actually
 4    what I call physical requirements that are in there to
 5    prescribe how you should address the analytical ones, and
 6    there's six high-level ones, and there's a lot more to these
 7    requirements, but this is what's actually in the regulation.
 8              If you start looking at the implementing documents
 9    and associated regulations, you get into more detail, but
10    this is all the regulation requires, to measure the hydrogen
11    concentration in the containment, ensure a mixed containment
12    atmosphere, control your combustible gas concentration --
13    that's where you see the recombiners -- install your
14    high-point vents, and those, so far, apply to all your
15    reactors, all your containment types.
16              The last two are specific to particular
17    containments, inerting your atmosphere, of course, for your
18    Mark I's and Mark II's, and having your igniters actually
19    providing the hydrogen control system for your Mark III's
20    and your ice condenser containments.
21              So, in the current 50.44, on the previous slide
22    and this slide, that's what the current 50.44 requires
23    licensees to do.
24              Before determining what our recommendation would
25    be, we tried to go back, starting with why the regulations
.                                                                55
 1    came about the way they did and looking at all the risk
 2    studies that are out there, what would be our current
 3    understanding of the risk significance of combustible gases,
 4    and I just tried to put some highlights here.
 5              The biggest one, of course, is that, you know, you
 6    can get from -- you can get your combustible gases from your
 7    core damage and your core melt accidents, from all accident
 8    types.
 9              It's not just restricted to your LOCAs, which you
10    saw as one of your analytical requirements, and it's not
11    just to core damage to a degraded core.
12              You can get your combustible gases from your
13    core-concrete interaction.
14              That gets to some of the points that you were
15    bringing up, Dana.
16              DR. WALLIS:  All your slides have words.  Do any
17    of them have any numbers on them?
18              MS. DROUIN:  What do you mean numbers?
19              DR. WALLIS:  Well, you give us all these
20    reassuring statements.
21              I presume they're based on analysis and someone's
22    numbers?
23              MR. KING:  Yeah, they're based upon looking at
24    IPE's, looking at NUREG-1150, available PRA results.
25              DR. WALLIS:  So, behind them all, if someone asked
.                                                                56
 1    how do you know something, you could say -- you could pull
 2    out some numbers and just show us that it's not just a dream
 3    but a reality.
 4              MS. DROUIN:  Absolutely.  When you go through the
 5    50.44 report, we do have a little table in there under each
 6    of the containment types that gets into the accidents and
 7    show what the numbers are that we pulled from the different
 8    risk studies.
 9              DR. POWERS:  50.44 is my favorite report on the
10    IPE insights document?
11              MS. DROUIN:  I'm sorry?
12              DR. POWERS:  50.44 is the IPE report on -- IPE
13    insights document?
14              MS. DROUIN:  50.44 is the number for the
15    regulation.
16              DR. POWERS:  I don't remember reports by numbers.
17              MS. DROUIN:  Oh, I'm sorry.
18              MR. KING:  1560 is the IPE insights.
19              DR. POWERS:  Still one of my favorite reports.
20              MS. DROUIN:  Thank you.
21              The biggest thing you do see from the numbers is
22    that third bullet, is that for not all containments, not all
23    accident sequences, but there are certain accident sequences
24    and for certain containment types, you do see conditional
25    containment failure -- sorry -- a conditional large early
.                                                                57
 1    release probability ranging from .1 to 1.
 2              DR. KRESS:  That's sequence by sequence.  That's
 3    not the aggregate.
 4              MS. DROUIN:  No, not the aggregate.
 5              DR. KRESS:  So, in essence, you would look at that
 6    in the light of the actual frequency of that particular
 7    sequence.
 8              MS. DROUIN:  Yes.
 9              DR. KRESS:  Okay.
10              MS. DROUIN:  Yes.  But this was just to point out
11    that there is a concern there.  You are seeing relatively
12    high contributions.
13              DR. WALLIS:  There's nothing less than .1?
14              MS. DROUIN:  Yes.
15              DR. WALLIS:  Never less than .1?
16              MS. DROUIN:  No, you do see some less than .1.
17              DR. WALLIS:  Well, you say ranges from .1 to 1.
18              MS. DROUIN:  Depending on the containment types.
19              DR. WALLIS:  But it's not less than .1, then.
20              MS. DROUIN:  You do see some less than .1.
21              DR. KRESS:  I'm sure there are initiating events
22    that are --
23              DR. SHACK:  They're only worried about the ones
24    that are larger than .1.
25              MS. DROUIN:  I'm saying the fact that you do see
.                                                                58
 1    some stuff from .1 to 1, you have a concern.
 2              If everything was less than .1, we would not have
 3    a concern here.
 4              DR. WALLIS:  But the impression I get is that
 5    everything is in that range.
 6              MS. DROUIN:  No.
 7              DR. KRESS:  It doesn't say that.
 8              DR. WALLIS:  So, you're telling me the range is
 9    from zero to 1.  That's pretty good.
10              MS. DROUIN:  Yes.
11              DR. WALLIS:  That's an informing statement.
12              DR. SHACK:  No, what she's trying to emphasize is
13    that there are a significant group where they're fairly
14    large, which is greater than .1.
15              MS. DROUIN:  Yes.
16              Now, when you start looking at the generation of
17    your combustible gases and you start looking at it in your
18    time periods, the biggest thing is, when you look at it for
19    less than 24 hours, in many cases, it's not so much of a
20    significant challenge to containment integrity, but when you
21    do start considering past the 24 hours, after the onset of
22    core damage, where people did not think there was a concern,
23    we still think there is a concern.
24              DR. KRESS:  But that bullet needs to be said that
25    it's not a significant challenge because we have
.                                                                59
 1    regulations.
 2              MS. DROUIN:  Yes, I didn't go into the bullets
 3    there.  I apologize.
 4              DR. KRESS:  I mean it would be a significant
 5    challenge if you didn't have these regulations.
 6              MS. DROUIN:  If you did not inert it or you did
 7    not have the igniters, absolutely, absolutely.
 8              DR. SEALE:  Yeah, but if the igniters work, it's
 9    hard to build up an awful lot of pressure from water vapor
10    as long as the temperature is below saturation.
11              MR. KING:  If the igniters work, we're in pretty
12    good shape.
13              DR. SEALE:  Even after 24 hours.
14              MR. KING:  Even after 24 hours.  The concern we
15    had is station blackout where the igniters don't work.
16              DR. SEALE:  That's a separate case.
17              MS. DROUIN:  I'm going to skip over to 8 and just
18    try and go through each of the requirements.
19              If we start with the analytical requirement, the
20    bottom line is here -- I mean I use the word "enhance," but
21    what we're talking about is that, as far as the analytical
22    requirements, we think that they ought to be -- and this
23    goes back to our -- one of our principles or ground rules in
24    our framework for risk-informing, is that the analyses
25    behind the technical requirements should be realistic, so
.                                                                60
 1    that we are going to revisit that.
 2              The requirements should not be conservative,
 3    shouldn't be bounding.  That should go more into the
 4    acceptance criteria.
 5              So, since this is one of our fundamental things
 6    and there has been a lot of work done in this area, so we
 7    are not talking about going off and doing years of research. 
 8    We're talking about, over the next couple of months, doing
 9    some calculations.
10              So, the biggest thing there is to try and base the
11    analytical stuff on realistic analysis.
12              If I go into --
13              DR. POWERS:  When you say you're going to do some
14    calculations, you're talking about this within-24-hour
15    period of time.
16              MS. DROUIN:  Yes.
17              DR. KRESS:  When you talk about a hydrogen source
18    term, you're including the quantity versus time or
19    concentration versus time?
20              MS. DROUIN:  Right.  You're looking at the amount
21    and the rate.
22              DR. KRESS:  And that would be -- that seems to me
23    like that would be accident- and plant-specific.  You're
24    going to try to bound it in a risk-informed manner?
25              MS. DROUIN:  Well, you would do it for certain
.                                                                61
 1    particular accident sequences under certain different
 2    conditions.
 3              MR. KING:  But you're right.  I mean, BWR versus
 4    PWR, that kind of thing --
 5              DR. POWERS:  I think that you could probably do it
 6    for a set of representative plants.
 7              DR. KRESS:  So, they're going to have more than
 8    one hydrogen source term.
 9              MR. KING:  We might have a B and a P.  The idea
10    was to go back and take a look, instead of just having one
11    number now, without a rate, to go take a look and see, you
12    know, should we have one, should we have two, three, but
13    whatever it is, based upon some realistic calculations.
14              I mean sort of our gut feeling is, when we're all
15    done, it isn't going to change, you know, the need to inert
16    Mark I's and II's and the need to have igniters on III's and
17    so forth, but it's sort of like a confirmatory-type step
18    that we want to go through.
19              MS. DROUIN:  Yes.
20              On the measuring of the hydrogen concentration, in
21    our risk-informed alternative, we're recommending that this
22    particular requirement be eliminated, so it would not show
23    up in the risk-informed alternative.
24              One of the things that you will see on each of the
25    slides is a last bullet that addresses Mr. Christie's
.                                                                62
 1    petition, because in our SECY, in our report, we're
 2    providing some of the technical basis to his petition.
 3              So, we're trying to show you also a comparison of
 4    where our recommendation -- where it does or does not match
 5    up with his particular petition.
 6              On this particular one, he is also requesting the
 7    elimination of this particular requirement.
 8              DR. KRESS:  I see to remember that they used that
 9    as part of their guidance on emergency response measures?
10              MR. KING:  Yeah.  Emergency response measures
11    require looking at hydrogen, and I think the thing that
12    we're talking about here is we're not changing what needs to
13    be done under the emergency response measures --
14              DR. KRESS:  I see.
15              MR. KING:  -- and whatever -- in terms of the
16    safety grade, nature of whatever instruments they're using,
17    that would stay the same, but what we're doing under 50.44,
18    since it doesn't -- monitoring hydrogen doesn't really
19    impact when you turn the igniters on and that kind of stuff,
20    we're eliminating it from this regulation.
21              DR. KRESS:  So, there may still be hydrogen
22    monitors as a result of some other regulation.
23              MS. DROUIN:  Absolutely.
24              DR. KRESS:  You're looking at 50.44, in this case,
25    in isolation.
.                                                                63
 1              MS. DROUIN:  Right, 50.44.
 2              I'm trying to go through this pretty quick, for
 3    time's sake.
 4              DR. WALLIS:  Are you going to get to a bottom line
 5    at the end?
 6              MS. DROUIN:  The bottom line?
 7              DR. WALLIS:  Yeah.
 8              MS. DROUIN:  Well, they're on each of the slides.
 9              I wasn't going to go through all the bullets, just
10    kind of give you the bottom line on each one of the
11    requirements.
12              DR. WALLIS:  Yeah, but you're going to say all the
13    things you're going to do.
14              What's the consequence of all the things you're
15    going to do?
16              MR. KING:  The bottom line is some burden
17    reduction and some safety enhancement.
18              MS. DROUIN:  Some safety enhancements.
19              DR. WALLIS:  Do you have a measure of that safety
20    enhancement?
21              MR. KING:  We have a measure in terms of
22    eliminating the sequences that have a high conditional core
23    damage probability.
24              DR. WALLIS:  So, you could measure -- give us a
25    measure in terms of CDF or LERF or something?
.                                                                64
 1              MR. KING:  Not CDF.
 2              DR. WALLIS:  LERF?
 3              MR. KING:  When you get hydrogen, the core has
 4    already been damaged, but it's the LERF, yeah, the LERF
 5    aspect of it.
 6              MS. DROUIN:  The next set of requirements, when
 7    you looked at them, it's atmosphere, controlling hydrogen
 8    for your postulated LOCA, which gets into your recombiners,
 9    inerting your Mark I and II's.
10              Well, the first one, the first two -- sorry.  I
11    was going to say something totally incorrect.
12              Ensuring the mixed atmosphere -- we aren't
13    proposing any changes to this one, keep it as is.  We aren't
14    going to enhance.  We aren't going to delete.  It would
15    remain the same, in the alternative.
16              DR. POWERS:  In your sub-bullets on this, you
17    bring up GDC-50.  My recollection of GDC-50 may be
18    incorrect, but it is my impression that it does not speak to
19    a 24-hour requirement --
20              MS. DROUIN:  I'm sorry?
21              DR. POWERS:  -- that GDC-50 speaks to -- seems to
22    speak to all time.
23              MR. KING:  Right.
24              DR. POWERS:  So, that aspect of GDC is going to be
25    sacrificed?
.                                                                65
 1              MS. DROUIN:  No, no.
 2              In going through and looking at the purpose for
 3    retaining the requirement, and if you go back earlier, we
 4    were saying what the risk significance is, and if you go
 5    back to our definition of defense-in-depth, we're modifying
 6    either because the risk is showing us, but there are also
 7    elements of it that, regardless of the risk, we will retain
 8    because of the defense-in-depth elements.
 9              If we were to look at this strictly from the risk
10    perspective, that would lead us to eliminate this
11    requirement, but when we're looking at the defense-in-depth
12    elements and we look -- which part of it was to meet the
13    intent of the GDCs and you look at GDC-50, then that leads
14    us to you really shouldn't touch this requirement, to leave
15    it alone.  So, it's not going to change the GDC.
16              DR. POWERS:  I think what motivates "ensure a
17    mixed atmosphere" is the models that you have for
18    calculating what the combustion -- combustibility and the
19    consequences of combustion really are fairly poor at
20    handling stratified environments.
21              I mean you have a major uncertainty there in your
22    phenomenological analysis that you really can't tolerate.
23              MS. DROUIN:  Uh-huh.
24              DR. POWERS:  The models are just poorly suited for
25    that sort of thing, and so, you retain the mixed atmosphere
.                                                                66
 1    so that all of the phenomenological base and the numbers
 2    that you're going to give Mr. Wallis are still valid.
 3              MS. DROUIN:  Okay.
 4              DR. APOSTOLAKIS:  So, from the risk perspective,
 5    you would not eliminate it, then, based on what Dr. Powers
 6    just said.
 7              You just can't quantify it, but you know it's a
 8    bad thing.
 9              MR. KING:  What Mary's saying is we're not
10    proposing any changes.
11              DR. APOSTOLAKIS:  But the argument that, from the
12    risk perspective, you would probably eliminate this
13    requirement probably is not true, based on what I just
14    heard.
15              MR. KING:  We did not, I think, take a serious
16    look at eliminating it, given your argument, given the fact
17    that you had GDC-50, we didn't spend a lot of time looking
18    at trying to eliminate it.
19              DR. SIEBER:  I guess one of the problems, though,
20    is that GDC-50 becomes an assumption that says, yeah, there
21    is mixing, and so we know something about the force of
22    combustion.
23              On the other hand, if you have a LOCA and you're
24    relying to any extent on fan coolers, the fan coolers will
25    either fail or trip during the process of the LOCA, so you
.                                                                67
 1    have to rely on natural phenomena in order to assure that
 2    mixing, and it's not all that clear to me that adequate
 3    mixing occurs under those circumstances.
 4              DR. POWERS:  Well, it's not unclear to you.  It's
 5    not clear to the codes either, because they lack the ability
 6    to do natural circulation very effectively.  I mean they can
 7    hook it up, and one of Graham's favorite equations, the
 8    momentum equation, causes some headache in lump node codes.
 9              MR. KING:  There has been some experimental work
10    that's been done since the hydrogen rule was written that
11    does help us believe that, particularly for the plants that
12    have igniters, that pockets that don't collect to detonable
13    mixtures before it migrates to igniters and you get some
14    burning to take place.  We've done some full-scale testing.
15              DR. POWERS:  Except where you have dead-end
16    condensation sources, sites.
17              MR. KING:  And Generic Issue 121 looked at
18    hydrogen needs for large drives and looked at pocketing that
19    could occur, particularly in closed compartments, and
20    concluded that the amount that's going to occur and the
21    detonations that may occur there are not
22    containment-threatening type of things.  So, there's been a
23    lot of work that's been done over the past 10 or 15 years.
24              DR. KRESS:  Let me ask a strange question.  I
25    think it's strange.
.                                                                68
 1              You're focusing on -- to a large extent -- on
 2    conditional probability of containment failure.  Suppose you
 3    had a sequence of events where you didn't fail containment
 4    but you had a significant amount of hydrogen produced and
 5    fission products produced and went into containment, and
 6    then you had a hydrogen combustion event.
 7              Because of the increased pressure, you're going to
 8    enhance the fission product leakage out of the leak paths in
 9    the containment, not a failed containment, the leak paths,
10    to the extent you might exceed 10 CFR 100 guidelines,
11    because the design basis for that doesn't include hydrogen
12    pressure.  It talks about the large-break LOCA pressures.
13              How are you protecting against these kind of
14    smaller effects that some of the regulations might be trying
15    to protect against?
16              I mean it seems to me like conditional probability
17    of containment failure is somewhat limited in terms of all
18    the regulatory objectives.
19              Is that a consideration in there anywhere?  Do you
20    deal with that some way?
21              MR. KING:  I think the key consideration is what
22    do you define as containment failure?
23              You're sort of in two different spaces.
24              Part 100 space is design basis, very stylistic
25    accident, very conservative, you know, assumptions on
.                                                                69
 1    transport off-site and so forth.
 2              That was looked at back when Appendix J, I think
 3    it was, was revised, and basically, the conclusion was
 4    you've got to really have a high leak rate before you even
 5    start to worrying about risk-significant releases.
 6              DR. KRESS:  I was thinking in terms of FC curves
 7    again, but there is consequences due to leakage of fission
 8    products, and you might want to have limits to -- at high
 9    frequency, low releases, and as the frequency goes up, you
10    can stand the higher -- I mean the frequency goes down, you
11    can stand the higher releases, but we don't deal with that
12    whole curve.  We just deal with the -- here, it seems like
13    we're dealing with the upper end of it.
14              MR. KING:  We deal with one end of that curve. 
15    Recognize, what we're doing is a feasibility study.  This is
16    not the end of the story.  And I don't think we've gotten
17    into that level of detail as part of this feasibility study,
18    at least the stuff that I've seen, we haven't.
19              MS. DROUIN:  Also, if I understood -- and I might
20    have misunderstood what you were saying, but it sounded to
21    me that you were talking more about a regulation that would
22    be a containment regulation versus a regulation that's
23    dealing with combustible gases.
24              DR. KRESS:  Normally, when we calculate the design
25    basis accidents, we don't include hydrogen pressure in those
.                                                                70
 1    except for some specific parts of the containment analysis,
 2    but what I really had in mind was, if you did a PRA and
 3    calculated the actual fission product releases, even from
 4    un-failed containments, there may be reasons to limit those,
 5    and the rules you have on hydrogen in terms of what's
 6    required, even then, even the recombiners may have some
 7    effect on that for some sequences, and you know, you may be
 8    exceeding a value that is not going to kill people, but you
 9    didn't want to release that amount of fission products
10    anyway.
11              MR. KING:  We haven't done the calculations to do
12    what you're talking about.  I think, if we did them, we'd
13    probably find out that the risk significance of those type
14    of situations isn't very much.
15              DR. KRESS:  Probably very low.  That's because
16    we're defining risk in terms of the safety goals.
17              MR. KING:  Right.  But I'm saying that based upon
18    the Appendix J work that's been done, where they did look at
19    higher release rates.
20              DR. KRESS:  I'm sure that's what you'll find.
21              MR. KING:  And also, when you look at realistic
22    off-site transport versus the Part 100-type calculation,
23    there's a big difference in terms of the way it's treated
24    there, as well.
25              DR. SHACK:  We're going to have to move.  We're
.                                                                71
 1    running behind.
 2              MR. LEITCH:  I just have one question regarding --
 3    it looks as though you have a concern about power supply to
 4    igniters during station blackout conditions.
 5              Certain BWR Mark II's have post-LOCA hydrogen
 6    recombiners.
 7              Is there a similar concern with power supplies to
 8    those hydrogen recombiners?
 9              MS. DROUIN:  For the hydrogen recombiners, we're
10    proposing eliminating that requirement.  That's not a
11    concern there.
12              MR. KING:  The answer is basically no, because
13    they're inerted containments, and it would take a long time
14    to de-inert from radiolysis or whatever is occurring.
15              DR. WALLIS:  On page 11, you say the type of
16    accident, not risk significant.  This is what type of
17    accident?
18              MS. DROUIN:  Postulated LOCA.
19              DR. WALLIS:  A LOCA is not a risk-significant
20    accident?
21              MS. DROUIN:  Excuse me?
22              DR. WALLIS:  LOCA is not a risk-significant
23    accident?
24              DR. SHACK:  The hydrogen you generate.
25              MS. DROUIN:  No, the LOCA -- a large-break --
.                                                                72
 1    sorry -- a postulated loss-of-coolant accident is not
 2    showing up as a contributor, as a large contributor.
 3              DR. POWERS:  Hardly even makes the cut-sets on
 4    most plants.
 5              DR. WALLIS:  Okay.  So, what's the criterion for
 6    not risk significant?
 7              You have a number that you use to decide if it's
 8    significant or not.  What is it?
 9              MS. DROUIN:  That gets back into our framework,
10    and depending -- it's 10 to the minus 5.  That's what we're
11    using.  10 to the minus 4 for the core damage frequency.
12              DR. KRESS:  That was one of my questions that I
13    wanted to ask you about the table.  This looks like an
14    opportunity to do it.
15              DR. POWERS:  No, it's not.  We're out of time.
16              DR. KRESS:  Okay.  Maybe I won't ask it.
17              DR. BONACA:  That is specified when you mean the
18    50.46 LOCA here.
19              MS. DROUIN:  Yes.
20              DR. BONACA:  There are very specific criteria on
21    the amount of oxidation and so on and so forth.
22              So, there is a quantification there to support the
23    statement.
24              DR. WALLIS:  What are your objectives, and what
25    are the criteria you're using?  That's why I'm asking this
.                                                                73
 1    question.
 2              I think it would be helpful if, instead of all
 3    these words, you simply say we applied these criteria, this
 4    led us to these conclusions, and that's why you should
 5    support what we want to do, and if you don't give us that
 6    logic, it's all words, and I just can't grasp anything.
 7              DR. KRESS:  Well, that logic is kind of in the
 8    framework document.
 9              MR. KING:  It's in the framework.  You go back to
10    the framework table.  It has CDF and LERF values on it. 
11    Take a look at the sequence.
12              DR. WALLIS:  But you're telling me to read
13    something which isn't being presented.
14              MS. DROUIN:  Well, it would have come out if we'd
15    had more time.  We would have explained it better.
16              DR. WALLIS:  Well, maybe, then, you should
17    concentrate on the things you omitted.
18              DR. POWERS:  It seems like all your slides are
19    very clear except for this long-term one, just because this
20    is unique.
21              MS. DROUIN:  We are proposing -- this would not be
22    a requirement in 50.44, but we are recommending to the
23    Commission that, after the 24 hours, because we still feel
24    there is a concern, that this be addressed under the severe
25    accident management guidelines.
.                                                                74
 1              DR. WALLIS:  I'm sorry.  I've got to ask you a
 2    question on number 15.
 3              It says maintain containment integrity for all
 4    risk-significant events.
 5              Does that mean additional failure probability of
 6    zero?
 7              MS. DROUIN:  No.
 8              MR. KING:  Less than .1, which is our framework
 9    document.
10              DR. WALLIS:  So, maintain integrity, the public
11    has to understand, means live with a 10-percent probability
12    of failure.
13              MR. KING:  Conditional.
14              DR. WALLIS:  You've got to say that.  I mean
15    containment integrity, to me, means it doesn't break, and
16    you're saying containment integrity to you means that it has
17    a 10-percent failure probability.
18              MR. KING:  Yes.
19              DR. WALLIS:  I think that should be clear.  I
20    don't think you should use words lightly like that.
21              DR. KRESS:  The .1 -- is that the aggregate for
22    all sequences, or is that for each sequence?
23              MR. KING:  It's intended to be the aggregate for
24    all sequences.
25              I think what we found out is, you know, a lot of
.                                                                75
 1    sequences at zero, and it's only a couple of specific ones
 2    that -- like one or two that gets you anything.
 3              DR. KRESS:  So, in practice, you can apply it on a
 4    sequence basis --
 5              MR. KING:  Yeah.
 6              DR. KRESS:  -- as opposed to the aggregate.
 7              MR. KING:  In practice, yes.
 8              DR. KRESS:  I got my question in after all.
 9              DR. POWERS:  There you go, Tom.
10              MS. DROUIN:  When you're looking at this bullet
11    and you go back to the framework, you know, there are four
12    strategies, and so, this is trying to get to a
13    performance-based one where -- and we just gave one small
14    part of the whole performance-based requirement, but you
15    could come in on any of those levels and show that you met
16    it.
17              So, instead of maybe coming in -- saying you were
18    a plant that you didn't want to have igniters, for whatever
19    reason, I mean you can come in and show that your
20    risk-significant accidents aren't contributing, you're below
21    those numbers that we have in the framework.
22              These numbers would not appear in the regulation,
23    but this would be more a description in how you would meet
24    this in your regulatory guidelines, or you'd come in and
25    look at your whole accident or you'd come in and show that
.                                                                76
 1    you're not threatening your containment, and there would be
 2    many different ways to meet this one.
 3              DR. WALLIS:  Mr. Christie's statement, "can
 4    withstand the hydrogen burn," to me that means hydrogen burn
 5    happens and nothing happens to the containment.  Do you mean
 6    there's a .1 percent of failure probability?
 7              MS. DROUIN:  These are Mr. Christie's words out of
 8    his submission.
 9              DR. WALLIS:  But you quote them.
10              If I were a tire manufacturer and I said my tires
11    won't lose their tread and then what it really meant was .1
12    probability, that's a tremendous difference in statement.
13              DR. KRESS:  If you had an alternative requirement
14    like this, would you cast it in terms of means?
15              MS. DROUIN:  Yes.
16              DR. KRESS:  That's because the safety goals are
17    specified as means?
18              MS. DROUIN:  Yes.
19              DR. WALLIS:  I guess I'll have to ask Mr. Christie
20    what he means, but you believe that your equivalent -- your
21    recommendation is equivalent to his.
22              MS. DROUIN:  Yes, we do.  We believe it addresses
23    his concern.
24              DR. KRESS:  If you cast this in terms of means,
25    does that mean you have to have a PRA with an uncertainty
.                                                                77
 1    analysis to determine what the mean is?
 2              MR. KING:  Where we've had such information,
 3    that's what we've used.
 4              Where it's been point estimates, we don't take a
 5    point estimate for a single plant.  We look at a whole
 6    ensemble of what came out of the IPEs, and you know, they
 7    define a range, basically, also.
 8              DR. KRESS:  That's a kind of a mean, yes.
 9              MR. KING:  I'm not going to call it a mean, but
10    it's not a point estimate.  It's looking at a range of
11    calculations that have been done.
12              DR. KRESS:  This is for a specific licensee to use
13    an alternative requirement, and it's for his plant, and he'd
14    have to do a PRA for his plant, it seems to me like, and
15    he'd have to do an uncertainty analysis to determine what
16    his mean is, or do something that assures the point estimate
17    he gets is higher than the mean or something.
18              MR. KING:  Do a mean or do a certain set of
19    sensitivity analysis to show that he's got a reasonable
20    number.
21              MS. DROUIN:  You're going to have to have an
22    understanding of your uncertainty and the impact on the mean
23    value, absolutely.
24              MR. KING:  Anyway, the bottom line of what we're
25    recommending is eliminate the requirement for hydrogen
.                                                                78
 1    recombiners, for hydrogen monitoring.
 2              If station blackout is a risk-significant
 3    sequence, provide back-up power to the igniters for Mark
 4    III's and ice condensers and have basically a practical
 5    cutoff of 24 hours beyond that, let your severe accident
 6    management program deal with situations -- long-term
 7    situations.
 8              MR. LEITCH:  And the elimination of the hydrogen
 9    recombiners -- does that impact in any way the requirement
10    that containment is allowed to be inerted -- excuse me --
11    de-inerted 24 hours prior to shutdown and not required to be
12    inerted until 24 hours after startup?
13              MR. KING:  No, we're not proposing any change to
14    that.
15              Mark I's and II's would still have the same
16    inerting/de-inerting requirements.
17              MS. DROUIN:  Yes.  But the thing I want to point
18    out on the Mark III's and the ice condensers -- we aren't
19    proposing in the risk alternative regulation that they have
20    to have back-up power.
21              What we're proposing is that, if station blackout
22    is a contributor, they have to deal with it, and so, they
23    have different ways they could deal with it.
24              They could either come back and show that station
25    blackout is not a concern, or if it a concern, their
.                                                                79
 1    containment isn't challenged, or they can come in and put
 2    back-up power.
 3              I mean it's open-ended.  It's flexible in how they
 4    can deal with it.
 5              DR. KRESS:  This is one place where you say you
 6    would accept a very low frequency --
 7              MR. KING:  Yes.
 8              MS. DROUIN:  Yes.
 9              DR. KRESS:  -- even though it's just for a
10    specific sequence.
11              MR. KING:  Yes.
12              MS. DROUIN:  Yes.
13              DR. KRESS:  You would sort of compromise
14    defense-in-depth a little for a specific sequence by
15    accepting very low frequency, as opposed to a high
16    conditional containment.
17              MS. DROUIN:  I don't think that's compromising
18    defense-in-depth.
19              DR. KRESS:  I don't think it is either, but some
20    people might think so.
21              MR. KING:  It's the rationalist approach to
22    defense-in-depth.
23              DR. KRESS:  Yes.
24              MS. DROUIN:  Then the last thing, of course,
25    that's in the paper is the recommendation to proceed with
.                                                                80
 1    rulemaking immediately upon this.
 2              I don't know, Tony, if you want to add anything in
 3    that regard.
 4              MR. MARKLEY:  This is Tony Markley.  I'm with NRR
 5    in the rulemaking section.
 6              Basically, once the paper comes back from the
 7    Commission, what we would hope the Commission would tell us
 8    is to proceed with rulemaking expeditiously.
 9              Given all the work and everything that has gone
10    into this, we would expect to submit a schedule to the
11    Commission for the rulemaking effort and then proceed to
12    proposed rulemaking without doing a rulemaking plan. 
13    There's certainly been a thorough evaluation of the issues
14    to this point to get us to proposed rulemaking.
15              Also, what we'd get back from the Commission is
16    basically the Commission's decision on 50.44 and going to
17    rulemaking, and that would provide us a basis for making a
18    decision on Mr. Christie's petition.
19              DR. KRESS:  Did you want a letter from us on just
20    the 50.44 part?
21              MR. KING:  We certainly would like something from
22    you on the 50.44 part, and if you want to say something on
23    the two policy issues, that's up to you.
24              DR. APOSTOLAKIS:  But the thing that concerns me
25    is the -- what you call Attachment 1, "Framework for
.                                                                81
 1    Risk-Informed Changes to the Technical Requirements of 10
 2    CFR 50, Revision 2."
 3              Our letter on 50.44 necessarily has to say
 4    something about that.
 5              On the other hand, this is a document that you
 6    told us earlier has already been updated.  Rev. 2 is a
 7    little old now.
 8              MR. KING:  There was a version that went to the
 9    Commission back in April.  What you have now is the next
10    update of that, and as we proceed, there will be even
11    further updates.
12              DR. APOSTOLAKIS:  At which point do you expect
13    this framework to be final?
14              MR. KING:  I would say probably -- we're working
15    on 50.46 now.
16              I'd say let us get through that, and then we'll
17    probably have enough experience to call it essentially a
18    final.
19              DR. APOSTOLAKIS:  So, that would be in a year?
20              MR. KING:  Probably no more than a year, maybe six
21    months, something like that.
22              DR. APOSTOLAKIS:  So, is it possible, Tom, then,
23    to write a letter that comments on 50.44 --
24              DR. KRESS:  I was having difficulty doing that,
25    yeah.
.                                                                82
 1              DR. APOSTOLAKIS:  -- and say that, you know, the
 2    elements that it is based on that come from the attachment
 3    are reasonable but make sure not to explicitly endorse the
 4    attachment either.
 5              DR. KRESS:  I think we'll have to go that way.
 6              DR. APOSTOLAKIS:  Something like that.  We have to
 7    rely on a master of the English language.
 8              DR. SHACK:  Maybe we can discuss that later. 
 9    We're running behind here.
10              DR. APOSTOLAKIS:  We have to understand what they
11    want, too.
12              MR. KING:  That's would be fine.
13              DR. WALLIS:  I'd like to say something here.
14              I want to try to obey George's rule about opening
15    your mouth and saying things.
16              This is an example of risk-informed alternative,
17    right?
18              So, what I was hoping to see was a logical
19    explanation of how risk information influenced your decision
20    on these various categories of decision you had to make.
21              My impression is that Mr. Christie's opinion is
22    more important than the logical exposition of how you used
23    risk information --
24              MS. DROUIN:  Absolutely not.
25              DR. WALLIS:  -- because almost every slide, he is
.                                                                83
 1    cited, rather than some number which says this is the
 2    criterion we used or this is how risk information was used
 3    in our decision-making.
 4              MS. DROUIN:  As I explained, we added those
 5    bullets on there so that you knew -- once we went through
 6    and made our recommendation, which was done independent of
 7    Mr. Christie's, and we looked at his petition, we were just
 8    giving you information of where our risk-informed
 9    alternative did or did not match up with his petition.
10              DR. WALLIS:  Well, I'm not trying to be critical. 
11    This is a risk-informed environment we're talking about. 
12    So, that's the important aspect we ought to focus on, not
13    the opinion of one person.
14              I don't understand why this is given that
15    prominence.
16              MR. KING:  The only reason it was put on there
17    was, one, we're into a situation now where we are in
18    petition for rulemaking.
19              DR. WALLIS:  So, I'm really mentioning Mr.
20    Christie to contrast it with what I expected to find as the
21    emphasis of your presentation.
22              MR. KING:  We tried to make your life easier by
23    putting it on our slides, basically.
24              DR. KRESS:  Yeah, we're going to get involved in
25    discussing that petition.
.                                                                84
 1              MR. KING:  Mr. Christie was one of many commenters
 2    on this, and he didn't get any more or less weight than any
 3    other commenters.
 4              DR. WALLIS:  But the risk-informed approach has
 5    nothing to do with what someone's opinion is.
 6              MR. KING:  We put that on to make your life easier
 7    in case you wanted to see how the two matched up.
 8              DR. WALLIS:  It has nothing to do with what
 9    someone's comment is.
10              It's a logical process, and that's what I'm
11    looking for.
12              DR. SHACK:  Well, the thing I got out of this was,
13    you know, you can do risk-informed regulation when you have
14    1150, 1560, and a whole bunch of other stuff to supply all
15    the technical information that you need in order to do this.
16              DR. KRESS:  Yeah, that's what I got out of it.
17              DR. SHACK:  This is one you can risk-inform,
18    because you understand the risk very well.
19              MS. DROUIN:  You know, if we'd had the time, it
20    would have been very nice to go through and explain how we
21    came up through our risk-informed manner in applying the
22    framework.
23              I apologize, we did not have the time.  We just
24    had time to give you the bottom line.  That's what we did.
25              DR. KRESS:  Yeah, I thought you did a pretty good
.                                                                85
 1    job of that in the document, in the attachment.
 2              MS. DROUIN:  There is a 100-page attachment that
 3    goes into quite a bit of detail.
 4              DR. BONACA:  My sense would be that, by the time
 5    we get 50.46 and we get close to endorsing a final approach,
 6    it will be worthwhile to have a subcommittee meeting where
 7    we can be walked through some of the examples, so that we
 8    have a better understanding of how the logic works.
 9              DR. APOSTOLAKIS:  I would suggest that, on page 7
10    of the Commission paper, where you say, "Risk insights
11    associated with hydrogen generation and combustion have led
12    to the following conclusion" -- why don't you add those risk
13    considerations that led you to this?
14              I really like what Dr. Shack just said.  Unless
15    you know that there is a hell of a lot of work behind this,
16    you could never really tell.  You know, risk insights -- I
17    mean what does that mean?  A couple of guys sat around the
18    table and thought about it?
19              MS. DROUIN:  I lost your point.
20              DR. APOSTOLAKIS:  You don't give credit to the
21    Office of Research.
22              MS. DROUIN:  Oh.
23              DR. APOSTOLAKIS:  I'm sorry, but you don't.  By
24    just saying risk insights lead to the following, you don't
25    give them credit, and you know, Dr. Shack just said, you
.                                                                86
 1    know, you have 1150, you had the IPEs, you had this.  I
 2    would add a page or two, maybe a diagram from an event tree
 3    or something.  This is really important.
 4              MR. KING:  Okay.  I understand your comment.
 5              We're done.
 6              DR. SHACK:  We have two presenters from industry.
 7              Mr. Heymer wants to talk on the benefit of NEI.
 8              MR. HEYMER:  Good morning.  My name is Adrian
 9    Heymer.  I'm a project manager at NEI dealing with
10    risk-informed regulation.
11              I'm here to give you a brief, I guess, 15-minute
12    presentation on what we think -- or where we think we stand
13    as regards option 2 and option 3.
14              But before I do that, I'd just like to make a
15    request.
16              We've heard mention of two SECYs.  There's
17    obviously a great interest in the industry in both those
18    SECYs.
19              There is a Commission briefing coming up on option
20    2, and we would like those SECYs released as soon as
21    possible so that we can be constructive in our comments as
22    we move forward.
23              We don't know what's in those SECYs.  Obviously,
24    we've had a brief overview today, but I think it would be
25    good for the overall progression of risk-informed regulation
.                                                                87
 1    if we could move those things forward.
 2              I did have some comments on what I heard today as
 3    regards option 2, and I can get to those towards the end, if
 4    necessary, of what I heard from the NRC staff on option 2.
 5              I think there's some issues which the industry
 6    sees as fairly significant associated with option 2.
 7              I think it's important that we focus on the
 8    safety-significant SSCs, and that presumes that we have some
 9    confidence in the categorization process, and I think once
10    we've done that and we have some confidence in the
11    safety-significant SSC categorization process, there should
12    be less concern about how we're handling SSCs and activities
13    associated with low safety significance.
14              There has been significant -- and that's probably
15    on the weak side -- interaction between the industry, STP,
16    other utilities, and NEI and the NRC staff on what goes in
17    RISC-3.  We've struggled to understand the NRC staff's
18    position on some of those issues in some cases.
19              DR. SHACK:  You don't mean the categorization. 
20    You mean the special treatment.
21              MR. HEYMER:  The special treatment, yes.  Thank
22    you.  And I think we're still struggling.
23              I can understand, to a certain extent, why the
24    staff's there, and it's a change in emphasis, but we're a
25    little concerned about describing how to -- or how we're
.                                                                88
 1    going to implement activities in fairly significant detail,
 2    as it appears to us at the moment, on SSCs that are of low
 3    safety significance.
 4              On the ASME standard and PRA certification, which
 5    is central to the -- I guess may be central to the
 6    categorization process, we believe a peer review is an
 7    acceptable methodology to accept -- to assess the PRA
 8    suitability associated with -- for the use in option 2, and
 9    to that regard, we submitted that to the staff for their
10    review.
11              As you're well aware, there have been significant
12    NRC staff comments on the standard, and I'm glad to say that
13    the industry and the NRC staff will be sitting down to try
14    and sort out where we go with the standard next week, and I
15    understand that there's a public meeting on that next week
16    to try and see a way ahead of how we deal with the standard.
17              DR. POWERS:  You've indicated that a peer review
18    is an acceptable methodology here.
19              Peer review is, of course, a widely used tool
20    within the scientific institution and probably has served
21    the scientific and engineering sciences well over the past,
22    but it is getting some reexamination in the more academic
23    areas.
24              I guess my question to you is, do you think that
25    the peer review you're talking about here is susceptible to
.                                                                89
 1    the kinds of difficulties that they have encountered with it
 2    in areas like NSF and NIH?
 3              MR. HEYMER:  I'm not aware of those difficulties,
 4    Dr. Powers, but what I will say is, if you get a group of
 5    people together who are knowledgeable about the subject, who
 6    are not directly linked to it, and they come in and they
 7    review it and they provide you insights and input, I think
 8    it's incumbent upon the utility that has done the PRA for
 9    that specific unit to take action on those comments and move
10    forward, and perhaps we haven't made that clear.  I think
11    that is our intent.
12              I mean I think the peer review is just one step,
13    it's one insight, and I think you need to follow up on what
14    did the peer review come out with and how am I dealing with
15    those issues, as we move forward.
16              DR. POWERS:  You got the essence of where I was
17    going on this, was that there has to be more than just the
18    requirement for peer review.
19              There has to be followup on the findings and doing
20    something about it, so there's really two reviews, one the
21    peer review and then what did you do about it, as well.
22              MR. HEYMER:  Yes.
23              So, I guess that is what I have got to say on
24    option 2.
25              There are some interactions scheduled with the
.                                                                90
 1    staff in a couple of weeks, and we look forward to reading
 2    the SECY.
 3              I'll try and make this as quick as possible in the
 4    interest of time.
 5              I think, as regards option 3, if you just sit back
 6    and think about where were were 12 months ago, 15 months
 7    ago, and where we are today, it is a significant step
 8    forward.
 9              We have interacted with the staff, and I think
10    there is an issue out there on option 3 as regards -- if
11    you're going to add additional requirements, that there
12    needs to be some form of assessment of what that burden is
13    going to entail, both as regards to cost as well as the
14    safety benefit.
15              The decision that the NRC has made -- and I think
16    it's come out pretty well as regards the recent presentation
17    just a few minutes ago -- is that the NRC decision should be
18    based on up-to-date technical analysis and information, and
19    I think, when you look at some of the material that's
20    associated with where the NRC has drawn its conclusions, it
21    may not be the most up to date, and in some cases, the
22    industry has some concerns about the technical basis.
23              The up-to-date issue, certainly as regards the PRA
24    and the IPE information, I think that's incumbent upon the
25    industry to make that information available.  There is a
.                                                                91
 1    significant benefit to the industry to making sure that the
 2    PRA information is available, that is up to date, is made
 3    available to the NRC so that they can base their conclusions
 4    and their discussions and their recommendations on the
 5    latest information and data.
 6              We're working within the industry, through the
 7    Risk-Informed Regulatory Working Group, to try and achieve
 8    that aim.
 9              I think the debate at the moment centers around,
10    well, what do we give the staff, how much do we give them,
11    do we give them the complete PRA all the time, or do we give
12    them a summary of the assumptions or changes in the
13    assumptions, and a summary of the results, and that's what
14    we're struggling with at the moment, so that, one, it
15    doesn't present a burden on ourselves to submit a huge
16    amount of information which is going to present even more
17    burden on the NRC to look at and review, but rather, can we
18    narrow that down, and when we've got our own thoughts
19    together, I think we intend to come and talk with the NRC
20    staff to see how best we can facilitate that action.
21              But I think it's important to recognize that
22    aspect, and I think, as you go forward in the rulemaking
23    process, there needs to be some form of estimate.
24              I'm not going to say it's a cost-benefit or a
25    back-fit analysis, but there must be some form of estimate,
.                                                                92
 1    and in fact, I think the rulemaking process requires of that
 2    that there needs to be an estimate of the benefit and the
 3    burden on the licensee.
 4              We did have some comments and some concerns about
 5    the way the framework document was written, and talking with
 6    the staff in some of our interactions, it is clear that
 7    they're revised the document, and now I heard today that
 8    there is a revision to the revision, and that's good.  We do
 9    recognize that as an evolving process.
10              I think they've made a good effort to try and link
11    it back to the sort of cornerstones to produce a document
12    that describes the overall framework of how they're going to
13    look at the technical requirements from a risk perspective.
14              DR. APOSTOLAKIS:  Adrian, I have a question on the
15    previous slide.
16              You say that there should be an estimate of
17    licensee/NRC benefits and burden when new requirements are
18    about to be imposed.
19              Shouldn't the same thinking apply when
20    requirements are to be removed?
21              In other words, couldn't the NRC say, yeah, it's
22    unnecessary, but it doesn't cost you much, go ahead and do
23    it anyway?
24              Why would the cost or burden be important only
25    when we impose things?  When we remove them, then we can do
.                                                                93
 1    the same thing.
 2              MR. HEYMER:  Well, I think if you're removing the
 3    burden, even if it's not costing you very much, there's
 4    still -- you come out on the plus side.
 5              DR. POWERS:  I've certainly heard people make this
 6    argument that removing burdens ought to be subjected to some
 7    benefit-burden analysis, and I guess I don't agree.
 8              I think that, if we find regulations that are
 9    imposing burden unnecessarily and we can remove them, that
10    it is the essence of good regulation to get rid of those
11    things.
12              DR. SHACK:  The trick is when you have burden
13    reduction but some increase in risk.
14              DR. POWERS:  I think that the -- again, the
15    essence of our approach here is that, if the incremental
16    risk is minuscule but removing burden, we're obligated under
17    our self-imposed standards of good regulation, to get rid of
18    those things, because the burden estimates that we tend to
19    make -- I think if we look at them historically, they are
20    under bounds, on the true burden, and there's no question
21    that they're a diversion of focus, just no question about
22    that.
23              DR. APOSTOLAKIS:  It seems to me that the
24    Caesar's-wife saying applies here.  You're going to do it
25    both ways.  You have to do it both ways.
.                                                                94
 1              DR. WALLIS:  Well, someone has to be looking at
 2    the public benefits and burden.
 3              MR. HEYMER:  And I think the public benefit is
 4    there by focusing on those aspects which have real safety
 5    significance.
 6              I think reducing both the economic and the
 7    resource burden as regards manpower, what you're looking at,
 8    so that you can focus -- you've got more people available to
 9    focus on the important stuff --
10              DR. WALLIS:  I think you have to keep saying that. 
11    Otherwise, it gives the impression that it's just NRC and
12    the licensees having a debate on who gets the best benefit
13    and the least burden.
14              Somewhere in there the public is looking on and
15    saying what's in it for us?
16              MR. HEYMER:  Well, yes, I think you're quite
17    right, Dr. Wallis.
18              DR. POWERS:  I guess I will interject again and
19    say that I think it's the responsibility of the NRC to
20    uphold the public's interest in these things.
21              MR. HEYMER:  Okay.
22              We would like to meet with the staff on 50.44 to
23    discuss some of the basis and some of the issues that are in
24    the technical document, certainly the technical document
25    that's associated with the ice condenser issue.  I think
.                                                                95
 1    that will improve the process.  It will get us off into a
 2    much more sound footing.
 3              We have some concerns about some of the analysis
 4    and the assumptions that went into that analysis, and I
 5    think it is important as we go through this process that, if
 6    we're going to produce a document like that, that the
 7    licensees at least get a chance to look at the assumptions
 8    going into the study.
 9              I'm not going to say you shouldn't do the study. 
10    We're not saying that you shouldn't move forward and develop
11    a study and show us the results.
12              But I do think it's important that the assumptions
13    that go into the study need to reflect what's at the plant
14    and in the plant conditions, and we have some concern in
15    that regard.
16              So, that is why we would like to meet with the
17    staff.
18              I don't think it changes the outcome of their
19    recommendation, but I think if you have an NRC report out
20    there that perhaps has faulty assumptions going in and
21    doesn't have sound assumptions or sound results coming out,
22    that that's out there for somebody to use in the future, and
23    it may not necessarily have to be that way.  So, that was
24    the real main point there.
25              On 50.46, we are working with the owners groups. 
.                                                                96
 1    Each of the owners groups has got their own particular view
 2    on 50.46, as do other people, and we're trying to coordinate
 3    that effort to improve the efficiency of what we do and the
 4    effectiveness of the regulatory process as we move through
 5    50.46.
 6              50.46 is a very large regulation, is a complex
 7    regulation, and I think if we have too many people coming in
 8    with different ideas to the staff, we're going to get lost. 
 9    So, I do think we are trying to focus that issue and to give
10    it some priority to help with the process of improving and
11    implementing --
12              DR. WALLIS:  When you say it's a large regulation,
13    you mean it has a big effect.
14              MR. HEYMER:  A big effect.
15              DR. WALLIS:  The actual number of words in the
16    regulation is pretty short.
17              MR. HEYMER:  Yes.  It has a big effect.
18              DR. WALLIS:  There's a lot of leverage.
19              MR. HEYMER:  It's a complex regulation.  Once you
20    get into it, you find that you're affecting a number of
21    other issues.
22              And we're also talking with the owners groups of
23    where do we go once we've defined the large-break LOCA, what
24    activities do we look at, and how are we going to manage
25    that from an industry perspective, which I think will help
.                                                                97
 1    the staff in moving forward.
 2              That's really what I've got to say on the option 2
 3    and option 3 activities.
 4              I do want to make --
 5              DR. WALLIS:  Do you think that risk-informing
 6    50.44 is helpful?  Is there some benefit from this
 7    risk-informing activity?
 8              MR. HEYMER:  Helpful in regards to has it enabled
 9    us to work through a regulation that was reasonably
10    straightforward and set a process for doing so.
11              DR. WALLIS:  Is industry going to buy into this
12    risk-informed activity now they've seen this example?  Does
13    it help illustrate how it can be done and what the benefits
14    are?
15              MR. HEYMER:  I think it's helped in sorting out
16    some of the problems that are associated with reviewing and
17    risk-inform the technical requirements.
18              I think when we look at 50.44 -- and we've still
19    got a few things to iron out, a few wrinkles to iron out,
20    but I think, overall, we're going to say yes, this process
21    came out as a positive experience and we can move forward.
22              There's certainly a lot more interest beginning to
23    develop in some of the other activities from the option 3
24    perspective as a result of where we're coming out on 50.44.
25              When I listened to the presentation that we just
.                                                                98
 1    heard from the staff on what their recommendations would be
 2    on 50.44, I think we've almost converged and say yes, that's
 3    about as far as we can do.  We've set a process.
 4              As I say, there still are some wrinkles that we
 5    want to iron out with the staff associated with some of
 6    their technical requirements or the technical basis for some
 7    of their suggestions, but I don't think that changes the
 8    outcome of the recommendation too much.
 9              I heard some statements on option 2 as regards the
10    SECY, and I just want to emphasize that we did have a
11    concern in our comments on the SECY as regards option 2 --
12    that is, the ANPR -- about prescriptiveness in the rule, and
13    I do think I heard some comments and statements about the
14    Consumer's Power.
15              We haven't interacted with Consumer's Power on
16    that topic, but we do recognize there are other utilities
17    out there that might want to look at a different way of
18    implementing 50.69, and that's why favor a guideline
19    approach, we favor an endorsed NRC guideline approach that
20    if somebody else comes up with a different methodology, that
21    they could develop a guideline and present that to the staff
22    for endorsement, as we move forward.
23              If it's in the rule, it does make it a lot more
24    difficult to adjust things as we move forward, and the more
25    detail you put in the rule, the more restrictive and rigid
.                                                                99
 1    the process becomes, and that's not necessarily good as you
 2    move forward.
 3              I think our experiences with detailed prescriptive
 4    regulation has not been good, and that's why we would
 5    propose a guideline.
 6              Part of that guideline, we believe, would include
 7    something along the lines of a program summary associated
 8    with commercial practices.
 9              DR. SHACK:  Thank you, Mr. Heymer.
10              Mr. Christie?
11              MR. CHRISTIE:  Good morning.  My name is Bob
12    Christie.  I'm the owner of a firm, Performance Technology,
13    Knoxville, Tennessee.
14              Some background:  I've been in nuclear power for
15    about 26 years now, and for the last 21 or so, 21, 22, I've
16    been involved in probabilistic risk assessment and all the
17    uses of it.
18              I've come today to give a quick summary of what we
19    had in interaction with the Nuclear Regulatory Commission,
20    ACRS staff on July 11th and 12th regarding combustible gas
21    control.
22              I'd like to do it with just one slide and give you
23    a briefing on where we stand with respect to the various
24    things.
25              There are four basic categories of things that are
.                                                               100
 1    going on in the industry with respect to combustible gas
 2    control at this time.
 3              I guess the first is the 10 CFR 50.12 exemption
 4    request.
 5              The first one of these was submitted by San Onofre
 6    back in 1998, was approved in September 1999.
 7              Oconee just submitted on back in July.
 8              There may or may not be another one this week, and
 9    there will be some more to follow.
10              So, the action is that utilities are submitting
11    50.12 exemption requests and will be doing so in the
12    immediate future.
13              How many, we don't know, and so on.
14              Petition for rulemaking -- as most of the ACRS
15    members know, I submitted a petition -- well, I didn't
16    submit a petition for rulemaking.
17              I submitted a letter to the NRC Commissioners on
18    October 7th, last year, after the San Onofre safety
19    evaluation report was approved, suggesting a lot of things,
20    one of which was changed to 10 CFR 50.44 to enhance safety.
21              The Commissioners turned it over to the Office of
22    Nuclear Reactor Regulation, who discussed with me making it
23    a petition for rulemaking.
24              We did make it a petition for rulemaking.  It was
25    noticed in the Federal Register in January of this year. 
.                                                               101
 1    The public comments have been submitted, and it is still a
 2    petition for rulemaking.
 3              It is not an option 3 petition for rulemaking.  It
 4    is a petition for rulemaking under the existing normal
 5    practices of the NRC with respect to petitions for
 6    rulemaking.
 7              We've had a number of interactions with the ACRS
 8    on this petition for rulemaking, including the meeting with
 9    the subcommittee on June 29th, the meeting with the full
10    committee on July 12th.
11              There were a number of letters from myself to
12    members of the NRC staff which are defined here in a letter
13    to Mike Snodderly, July the 3rd, letter to Mr. Collins, July
14    the 14th, letter to Ms. Carpenter, July 20th.  If you read
15    those letters, you can get definite understanding that we
16    are not very happy with the way the petition for rulemaking
17    has been treated.
18              With respect to the SECY option 3 framework, we've
19    had interaction with the staff, again back in June, July. 
20    There have been a number of letters from myself to Dr.
21    Thadani, but I think we've finally cleared up in our own
22    minds what are the differences between what the -- what we
23    call the whole plant study from the industry has been trying
24    to accomplish versus option 3, and we now have, I think,
25    finally worked out the differences.
.                                                               102
 1              There are absolute differences between them.  They
 2    are major.  We don't have the same objectives.  We don't
 3    have the same principles.  We don't have the same
 4    implementation plan.
 5              So, it's definitely a different way of proceeding,
 6    and hopefully I've explained it fairly well in the letters
 7    that I've sent, and when we go into the next meeting on the
 8    framework, we can go over it again if we have to.
 9              As far as the option 3, 10 CFR 50.44, I notice
10    there's a lot of stuff on the slides about my position and
11    whether the NRC agrees with it or not.
12              I will have to wait to see the SECY and the
13    recommendations for rulemaking before I can say whether I
14    agree with them or not.
15              DR. WALLIS:  Can I ask you, then, my question?
16              MR. CHRISTIE:  Sure.
17              DR. WALLIS:  Your petition asks that the reactor
18    containment withstand a hydrogen burn.  That's what you
19    said, simply can withstand the hydrogen burn.  What do you
20    mean by that?
21              MR. CHRISTIE:  Okay.
22              If you look at the petition for rulemaking, for
23    the large drives --
24              DR. WALLIS:  Do you mean by that that there's no
25    probability of failure?
.                                                               103
 1              MR. CHRISTIE:  No.  What we've said is that we
 2    would look at the sequences that have a high probability of
 3    causing core damage and we would look at the ability of the
 4    containment to withstand the burn, and back in the -- and
 5    what we meant in that sense was the work that we had done in
 6    IDCOR, industry degraded core studies that were done back in
 7    the '80s --
 8              DR. WALLIS:  I'm just looking for a definition of
 9    what you mean by --
10              MR. CHRISTIE:  That's what I'm trying to explain,
11    Dr. Wallis.
12              DR. WALLIS:  Okay.
13              MR. CHRISTIE:  We did a whole bunch of studies
14    back in the IDCOR to look at what was the containment
15    capability both from a design and an ultimate standpoint and
16    see whether or not we felt that the containments would
17    withstand the burns for the large dry containments.
18              DR. WALLIS:  What does "withstand the burn" mean?
19              MR. CHRISTIE:  No releases.
20              DR. WALLIS:  No leakage.
21              MR. CHRISTIE:  Yeah.
22              DR. WALLIS:  Not a probability of 10 percent.
23              MR. CHRISTIE:  No, not 10 percent.
24              For the large drives, we looked at can the large
25    drives containment for the sequences that have a fairly
.                                                               104
 1    decent probability of causing core damage -- can they
 2    withstand it, and we looked at it in a sense --
 3              DR. WALLIS:  No failure of containment.
 4              MR. CHRISTIE:  Okay.  We looked at it in the same
 5    sense that we looked at the Three Mile Island Unit 2
 6    accident.
 7              We had containment failures at Three Mile Island
 8    basically because we pumped water out of the sump back into
 9    the aux building and so on and so forth, but the containment
10    withstood the burn.
11              It did not leak.
12              The burn occurred.  It had a peak of about 28
13    gauge.  The design was about 45 to 50.  The ultimate is
14    probably anywhere between 130 to 150.  It withstood the burn
15    in the sense there's no leakage, and that's what we meant
16    when we did that.
17              DR. WALLIS:  So, yours is essentially
18    deterministic.  You're saying it won't fail.  Your
19    calculations indicate it won't fail.
20              MR. CHRISTIE:  When you look at the calculations
21    that were done for IDCOR, no containment can be said to not
22    fail.
23              It has a probability of failure no matter what you
24    do, okay?
25              What we said was we believe, when we did all the
.                                                               105
 1    IDCOR analysis, that the probability of failures for the
 2    hydrogen burns that would come from the sequences that had
 3    some probability of occurring, you know, high-probability
 4    sequences -- we can withstand it, and some of the people
 5    went through the -- you know, uncertainty bands -- we went
 6    through uncertainty bands.  We went through the 95-percent
 7    calculations.
 8              We did things like -- they hydrogen burn at Three
 9    Mile Island was probably somewhere in the neighborhood of 45
10    percent, 50 percent, metal-water reaction.  We looked at
11    analysis for 75.
12              DR. WALLIS:  All I want is -- it's a one-line
13    answer.
14              What do you mean by withstand the hydrogen burn?
15              MR. CHRISTIE:  We do not believe the large dry
16    containments will have containment failures that will have a
17    significant impact on the public health risk during the
18    burns from core damage events.
19              It doesn't fail.
20              DR. WALLIS:  Does not fail.
21              MR. CHRISTIE:  We can't say it doesn't fail 100
22    percent of the time.
23              What we've said is we have uncertainty bands on
24    the failures, but we are pretty confident of the large
25    drives, and the Nuclear Regulatory Commission people put a
.                                                               106
 1    lot of effort into duplicating the IDCOR work.
 2              They looked at it from the standpoint of
 3    back-fitting requirements for igniters, and they also agreed
 4    the large drives don't fail during hydrogen burns.
 5              So, we don't have a requirement.
 6              DR. WALLIS:  I just don't think I've got the
 7    answer I want, and I don't think I will get it, but I don't
 8    want to pursue it anymore.
 9              MR. CHRISTIE:  You would have to look at the IDCOR
10    analysis to do that.
11              DR. WALLIS:  I think there should be a one-line
12    answer to these questions, not a lot of equivocation.
13              MR. CHRISTIE:  I was present during a lot of that
14    IDCOR work.  I was present during a lot of the NRC work.  I
15    don't think there's a one-line answer.  There's people at
16    this time that also were there.
17              Okay.
18              So, as far as the agreement and disagreement with
19    what the staff thinks is going to happen in their option 3
20    and what we have in the petition for rulemaking, that's
21    neither here nor there, but I think -- well, okay.
22              Let me say, in summary, we can't -- we have known
23    for a year -- you're talking about the public interest and
24    who's worried about the public and how do we enhance safety
25    and how do we, you know, do this balancing act between the
.                                                               107
 1    elimination of the requirements and the cost-benefits and
 2    all the rest of it.
 3              We've known for a year, since San Onofre safety
 4    evaluation report was put out, that the existing hydrogen
 5    control requirements are detrimental -- they do not enhance
 6    safety.
 7              There are many things in those regulations which
 8    we have, you know, submitted to the Nuclear Regulatory
 9    Commission.  They agree with us.  They do not enhance
10    safety.
11              Safety would be enhanced by the removal of these,
12    okay?
13              That's the risk significance of the petition for
14    rulemaking that we did.
15              We wanted to enhance safety by elimination of
16    requirements.
17              We also wanted to enhance safety by additional
18    requirements along the rules of adequate protection in the
19    back-fit rule, and we did that.
20              For one year, we have had existing nuclear power
21    plants in the United States that are not as good as they
22    could have been if that petition for rulemaking had been
23    approved.
24              We're now going into, I guess -- and I haven't
25    seen the SECY -- an option 3 which is a voluntary program
.                                                               108
 1    for plants that want to get into this to improve it.
 2              What happens to the rest of them who had the
 3    petition for rulemaking under the old regime, and where do
 4    they stand?
 5              We wanted to enhance safety.  We presented the
 6    documentation.  We went through all the task zeros for
 7    Arkansas, San Onofre.  We put the petition for rulemaking
 8    in.  We thought we had played the game according to the
 9    rules, and nothing's happening.
10              Now, we're having to go back and submit exemption
11    requests again under 50.12.
12              It makes no sense to us.
13              I would have to say, beyond all shadow of a doubt,
14    the interaction we've had with the staff on 10 CFR 50.44 has
15    just flat increased the cynicism of the people at the plants
16    to the nth order.
17              They don't believe it anymore.
18              They hear words, "enhance safety," and all the
19    other things that people talk about.
20              When they had a concrete effort, devoted a lot of
21    resources to it, put a good faith effort to it, paid
22    attention to all the rules and regulations as they
23    understood it, and nothing has been done.
24              One plant in the United States is an exemption to
25    the requirements of 50.44.
.                                                               109
 1              Why not every plant?
 2              Why are we sitting here today with something we
 3    know the answer to -- we know the problem, we know the
 4    answer, and it doesn't happen, and I have no message to tell
 5    the people at the plant when they say why isn't the petition
 6    for rulemaking done and why do we have to go about
 7    submitting an exemption request?
 8              I have no answer.
 9              If you have an answer, I would certainly
10    appreciate it.
11              Thank you.
12              DR. POWERS:  Do you have any concluding remarks,
13    Mr. Shack?
14              DR. SEALE:  No, I think we're done.
15              DR. POWERS:  Okay.
16              I am going to recess us for -- till 10 after the
17    hour.
18              I have adjusted the schedule so we will be late
19    for lunch and the starting of the last presentation, but
20    otherwise, we're going to go through this morning's agenda. 
21    But we've just shifted it by roughly 45 minutes.
22              So, till 10 after.
23              [Recess.]
24              DR. POWERS:  Come back into session, and I'll turn
25    to Professor Seale, and he will discuss the causes and
.                                                               110
 1    significance of design basis issues with us.
 2              DR. SEALE:  Well, I would remind the members of
 3    the committee that, back when the Commission reorganized and
 4    compressed its organization somewhat, the -- one of the
 5    major results of that was the folding of the
 6    responsibilities of the AEOD into, in part, NRR and also
 7    with the balance to the research organizations.
 8              And at the time, many members of this committee
 9    expressed some concern for the loss of the independence that
10    was inherent in the former organizational structure and were
11    concerned somewhat for the future of the kinds of helpful
12    and incisive observations of the experience base that they
13    had been providing over the years to the Commission, and I
14    think most of us would agree, for the information that the
15    ACRS based many of its comments on.
16              Well, today, we're going to hear about an activity
17    that was begun back in those days, and as we do so, I want
18    to ask my colleagues to think carefully about the results
19    that are being performed, assess as best you can the extent
20    to which the chips are falling where they may, and also, and
21    ultimately, whether or not we're really getting the kind of
22    information out of this assessment of experience-based
23    results that can be useful to us as we go forward.
24              And I think this is particularly important at this
25    time, when we're in this transition toward risk-informed
.                                                               111
 1    regulation, that we keep our eye on what the -- what
 2    experience is perhaps telling us the real currency of risk
 3    is, what is it we're really concerned with, at least to this
 4    point.
 5              In view of the hour and so on, I won't try to go
 6    into a lot more detail.  I think the have a fairly complete
 7    presentation here, but it's whether it's shades of the ghost
 8    of Marley or Ed Jordan or who, we're going to hear about
 9    this one, okay?
10              Gentlemen.
11              MR. LLOYD:  Thank you very much.
12              I would say thank you.  I think this is a good
13    opportunity to explain all this stuff, and being a kinder
14    and gentler committee out there, as I've seen from this
15    morning's activities, I'm sure that we'll be able to make up
16    a lot of time and get everybody out to lunch on schedule.
17              DR. POWERS:  You don't need to worry about the
18    schedule.  I made all the adjustments, and members need not
19    withhold any of their burning questions and in-depth
20    understanding here.
21              MR. LLOYD:  Thank you.
22              As was mentioned, this study actually began in
23    early 1997.
24              It was at the request of our then-EDO, Ed Jordan. 
25    Ed Jordan was there, and also Joe Cowan.  This was a time
.                                                               112
 1    period when everybody was concerned about design basis
 2    issues.  Millstone was going on.  Maine Yankee was another. 
 3    Crystal River was another, and so on.  And so, there was a
 4    time period, I think, when the agency was interested in what
 5    the extent of design basis issues really meant, you know,
 6    should we be worried about it, what is the risk significance
 7    and so on, and so, we started out by making monthly reports
 8    on -- 50.72 reports, as we got those.
 9              As the time lag took care of itself, we got into
10    looking at 50.73, or LERs.  There's only about a 90-day time
11    period between the time of issuance to the time that it
12    actually gets logged in through Oak Ridge and gets
13    evaluated, and so, there was that time space.
14              We had several of the old reactor analysis branch
15    in AEOD that would go through and review these LERs.
16              We set up a database to track all the various
17    kinds of pertinent facts, the type of the vendor, the age of
18    the vendor, how long the plant has been operating, what the
19    power levels were, what initiated the design basis issue to
20    be documented in the first place, what the AE background
21    was, what systems were affected by this design basis
22    problem, and there were several other things that we snuck
23    into that very specific AEOD database.
24              We also used the -- Oak Ridge's sequence coding
25    database, SCSS, and inputs from the region and NRR.  There
.                                                               113
 1    were several other sources that were utilized to come up
 2    with the study.
 3              As time closed on '97 and we actually started
 4    doing things, data reduction, in early -- about mid-1998,
 5    and then things were added at the request of the regions or
 6    NRR to the report, and it kind of moved around in that
 7    scope, and eventually, it turned out the way it is as you've
 8    seen it.
 9              We went out for peer review on the report in May
10    of this year, 2000, and we hope to get a finalized version
11    of it by December of this year.
12              Next slide.
13              We looked at reporting trends from 1985 through
14    1997.
15              If you look at the total, there were approximately
16    3,100 design basis issues, or as we call them, DBIs, over
17    that 13-year period.
18              If you look at the trends, there was sort of a
19    general increase in the number of reported DBIs.  It was
20    kind of based on the focus that the NRC had at the time in
21    the way of inspections or enforcement actions or generic
22    communications.
23              If you look specifically at 1997, there were
24    approximately 500 LERs that had design basis issues in
25    those.  The total number of LERs that were produced at that
.                                                               114
 1    time for 1997 was over 1,900.
 2              We've tried to look at what the risk might be, and
 3    we tried different ways to evaluate risk of design basis
 4    issues, and one of those was using the ASP program.
 5              If you look at ASP trends that actually affected
 6    design, it has varied over the last several years from as
 7    high as 8 percent of the design basis issues that were
 8    reported that were -- ended up meeting the threshold of ASP,
 9    which would be 10 to the minus 6, conditional core damage
10    probability.
11              In 1997, the number of DBIs that met that ASP
12    threshold was less than 1 percent.  So, there's been a
13    steady decrease in the risk significance based on the ASP
14    information that we have.
15              As far as reporting, number 5 at the bottom,
16    approximately 80 percent of the DBIs were reported by
17    licensees as un-analyzed conditions, and I think you will
18    hear probably more about that.
19              I think you've also heard some in the previous
20    topic discussion, also, about, you know, how you might look
21    at risk significance of these sorts of issues.
22              The next slide shows the long-term reporting trend
23    for DBIs.
24              As you can see here, going back to 1985, we had
25    just a little over 150.
.                                                               115
 1              We had kind of a slow increase in that period,
 2    between there and '89, dropped off again by virtue of some
 3    focus, Dr. Murley looking at how we should view design basis
 4    issues, and then we had quite a large pick-up in '96 and
 5    '97, and as I mentioned earlier, I believe that the main
 6    increase in '96 and '97 were the result of the Millstone
 7    inspections, Crystal River.
 8              There was a 50.54(f) letter that went out in '96
 9    requesting licensees to come forward with an design basis
10    problems that they might have with their programs and
11    whether they thought it was adequate or not and what they
12    should do about it.
13              There were also some generic communications that
14    came out of these same kinds of looks that also tended to
15    add to the number of design basis issues that were actually
16    reported.
17              The blackened area on the top of each one of those
18    graph points would be the contribution from the design basis
19    issues that actually met the ASP threshold.
20              So, as you can see, there's a small percentage of
21    DBIs that actually get issued that actually meet the ASP
22    threshold.
23              It had a high in the '90-'91 period, as you can
24    see there, of about 8 percent and dropped off to what we
25    have now in '97, which is less than 1 percent met the ASP
.                                                               116
 1    thresholds.
 2              There were reasons for each of these.
 3              If you look at the period '86 to '89, there were a
 4    number of SSFIs done which had a significant design input in
 5    those inspections.
 6              We had -- through the '90 to '93 time period,
 7    there were the SVs that went out.
 8              Through the '93 to '95 time period, we had the
 9    service water inspections, the SWOPEs, that added a lot, and
10    then, of course, in the '96-'97 time period, we've got those
11    plants that were a significant focus in the design area by
12    the NRC.
13              DR. POWERS:  Roughly that time period, they were
14    doing the functional fire inspection pilot program.
15              Were you getting design basis issues coming out of
16    that exercise?
17              MR. LLOYD:  We got some, and it was interesting. 
18    If we went back and we looked at the databases for the SVs
19    and the SWOPEs and others, and then if you look at what was
20    actually produced in LERs or actually documented, in a lot
21    of cases, if it got documented in an inspection report some
22    place, it didn't necessarily get documented in an LER.  So,
23    you can't really find a one-to-one correlation between the
24    inspection findings and some of the issues that actually get
25    reported in LERs.
.                                                               117
 1              DR. POWERS:  What I was thinking of is, because
 2    the functional fire inspection was just a pilot program,
 3    only did four plants, you might have to do an extrapolation
 4    in order to estimate what the whole population would be.
 5              MR. LLOYD:  Right.
 6              DR. POWERS:  I wonder if you thought any about
 7    that.
 8              MR. LLOYD:  We didn't do that.
 9              Later on, in some additional slides, we actually
10    took the Appendix R fire issues and also the seismic issues
11    and removed them from our risk-sorting process.
12              One of those reasons was because of what you said.
13              Another reason was because I'm not sure if we've
14    really decided what the risk significance is for some of the
15    postulated fires and also what the risk might be from the
16    seismic events.
17              So, you get quite a difference in opinion as to
18    where that risk really is.
19              DR. POWERS:  You're saying that we don't have is
20    good risk assessment tools for fire.
21              MR. LLOYD:  Exactly.
22              DR. POWERS:  That's probably a familiar song this
23    committee has heard.
24              MR. LLOYD:  Yeah.
25              DR. POWERS:  Once or twice maybe.
.                                                               118
 1              DR. APOSTOLAKIS:  One of the criticisms that the
 2    recent UCS report on PRA has raised is that what the PRA
 3    models is not necessarily what's in the plant.
 4              Now, I get the impression from this presentation
 5    that people find things, you know, design basis issues and
 6    so on, and then there is an assessment or evaluation after
 7    the fact as to how significant that finding was.
 8              Were there any of these found when the facility
 9    was doing a PRA?  In other words, they looked because they
10    were about to do the PRA?  Or is the PRA done on the basis
11    of the paper?
12              MR. LLOYD:  I don't recall very many issues that
13    came out while they were doing the PRA.
14              There were a number of issues that actually got
15    reported as part of some of their design basis
16    reconstitution programs that they were either working on --
17    and of course, those varied a lot from just go find the
18    information to actually try to validate that the information
19    is correct.
20              So, there's a wide difference on what licensees
21    actually did in the way of restitution or reconstitution of
22    their design basis issue, but a lot of those issues came out
23    of those kinds of things.
24              A lot of issues came out of generic
25    communications, where we would send a communication out and
.                                                               119
 1    they would take a look to see if they had any problems, and
 2    where they actually gave credit back to the NRC that said,
 3    you know, while reviewing generic communication, you know, a
 4    generic letter, a bulletin, whatever, you know, we found
 5    this problem and now we're reporting it.
 6              That got reported in our database, also.  So, we
 7    have those kinds of things.
 8              And then there were the inspection issues that
 9    came out that many times the LERs would give credit to the
10    NRC inspection that raised this issue and then they reported
11    it.
12              DR. BONACA:  But I think, at least from my
13    experience from the mid-'80s, when we performed PRAs of some
14    of the northeast plants, not enough credit was given to PRA
15    in the sense that we raised an issue, electrical engineering
16    said, oh, the plant is not configured this way, that way,
17    and we said oh, so we changed it, we report it, but it was
18    reported as -- not necessarily as, you know, we were
19    verifying the PRA.
20              It was reported as electrical engineering found an
21    inconsistency or whatever.
22              So, I don't think PRAs were given, at least from
23    my experience, enough credit for the findings.
24              There were a lot of those findings that came from
25    the modeling effort.
.                                                               120
 1              MR. LLOYD:  Right.
 2              DR. POWERS:  I think there's a more seminal issue
 3    here.
 4              I may be stealing a little bit of the thunder from
 5    later in your presentation, and I apologize if I am, because
 6    I think it's an important thing.
 7              We do see this criticism coming down, especially
 8    in Europe, on PRA that says, gee, the plants don't model
 9    design errors, and clearly, they don't, because you don't
10    know about them, or you would, and it seems to me what
11    you're getting here -- you collected a database that said,
12    yeah, verily, there are a lot of design errors showing up in
13    these things and their risk significance is getting smaller,
14    and that means we're finding important ones, the ones that
15    are coming up now become less important, and I think, by
16    implication, says the fact that the PRA doesn't have this in
17    it is becoming less and less of an issue all the time.
18              If I was going to say what was the big bottom line
19    for me in the report, it was that.
20              MR. LLOYD:  Yeah.  I think that's probably a true
21    statement.
22              If you go farther back in time, when there were a
23    lot more latent design basis issues out there that licensees
24    just didn't know about -- so, in the 1980s, for example, you
25    know, there were probably thousands of things, you know,
.                                                               121
 1    spread out over the 100-and-some plants that were out there
 2    at that time, that they didn't know they existed, and you
 3    know, they thought their models were good, and their models
 4    were probably pretty good, but they didn't know that the
 5    plant didn't reflect the actual design.
 6              DR. BONACA:  I would like to add that, in large
 7    part, also, is actually shows, in my sense, the strength of
 8    the PRA, of the technology in some or many of these issues
 9    which were identified as design basis issues, were not
10    design basis -- were not significant from a PRA standpoint.
11              For example, we found in the mid-'90s that a
12    number of plants had inadequate PSH in the circulation
13    systems, and what that meant was that, at the limit of the
14    assumptions for the recirculation, which means you have a
15    de-pressurized containment, which you are not likely to find
16    in many sequences, you know, under the most extreme
17    conditions, you may have, in fact, some cavitation of those
18    pumps.
19              The licensing basis assumes that you have a failed
20    system, because you have that happening.  You defy your
21    design basis.
22              The PRA describes accurately the process of
23    performance of the recirculation system under all conditions
24    in a spectrum of LOCA.
25              Therefore, the PRA provides a much better
.                                                               122
 1    representation of the issue just for the modeling that it
 2    provides.
 3              The statement of not meeting the design basis is a
 4    very narrow representation of the actual fault found, which
 5    is under the extreme condition may not work.
 6              MR. LLOYD:  Right.
 7              DR. BONACA:  Okay.
 8              So, you know, to me, one could argue that that's
 9    really the strength of the PRA with respect to deterministic
10    determinations that allows it to give that kind of
11    representation.
12              Now, there may be cases where you have an actual
13    missing of the design commitment, and then that's a
14    misrepresentation in the PRA.  I haven't seen many of those,
15    if ever.
16              MR. LLOYD:  The next couple of slides, maybe some
17    of these things will come out, also.  What we've got here on
18    slide number four, we went through and tried to mix the
19    deterministic side with the risk side, and we came up with
20    four different wickets that we went through and we did sorts
21    on each of the design basis issues.
22              We also presumed that each one of these would sort
23    of be in a hierarchical order.  So if you look at the first
24    category, we looked at the risk category and we determined
25    that we had three slots that we could stick a DBI in.  One
.                                                               123
 1    was potential, minimum and none.
 2              Potential, in this respect, means that it would
 3    meet the risk information matrix which was generated by
 4    Brookhaven National Lab as being something that was
 5    potentially risk-significant.  Minimal meant that it was a
 6    safety-related system, but necessarily didn't perform a
 7    function that was rated highly as far as risk space goes. 
 8    And none was generally reserved for programmatic issues,
 9    administrative issues, where a piece of paper was incomplete
10    and they just found the paper or they did an analysis and
11    there was never any problem.
12              So we would go through those three wickets there.
13              The next one that we went through was did you
14    actually have a safety demand and either a yes or a no. 
15    Then you would go into a different cut-set.
16              You would look at effect type.  Actual event was
17    something where a component or system did not work or did
18    not work to design expectations.  Potentially, that was a
19    set of conditions or postulated things.  So in this context,
20    nothing really did happen.
21              It was just some engineers sitting around saying,
22    well, okay, if we have this and we have that, well, then,
23    this system will not meet its design basis.  So that would
24    be the effect type.
25              The effect extent is similar to what you mentioned
.                                                               124
 1    earlier here.  We've got three categories there.  You either
 2    had a failed system, which means the system would not work
 3    at all, or you had a degraded system, where the system
 4    worked, but it didn't meet 100 percent of its design basis
 5    criteria.  Then the third and lowest in this grouping was
 6    that you either had a degraded or a failed train, that you
 7    had an additional train that would pick up whatever
 8    requirements you had to mitigate an accident.
 9              Degraded would be the same thing, that you had a
10    train that you actually turned it on and it didn't exactly
11    do everything it was supposed to in accordance with its
12    design requirements.
13              The next slide shows --
14              DR. APOSTOLAKIS:  Help me understand something. 
15    The accident sequence precursor program would pick up some
16    of these and do an analysis.
17              MR. LLOYD:  Right.
18              DR. APOSTOLAKIS:  So when you talk about DBI risk
19    category, you include the ASP?
20              MR. LLOYD:  Right.  Any event that met the
21    threshold of ASP, which would be ten-to-the-minus-six
22    conditional core damage probability, we also had another
23    slide in the report, I believe, that shows where those
24    actually showed up, and every one of those ended up in what
25    we call the group one section, which is on the next slide.
.                                                               125
 1              DR. APOSTOLAKIS:  But what is the different
 2    between potential risk category and ASP?
 3              MR. LLOYD:  If you were in a -- you would end up
 4    being in the same place.  If it were an ASP event that was
 5    design basis related and through the analysis it said, yeah,
 6    this meets the ASP threshold, it would also be a potential
 7    event.
 8              DR. APOSTOLAKIS:  But would the potential event be
 9    ASP, an ASP event?
10              MR. LLOYD:  It could be.
11              DR. SEALE:  It should be, shouldn't it?
12              DR. APOSTOLAKIS:  Should be or could be?
13              MR. LLOYD:  It could be.
14              DR. APOSTOLAKIS:  It could be.
15              MR. LLOYD:  Yes.
16              DR. SEALE:  So all of the ASPs are the caps on
17    your previous bars, but all of the potentials are not in the
18    caps.
19              MR. LLOYD:  Exactly.
20              DR. APOSTOLAKIS:  Have we ever found a DBI that
21    led to a significant change in the CDF or LERF of a
22    particular plant?
23              MR. LLOYD:  None of these have changed a lot, but
24    there's a couple more slides back that actually have those
25    values on it.  The largest one, I think, was a
.                                                               126
 1    ten-to-the-minus-four.  Most of those were smaller than
 2    that.  So there's not that big of an impact.
 3              DR. APOSTOLAKIS:  So we'll come back to this
 4    later?
 5              MR. LLOYD:  Yes.
 6              DR. APOSTOLAKIS:  Okay.
 7              MR. LLOYD:  The next slide, number five, shows the
 8    complete set of sequences that you would end up with after
 9    you go through each of those four different wickets.  So
10    you've got 19 possible end states.
11              The group one, as you can see from the upper
12    left-hand corner, up here, this would be group one and then
13    you had a group two, group two was anything that was either
14    minimal or no risk significance at all.  Group one would
15    include those DBIs that had some potential to impact the
16    plant.
17              In 1997, there were 512 DBIs, 102 of those were
18    either fire or seismic.  So we limited those.  So you end up
19    with 410 left over for 1997.  Out of that, in this category
20    two, there ended up being 13 DBIs.  In the category three,
21    there ended up being 82 DBIs.
22              The bulk of the DBIs fell within the group two. 
23    The largest was in category six, with 204; five, at 73; and
24    down at seven, which was no impact at all, there were 38 in
25    that group.
.                                                               127
 1              If you can kind of follow across, you can see what
 2    the chart does.  The top part of the chart is basically
 3    identical to the bottom chart.
 4              If you look at category 1A, for example, that
 5    would be a potential, which means it would be risk
 6    significant.  It was on the rim.  You had a safety demand,
 7    so you had a yes.  It was an actual failure, which means
 8    that a component or system did not work when it was called
 9    upon, and you actually had a system failure here.  So that
10    would be a 1A category.
11              In all the ones that were reported during 1997,
12    there were no category one kinds of DBIs, because there was
13    no safety demand.
14              DR. APOSTOLAKIS:  When you say actual failure,
15    what does that mean?  It's a failure that's due to some
16    design deficiency, right?
17              MR. LLOYD:  Yes.  It would be a failure of a
18    system or component to actually work.  So it actually was
19    turned on or it had to work.  If it was instrumentation, the
20    instrumentation failed to work when it was supposed to work,
21    that would be an actual failure.
22              DR. APOSTOLAKIS:  Right.  But you --
23              MR. LLOYD:  Potential failure would mean that
24    given certain postulated conditions, something might not
25    work.  But you never had an event where it didn't work.  It
.                                                               128
 1    was just postulated that it might not work.
 2              DR. APOSTOLAKIS:  But I thought we were looking --
 3    maybe I misunderstood -- we were looking at design basis
 4    issues.  What does that mean?  You can have random failures
 5    of components.  Is that the design basis issue?
 6              So how do you decide that an actual failure is not
 7    a random failure?
 8              MR. LLOYD:  What we're looking at here is the
 9    design.  First of all, you had to go through the wicket
10    that, yeah, it affected the design of the plant and there
11    were a bunch of events that got reported that we eliminated
12    because it didn't affect the design of the plant, even
13    though there was a failure.
14              Testing, for example, there were a whole lot of
15    testing issues.
16              DR. WALLIS:  You said define -- it seems backwards
17    to me.  It doesn't affect the design of the plant.  It's the
18    design of the plant that affects the performance.  You're
19    implying that it was the design of the plant.
20              MR. LLOYD:  It had to effect the design of the
21    plant.  So there had to be some problem with the design of
22    the plant, where then you had a --
23              DR. WALLIS:  But this is a bifurcation.  You're
24    implying something.
25              MR. LLOYD:  The first wicket you had to go through
.                                                               129
 1    that you had to actually have a design problem and then that
 2    problem was created by various kinds of mechanisms.  It
 3    could be that the pump was supposed to turn out 10,000 gpm,
 4    but it only turned out 8,000 gpm.
 5              DR. WALLIS:  That could be because the
 6    manufacturer made a lousy pump.  That's not a design
 7    problem.
 8              DR. SEALE:  Yes, but you picked it to do 10,000.
 9              MR. LLOYD:  There was a design requirement that
10    said it had to be 10,000 and all the analyses were based on
11    the fact that you could get 10,000 gpm out of that pump.  If
12    they went down and actually had an event where they ran the
13    pump and they discovered that they only got 8,000 gpm out of
14    it, the pump still worked, it didn't fail.  So you would be
15    in a degraded situation that affected the design, because
16    that pump did not meet the design requirement.
17              DR. WALLIS:  That could be because something was
18    worn.  It could have been okay at the beginning.
19              MR. LLOYD:  There could have been all kinds of
20    reasons, but it failed to meet the design requirement.
21              MR. SIEBER:  But the only place where you would
22    care and categorize them is if there was actually a design
23    error that said I applied the wrong pump to meet the
24    conditions of the system demand as opposed to a pump
25    degrading over time as --
.                                                               130
 1              DR. SHACK:  Maintenance problem.
 2              DR. SEALE:  Maintenance or inspection.
 3              MR. SIEBER:  That could be reported as an LER, but
 4    it wouldn't be classified as a design basis issue.
 5              DR. APOSTOLAKIS:  Is that what you did?
 6              MR. LLOYD:  We did what you're talking about here. 
 7    If there was a design requirement, using the pump issue, if
 8    it was supposed to be 10,000 gpm and they actually went down
 9    there and they ran the thing and under certain situations,
10    it only turned out 8,000 gpm.
11              First of all, it didn't meet the design
12    requirement.  So there was a design problem.  So it fell
13    short of whatever the analysis was for that particular pump.
14              DR. APOSTOLAKIS:  Regardless of the cause.
15              MR. LLOYD:  Right.  If it didn't work, a lot of
16    times, the licensees would go through and sharpen their
17    pencils and say, yeah, it turns out less than the design
18    requirement, but we do analysis here and I think we're okay.
19              DR. BONACA:  What if they went back and said,
20    okay, it delivered 10,000 when we bought it, has been
21    degrading beyond the degradation limit, and, therefore, it's
22    a wear issue.  Now, that would still be considered design?
23              MR. LLOYD:  It could be a wear issue.  It could be
24    --
25              DR. BONACA:  Assume that it was determined to be a
.                                                               131
 1    wear issue.  Assume that.
 2              DR. APOSTOLAKIS:  It's still a design basis issue.
 3              DR. BONACA:  It would be still a design basis
 4    issue.
 5              MR. LLOYD:  It's still a design basis issue,
 6    because they don't meet the design basis requirement.  But
 7    it could be -- to answer part of your other question, it
 8    could be a wear issue, it could be a system alignment
 9    problem where alignments changed, and, at one time, with a
10    certain kind of alignment, with different sorts of valves
11    opened or closed, they may have been able to get 10,000 gpm
12    out of that thing.
13              But as changes were made here or there or maybe
14    system alignments, they only got 8,000 gpm.
15              DR. BONACA:  But the point that Jack is making,
16    which is a good point, is that it will not be reported in
17    the LER as a design issue if it was a question of
18    maintenance, for instance.
19              MR. SIEBER:  Well, everything in the plant
20    degrades.
21              DR. BONACA:  That's right.
22              MR. SIEBER:  With time, valves begin to leak,
23    pumps don't pump as much as they used to.  So to me, all
24    those things should be maintenance issues.
25              DR. BONACA:  Well, at least it would be important
.                                                               132
 1    that way.  So if you read the LER, you may miss the DBI
 2    issue, if there was one.
 3              MR. SIEBER:  The more important one is the place
 4    where the designer misapplied a certain component.
 5              MR. LLOYD:  Right, if I got the wrong pump
 6    installed.
 7              DR. APOSTOLAKIS:  I thought we were looking at
 8    those, but now I think you are saying anything that does not
 9    perform as expected --
10              MR. LLOYD:  As designed.
11              DR. APOSTOLAKIS:  -- is under this.
12              MR. LLOYD:  Right.  And this would be part of the
13    burden reduction, I think, that everybody is trying to
14    figure out and as far as reporting requirements go.  A lot
15    of the things that are reported here, if you go and
16    wordsmith the thing and make some changes, would put the
17    licensee, if it was just strictly an issue where they didn't
18    meet the design because of some other sets of causes and if
19    that cause was maintenance or something else, well, then you
20    could not report this issue.
21              There are lots and lots of things that got
22    reported that really kind of spun up the licensees, I think,
23    to report a lot of things that were really of no
24    significance or consequence at all.
25              But by virtue of the reporting system that we've
.                                                               133
 1    got, if they had a pump that said here is my design
 2    requirement of 10,000, it turns out 8,000, it doesn't meet
 3    the design requirement, so the licensee has to fill out an
 4    LER that says, hey, I've got a pump here that doesn't meet
 5    its design basis, it's only turning out 8,000 gpm.
 6              So I think there's a lot of places where things
 7    could be improved and the reaction of the licensees could be
 8    made by just changing some of the definitions of what should
 9    be reported or what should not be reported.
10              DR. WALLIS:  The remarkable thing to me is that
11    these keep being discovered, and in '97, at a very great
12    rate.  This is a long time for this design error to lie
13    latent, undiscovered.
14              MR. LLOYD:  Right, and never find it.  That's
15    disturbed quite a few people and like I said, at the very
16    beginning, you've got the deterministic people on one side
17    that say, hey, we've got all these design basis requirements
18    and we've got defense-in-depth and I think that's working
19    for us, and you've got the risk people over on the other
20    side that says, well, so what if it works, it's of no
21    consequence in risk space.
22              It's very difficult to get those two groups
23    together and compromise.
24              DR. WALLIS:  That should be like the example we
25    got from an unknown -- I won't mention the name -- a cable
.                                                               134
 1    which had not been connected for ten years and just suddenly
 2    was -- that's typical design error.
 3              MR. SIEBER:  That's a construction error.
 4              DR. WALLIS:  But that would fit into your category
 5    of design.
 6              MR. SIEBER:  We better try to move along, if we
 7    can.
 8              MR. LLOYD:  Next slide.  We've got various
 9    observations.  As I mentioned, these are all based on LER
10    reviews, Oak Ridge databases, the AEOD database, the ASP
11    database, the Reactor Program System database in NRR, which
12    has inspection effort and other kinds of things in it, and,
13    also, region input.
14              If we go on to the next one.  We've got the
15    causes, was one of the things that we looked at, and here we
16    have approximately 72 percent show up as original design
17    error, which has been Dr. Wallis' comment.
18              A lot of these things have existed for 20 or 30
19    years and went through this entire time period and were not
20    discovered.
21              There may be more than one cause that gets
22    documented by the licensees and also Oak Ridge when they
23    document all these things. And this is why the percentages
24    don't add up to 100.
25              The next one is procedure deficiency,
.                                                               135
 1    approximately 28 percent of the DBIs attributed procedure
 2    problems with how they got themselves in a condition that
 3    would be outside of their design basis, and then human
 4    error, just bad things happen and that's what the licensee
 5    came up with.
 6              DR. WALLIS:  It's really all human error.
 7              MR. LLOYD:  A lot of that is all human error.
 8              DR. WALLIS:  Even the design error is human error.
 9              MR. LLOYD:  Right.  The design error, the designer
10    made an initial error.
11              DR. APOSTOLAKIS:  This 72 percent of original
12    design error, say some of them were there for 10-20 years, I
13    mean, why is that?  How can we believe the PRAs if we find
14    things like that?  What do we learn from this?
15              MR. LLOYD:  That certainly comes up by the
16    opposition that would say that we had all these design
17    errors, they have existed for years.  We've had testing
18    programs to go out and test systems and components to make
19    sure they're in compliance with the design, and then somehow
20    we miss them.
21              DR. BONACA:  But the fundamental issue is what we
22    saw before in the chart, that very, very few were
23    significant.  Why?  Because most of them were, again, you
24    have MPSH that would work for most scenarios, except the
25    extreme limit, or you had, for example, screens for the sump
.                                                               136
 1    systems that had developed some opening somewhere, where you
 2    could possibly entrain some debris.
 3              So you had the situation where most of the cases
 4    you had degraded components or functionality, but you had
 5    functionality, which you were missing.  It was the pedigree
 6    portion of compliance that gives you -- which is required by
 7    law.
 8              So you had cases where you find piping that wasn't
 9    fully qualified to the temperature for the circulation
10    system.  The result of that was that several of these
11    reports, but the system would not be non-functional.  It
12    would function as required; however, did not meet the
13    pedigree.
14              So most of these issues, that's why they have the
15    differentiation, large number or very few had safety
16    significance.
17              IN the modeling of the functionality, the PRA was
18    correct and very few of those had an impact on the PRA.
19              MR. LLOYD:  You could look at why these issues
20    weren't discovered before and I think there's two or three
21    things that you can point to.  One is the adequacy of
22    licensees' testing programs.  A lot of the tech spec testing
23    requirements, if you go through them and really looked at
24    them, they may have been testing systems for years and the
25    nature of the test was such that you would not have found
.                                                               137
 1    the problem.
 2              Like logic system functional testing, for example. 
 3    I was on an inspection down at Cooper and they had
 4    discovered there were over 700 different tests that they had
 5    were inadequate and would not have caught whether or not
 6    things would have worked or not worked.
 7              So a lot of that is the adequacy of the test
 8    program.  Some of it is just people missing things, not
 9    testing the things they should test, and just nothing really
10    bad happened.  And as we're seeing, the end result here is
11    that very few of these DBIs have a lot impact in risk space.
12              So we looked out there, too.
13              MR. SIEBER:  I think another way to look at it is
14    you don't find most of these design basis issues unless you
15    actually look for them and that's where the SSFIs and the
16    SWOOPIES and so forth would do those.
17              You identify a lot of issues that will never turn
18    up in an acceptance test or a surveillance test or
19    post-maintenance test. Surveillance tests are designed to
20    make sure that you meet the tech spec.  They do not test
21    every aspect of the design.
22              MR. LLOYD:  Exactly.
23              MR. SIEBER:  So the testing programs can't be
24    relied on as the ultimate mechanism for identifying all
25    these design issues.
.                                                               138
 1              DR. BONACA:  Actually, the point you made about
 2    the SSFI program was extremely effective.  That's why you
 3    see the decrease in the significant DBIs through the years,
 4    although you increased the inspection so much in '97, you
 5    found a lesser number of -- and that was because of the
 6    SSFIs and the SWOOPIES, which were very effective.
 7              MR. LLOYD:  Right.  They found a bunch of problems
 8    initially and a lot of the big nuggets have already been
 9    discovered.
10              DR. APOSTOLAKIS:  In PRA space, it seems to me
11    there is a problem with the Bayesian updating of the failure
12    rates, because what people do is they start with a fairly
13    broad generic distribution and then they use test results,
14    specialized to update the distribution.
15              And it's a property of Bayes' theorem that you
16    don't need very many of those to end up with a very narrow
17    distribution, and I think what you're saying is that this is
18    not the right thing to do, because in cases where the test
19    does not -- is not a complete test.
20              MR. LLOYD:  It's not a complete test.
21              DR. APOSTOLAKIS:  So the high tail of the
22    distribution should not be moved or lowered, but it should
23    survive, which comes all the way back to the original
24    reactor safety study model, which I think was not quite
25    correct, saying that we will have broad distributions
.                                                               139
 1    because we want to cover all accident conditions.
 2              There should be actually two distributions, one
 3    for the severe accidents, which you may not be able to get
 4    tests for, and then the other one, the true Bayesian
 5    updating becomes very narrow.
 6              And I think that's what you're telling us here.
 7              MR. LLOYD:  And I think some of these things
 8    you're saying should be considered when you do those things.
 9              DR. APOSTOLAKIS:  I don't think anybody is looking
10    into it.
11              DR. BONACA:  That's a very good point you're
12    making.
13              DR. APOSTOLAKIS:  I made that ten years ago.
14    DR. BONACA:  In particular, these problems of testing were
15    found in the safety systems, which are difficult to test,
16    because the standby systems never run and when you look at
17    some of the recirculation pumps, you recirculate back and on
18    a look that doesn't represent the actual physical
19    performance.
20              MR. LLOYD:  Exactly.
21              DR. APOSTOLAKIS:  But yet, if you do go to Bayes'
22    theorem, that high tail disappears in a second.  So maybe
23    when next we speak to Mr. Cunningham.
24              DR. SEALE:  Can we move along here?
25              MR. LLOYD:  Yes, we need to move along.  The slide
.                                                               140
 1    eight just shows the distribution of each of those.  There
 2    were a number of plants that had zero DBIs for the entire
 3    year '97.  The highest one was 37, that was Crystal River.
 4              Engineering inspection hours varied a lot, as you
 5    can see, from 90 to 3,700.  And if you look at how fertile
 6    the field might be at a particular facility, you can say
 7    that the inspection hours per design basis issue ought to
 8    tell you something.
 9              If it's 15, you've only got 15 inspection hours in
10    for every single reported DBI that comes out, and we had a
11    plant like that.  We had, at the other extreme, 630 hours of
12    inspection time and a lot of these -- in both places -- used
13    contractors of supposedly high experience and background in
14    order to pull that stuff out, and they still didn't find a
15    problem.
16              DR. SEALE:  Could I ask you, when you say that
17    there was a certain number of hours per DBI, is that taking
18    all the DBIs and dividing them into all of the inspection
19    hours or only the inspection hours that were expended
20    looking into that particular issue?
21              MR. LLOYD:  It's kind of a combination of the two. 
22    We looked at just engineering and design inspections at a
23    particular facility and then the number of DBIs that came
24    out of that same facility.
25              DR. SEALE:  Okay.  So in some cases, if you were
.                                                               141
 1    really good, that is, if your plant was in good shape and in
 2    general compliance, that tended to push you to the high
 3    inspection hour number, which is not really a valid adverse
 4    effect.
 5              DR. WALLIS:  On the other hand, there were 20
 6    years of inspection hours which did not show up, some of
 7    these DBIs.
 8              DR. SEALE:  That's right.
 9              DR. WALLIS:  So I'm not quite sure what to
10    conclude.
11              MR. LLOYD:  The next slide shows where we divided
12    up the various DBIs and the systems that were affected.  If
13    you included both the group one and group two DBIs, which
14    would be any design basis issue that got reported, whether
15    it was potentially risk significant or not, then you had
16    emergency core cooling and the AC/DC system would be the top
17    two contributors out of that.
18              If you only looked at those DBIs that had a
19    potential to affect risk at that plant, well, then the
20    distribution changes somewhat and you've got your emergency
21    core cooling at 34 percent, your AC/DC at 18, and then it
22    drops off after that.
23              The group one, as I mentioned before, is the
24    potentially risk significant.  There were 95 of those that
25    occurred during '97.  The group two, there were 315 of those
.                                                               142
 1    that occurred.
 2              DR. APOSTOLAKIS:  Why are you reporting
 3    potentially risk significant?  You haven't done the risk
 4    evaluation yet?
 5              MR. LLOYD:  This was based on the Brookhaven Lab,
 6    whether it was on the risk issue matrix, and then we --
 7              DR. APOSTOLAKIS:  Somehow we have to have a
 8    resolution.  Were they significant or not?
 9              MR. LLOYD:  We had 95.  Out of that, there were
10    like just three that met the ASP threshold.  So there's
11    quite a drop-off. So this would give you a conservative
12    estimate as to whether it was risk significant or not.
13              DR. APOSTOLAKIS:  Do you plan to actually evaluate
14    the risk significance?
15              MR. LLOYD:  We didn't, no.
16              DR. APOSTOLAKIS:  Somebody else will?
17              MR. LLOYD:  Right.
18              DR. BONACA:  The figure three shows -- I'm sorry. 
19    That's different.
20              MR. LLOYD:  We did not.  We grouped them
21    conservatively into these two groups based on Oak -- not Oak
22    Ridge, but Brookhaven group, and then we looked at that and
23    read through the design basis information as best we could
24    and then sometimes, even though it was on the rim, we looked
25    at the function and the problem that had actually occurred
.                                                               143
 1    and because of that, we eliminated that particular issue.
 2              So it would be something less than what was
 3    actually on the rim, but it would give you a conservative
 4    amount.  So you've got like 95 out of 500 issues or so that
 5    you would actually have to maybe be concerned with and then
 6    only a small fraction of that would actually get you into
 7    the ten-to-the-minus-sixth or bigger.
 8              DR. APOSTOLAKIS:  My concern is that a statement
 9    like this up there may not give a warm feeling to the
10    general public that we know what we're doing.  Potentially
11    risk significant, I come back to Dr. Wallis' argument, what
12    do you mean numerically potentially risk significant and if
13    it's potential, why haven't you done it last night to find
14    out what it is.
15              MR. LLOYD:  I think that's what we're really
16    trying to do in the inspection program today.  If you've got
17    something that you've ran through the SEP process, you'd
18    like to get an SRA to look at it and see as quickly as
19    possible whether or not there's any real risk significance
20    standing there.
21              DR. APOSTOLAKIS:  And they have the tools to do
22    that?
23              MR. LLOYD:  In times past, people would write an
24    LER, even the Wolf Creek event, for example.  It wasn't
25    until AEOD went down and looked at Wolf Creek that it was
.                                                               144
 1    determined that there was any significance there at all. 
 2    People wrote it off as not significant.  The licensee wasn't
 3    even going to report it, in fact.
 4              So what we're trying to do is speed up this
 5    process and I think we're heading in that direction with the
 6    kind of program we have now.
 7              DR. APOSTOLAKIS:  Speaking of the AEOD, we have
 8    seen a series of reports where they estimate
 9    unavailabilities of trains and so on using information
10    pretty much the same as yours and they come up with numbers
11    that are within the PRA range.
12              So are we talking about the same body of
13    information here that the AEOD has already done the analysis
14    and they found the PRA is not off?
15              I mean, all these incidents, the DBIs that you
16    mentioned, are they also included in these AEOD analyses? 
17    In which case I know that they are not risk significant.  Or
18    are you doing something entirely different?
19              MR. LLOYD:  I think they're already included.
20              DR. APOSTOLAKIS:  They're already included.
21              MR. LLOYD:  I think so.  Next slide.
22              DR. APOSTOLAKIS:  So we know the risk
23    significance.  You don't need to go to the BNL tables.
24              DR. KRESS:  I think that's the message Dana
25    brought up a while ago, that it's not a real risk
.                                                               145
 1    significance.
 2              MR. LLOYD:  It's not very risk significant.
 3              DR. KRESS:  So that this is an answer to the
 4    critics who say you got all these problems not modeled in
 5    the PRA.  They are.  They show up in some of the database of
 6    availabilities and reliabilities.
 7              DR. APOSTOLAKIS:  The point is we have gone beyond
 8    what the footnote says that these are potentially risk
 9    significant, they have already been evaluated.
10              DR. KRESS:  The potential is just a category that
11    came out of Brookhaven.  It's just a name.  You shouldn't
12    interpret it to mean it really is.
13              DR. APOSTOLAKIS:  What I'm saying is we shouldn't
14    even be using those things.
15              DR. KRESS:  I understand.  I don't like the name
16    either.
17              DR. APOSTOLAKIS:  Since we already have these
18    other kind of analyses, why go to the tables?
19              DR. KRESS:  But it was the name they pulled out of
20    the Brookhaven report.
21              MR. LLOYD:  The next one, slide ten, shows how the
22    breakdown would be by age, which was one of the things we
23    looked at.  This is a standard age grouping.
24              If you look at the older plants, they showed up as
25    producing more design basis issues than the newer plants and
.                                                               146
 1    there's several reasons, I think, for that.  One is just the
 2    completeness of the design basis information, that at some
 3    of the older plants, it's not nearly as good as the newer
 4    plants.
 5              The analysis techniques that were used back in the
 6    '70s are different than the analysis techniques used in the
 7    '80s and '90s.  So that's probably the biggest reason for
 8    those changes.
 9              But nonetheless, the older plants are the ones
10    that tend to report more problems.
11              DR. KRESS:  I have problems deciding whether those
12    numbers are significantly different.
13              DR. WALLIS:  This is over what time span?
14              MR. LLOYD:  This is just over this one year.
15              DR. WALLIS:  One year, that's right.
16              MR. LLOYD:  We went back in time and tried to
17    correlate with previous years and it appears to be very
18    little from year to year.
19              DR. SEALE:  Very flat.
20              MR. LLOYD:  It was very flat.  So the production
21    of each of these is very similar to previous years, but this
22    was just done specifically for 1997.  You would expect
23    essentially the same thing to occur at other ones.
24              The next slide shows the group one, which is this
25    potentially risk significant set of DBIs, and how that might
.                                                               147
 1    show up, and it combines age and whether or not you're at a
 2    single-
 3    unit facility or a multi-unit facility.
 4              For each of the age brackets here, you've got more
 5    design basis issues being reported at multi-unit facilities
 6    than at single-unit facilities.
 7              The reason being for that is largely the
 8    connection between various systems that are either utilized
 9    in both plants or it's a multi-unit site, some of the
10    interconnection.  So you've got problems in addition to just
11    trying to resolve a single unit source of issues.
12              So in each case, whether you're an A group or a B
13    group or a C group, as far as age category goes, it was an
14    increase if you happen to be at a multi-unit facility.
15              Slide 12, we can just briefly go through this one,
16    since we've already talked about it.  It goes along with the
17    ASP and how ASP relates to design basis issues.
18              If you go back to the 1990-91 time period,
19    approximately eight percent of the design basis issues met
20    the ASP.  Today, it's less than one percent, it's like .6
21    percent met that.
22              The number of ASP DBI events went from 13 to three
23    over that time period, it's been a steady decrease.
24              The total number of ASP events from any kind of
25    initiator decreased from 28 to five.
.                                                               148
 1              So you could assume that the licensees are doing
 2    better.  You could assume that we've found the bigger
 3    nuggets in the past and we're left with some of the smaller
 4    design basis issues.
 5              And a lot of the issues I think today are actually
 6    discovered because of our analysis techniques are a lot
 7    better today than what they were ten or 15 years ago.
 8              So what might show up as, yeah, I can find this
 9    very minute problem in my design, previous analysis
10    techniques, done ten, 15 years ago would not have discovered
11    that.
12              DR. APOSTOLAKIS:  Again, just citing the proper
13    number of ASP events is not sufficient information, because
14    I may end up with one ASP event and feel happy and the
15    conditional core damage probability may be
16    ten-to-the-minus-two.
17              So can you give us an idea of what kinds of --
18              MR. LLOYD:  Next slide, good lead-in.
19              DR. WALLIS:  I just have a couple of facetious
20    questions.  Were you asked to put a lot of numbers up to
21    please me?
22              DR. SEALE:  It's just these guys talk about data.
23              MR. LLOYD:  Slide 13 has all the important ASP
24    events on it for an eight-year time period.  Important means
25    that it has a conditional core damage probability of
.                                                               149
 1    ten-to-the-minus-four or bigger.
 2              So if you look at those, there were only three out
 3    of the 14 that involved a design issue and all three of
 4    those occurred at PWRs.  So you can draw your own conclusion
 5    on that.  I think the density of the data is not really big
 6    enough to say that PWRs are the ones that we should be
 7    worrying about and we shouldn't worry about the B side.
 8              DR. APOSTOLAKIS:  Again, I don't think this is
 9    complete information.  For certain purposes, it's okay, but
10    if you worry about the quality of PRA and its fidelity, I
11    think you need an extra column showing the uncertainty that
12    the PRA estimated for the core damage frequency.
13              So then a number like 2.5-ten-to-the-minus-four
14    would be meaningful to me, because if the PRA had a
15    ten-to-the-minus-five, then I would really worry. But if it
16    was within the range, then I would say, well, gee, they
17    missed it, but, you know.
18              So if you could show something like that, I think
19    that would go a long way.  Now, down there, I see a
20    three-ten-to-the-minus-three.  That was at Wolf Creek.
21              DR. KRESS:  That's conditional on the event.
22              MR. LLOYD:  That's just conditional.
23              DR. APOSTOLAKIS:  But at that time, that was the
24    frequency.  So I'd like to know what the estimated range
25    was.
.                                                               150
 1              DR. KRESS:  But you need another number, and
 2    that's the conditional that the event would happen because
 3    of this DBI.
 4              DR. APOSTOLAKIS:  I understand that, but in this
 5    particular case, you are talking about the future.  What I'm
 6    concerned about is the criticism that the numbers that you
 7    get now are not representative.
 8              DR. KRESS:  Yes, I understand.
 9              DR. APOSTOLAKIS:  So if I get a number that's
10    ten-to-the-minus-four and they show me
11    three-ten-to-the-minus-three, then it's not representative.
12              MR. LLOYD:  This has been a compliant, I think, of
13    PRAs in the past, that you've got similar units and if their
14    baseline CDF is X and why is it so different at some other
15    place, and do they do the PRA different, is the model
16    different, is the level of information that you put into not
17    as good.
18              There's all sorts of assumptions that you would go
19    through.
20              DR. BONACA:  The other thing I would like to add
21    is that the comforting issue and where you see the trend in
22    decreasing number of significant issues, that some of these
23    issues were not unique to the plant.
24              When you find MPSH issues on plants, other plants
25    very quietly reviewed it and found they had the same
.                                                               151
 1    problem.
 2              MR. LLOYD:  Right.
 3              DR. BONACA:  Now they've fixed that problem.  So
 4    what has happened is that some of these issues were generic
 5    and where they were found significant by this common
 6    experience, they have been resolved, and that's the reason
 7    why you find less.
 8              DR. KRESS:  Don't those show up in an LER?
 9              DR. BONACA:  I'm sorry?
10              DR. KRESS:  Wouldn't those show up in an LER?  If
11    they found them, even though after the fact, they'd have to
12    write an LER on them and they would show up in here,
13    wouldn't they?
14              DR. BONACA:  Would they show up in an LER that
15    way?
16              MR. LLOYD:  They may or may not.
17              DR. BONACA:  They may not.  Because I know, for
18    example, the MPSH was found by many plants after we found it
19    at Haddam Neck.
20              MR. LLOYD:  Haddam Neck, right.
21              DR. BONACA:  And they were resolved.  But now I
22    don't remember there were LERs.  I don't know why.
23              DR. KRESS:  I think what George is looking for is
24    some ammunition to use and I'm not sure we get it completely
25    out of this, but it looks like this has the potential to
.                                                               152
 1    give you that information and I guess you're looking for how
 2    to take it further.
 3              DR. APOSTOLAKIS:  All I want to know is the guy
 4    who did the PRA for the fourth row, for example, what kind
 5    of distribution for the CDF did he report and then I would
 6    look at the 2.1-ten-to-the-minus-four and get some idea, if
 7    I do that for all of them, as to how good the PRAs have
 8    been.
 9              DR. BONACA:  The uncertainty analysis should be
10    within -- sure.
11              DR. APOSTOLAKIS:  They are.
12              MR. LLOYD:  Good point.  Next slide talks about --
13    we looked at regions and plants, once again, that had these
14    group one DBIs.  Regions I and III had the highest
15    percentage of plants that had at least one DBI at 52 and 59
16    percent.  Two and four were significantly less, 36 and 19.
17              DR. POWERS:  Aren't these just highly correlated
18    with the age of the plants in the regions?
19              MR. LLOYD:  Pardon?
20              DR. POWERS:  Isn't this just highly correlated
21    with the age of the plants?
22              MR. LLOYD:  I think it's highly correlated with
23    the age of the plants.
24              DR. SEALE:  There might be a latitude effect here,
25    too.
.                                                               153
 1              DR. POWERS:  I think that would be an unfortunate
 2    conclusion because of the correlation effect here.
 3              MR. LLOYD:  This could be north versus south.
 4              DR. KRESS:  Clearly, Region IV is a much better
 5    region.
 6              DR. BONACA:  You also reported in your report that
 7    the more you look, the more you find.
 8              MR. LLOYD:  The more you look, the more you find. 
 9    And if you look at the number of inspection hours that
10    occurred in Regions I and III, you'll see a much higher
11    number than the number of inspections hours that you will
12    see in either of the southern regions.
13              So that would have an impact on it, also.
14              DR. POWERS:  So you're telling me that the move
15    toward a more averaged inspection hours may not be a good
16    move.
17              MR. LLOYD:  I think it's a good move.
18              DR. POWERS:  You think it's a good move.
19              MR. LLOYD:  I think it's a good move.  If you
20    standardized who gets what and when, then you have a little
21    more normalization going on and you can decide whether or
22    not somebody is good or bad a lot better.
23              DR. APOSTOLAKIS:  Maybe I missed it, but who
24    discovered this?  Was it NRC inspectors or the plant people?
25              MR. LLOYD:  These were plant people.
.                                                               154
 1              DR. APOSTOLAKIS:  Plant people.
 2              MR. LLOYD:  Mostly plant people that discovered
 3    these.  A portion of those came because of us; i.e., we
 4    turned out a generic letter or a bulletin somehow that made
 5    the licensee go look and then they found a problem.
 6              DR. APOSTOLAKIS:  Right.
 7              MR. LLOYD:  In some places, we told them, in the
 8    50.54(f) letter, to go out and do their design check and
 9    when they did that, they found some problems.  Some of these
10    were the result of NRC inspections, like the SWOOPIES and
11    things like that, where they went out and we found something
12    and the licensee picked it up and then subsequently reported
13    it.  So there's a combination of all those things.
14              The next slide has to do with what we've already
15    mentioned here, the more you look, the more you find.  We
16    did a correlation analysis between the number of issues
17    reported versus the number of hours that we actually
18    inspected, and it showed exactly that.
19              You go look more, you'll end up finding more.  The
20    correlation coefficient on that, as shown in the report, was
21    .77.  The P value was less than .01.  And so that has an
22    impact on how you do your inspections.
23              You could go out to a Millstone, for example, and
24    inspect the living daylights out of them and certainly they
25    reported a lot of issues.
.                                                               155
 1              DR. APOSTOLAKIS:  You haven't done this?
 2              MR. LLOYD:  And very little of this has ever
 3    turned up as really safety significant.
 4              DR. APOSTOLAKIS:  The correlation analysis you did
 5    was only on the NRC findings, not the plant findings.
 6              MR. LLOYD:  This includes all the findings,
 7    whether they originated from us or the plant.
 8              DR. KRESS:  Number of findings and number of
 9    inspection hours, total.
10              MR. LLOYD:  It's here is how many inspection hours
11    we put in and then here's how many findings.
12              DR. SEALE:  The LER comes from the utility.
13              MR. LLOYD:  Right.  The LER comes from the
14    utility.
15              DR. SEALE:  Whatever may have motivated it.
16              DR. POWERS:  I had a question.  You used a linear
17    regression analysis and I don't fault that, but I notice a
18    lot of AEOD reports or -- I'm going to keep calling them
19    AEOD reports, regardless where you are.  I'm still holding
20    out for an independent group here.
21              MR. LLOYD:  No AEOD.
22              DR. POWERS:  You used a linear correlation
23    analysis.  I was surprised by that, because there's no
24    reason to think that there's a linearity between the number
25    of inspection hours and the number of findings.  In fact,
.                                                               156
 1    you would probably --
 2              DR. KRESS:  That would trail off at the end.
 3              DR. POWERS:  You would probably expect some
 4    non-linearity and whatnot.  And I was wondering, as a
 5    general process, do you have more sophisticated
 6    correlational analyses than just linear regression available
 7    to you?
 8              MR. LLOYD:  What was done here, we used the SAS
 9    program, which I think is used lots of places in the NRC and
10    in the industry as an accepted program that does that kind
11    of analysis.
12              DR. KRESS:  It has two or three correlations.  I
13    think if you choose any of them here, you get about the same
14    correlation.
15              DR. POWERS:  It seems to me that I would have --
16    my initial reaction to it was I would have done an analysis
17    to see if they came out with the same distributions, if they
18    were isometric distributions, and get rid of the hypothesis
19    of linearity on the thing.
20              And I just wondered if tools like that were
21    available to you, because I see so many linear correlations
22    coming out of these.
23              DR. KRESS:  That does exist in the SAS program.
24              DR. POWERS:  It does.
25              DR. KRESS:  And I think if you used it, I don't
.                                                               157
 1    know if they did, that part of it, used it, you would find
 2    out the same.  You wouldn't have much reason to choose
 3    another correlation over the linear, in this case.
 4              But I think this correlation is a pretty high
 5    correlation, actually.
 6              MR. LLOYD:  It's a very good correlation.
 7              DR. KRESS:  And I think it tells you something
 8    about the LER process.  Maybe it's deficient in some way or
 9    other.
10              MR. LLOYD:  The next slide shows something we've
11    been talking about here in between the lines as we've gone
12    through the presentation, number 16 shows the highest number
13    of DBIs over this eight-year period, shows the plants.
14              DR. POWERS:  What's going on down at Crystal
15    River?
16              MR. LLOYD:  Crystal River had 93.  Then you go on
17    down to Millstone and you drop off.  I had the cutoff down
18    there at Salem I, but it's interesting to look at the -- out
19    of all those DBIs at Crystal River 3, 93 of them, zero of
20    those tripped the ASP threshold.
21              For all the effort that we did at Millstone 3,
22    there were 55 DBIs that came out of that, none of those
23    tripped the ASP threshold.  It's interesting to go find
24    these design problems, but at the same time, if there's no
25    real impact on risk, the question has to come out, you know
.                                                               158
 1    --
 2              DR. KRESS:  Why do it.
 3              MR. LLOYD:  -- why do we have to report these
 4    kinds of things and couldn't we change the reporting system
 5    to reflect the risk side of it and then get to the place
 6    where we could reduce burden on not only the licensee by
 7    having to report this stuff, but it's also a burden on the
 8    agency, because we have to analyze it and try to figure out
 9    what it means.
10              DR. POWERS:  We could cut back Oak Ridge's budget
11    pretty good here.
12              DR. APOSTOLAKIS:  I think in the name of
13    defense-in-depth, we should keep it.
14              DR. WALLIS:  Whether it's risk significant or not,
15    it's the measure of performance versus regulation.  It's
16    telling you something about whether the regulations actually
17    lead to better performance or not.
18              MR. LLOYD:  Exactly.  Right.
19              DR. WALLIS:  That seems to be a wider message than
20    just risk significant.
21              MR. LLOYD:  It is.  Slide 17, we took a couple of
22    case studies, and this was one of them, and we just said,
23    well, you know, what has happened and our bottom line, I
24    guess, was that it takes, in many cases, several years to go
25    out and resolve and implement changes to go out and fix some
.                                                               159
 1    of the design problems.
 2              Some of the more obvious ones that everybody has
 3    seen, and that's the PWR containment sump strainer and the
 4    BWR ECS strainer clogging issues.
 5              And if you look at the next slide, the generic
 6    communication that we have issued goes back to 1988 and that
 7    didn't work and then we issued one in '89 and '90 and '92
 8    and we just kept on issuing them, issue after issue after
 9    issue, when they were very, very similar.
10              A lot of the same kinds of problems were
11    identified in all these different issues.  It wouldn't have
12    been that difficult for a licensee to extrapolate and say,
13    well, you know, maybe we ought to do something here, or for
14    the agency to do the same thing.  Why should we have to turn
15    out this many generic communications before we got the big
16    flick?
17              DR. POWERS:  In defense of the licensee, if he is,
18    in fact, handling 6,000 pieces of communication coming in,
19    one, it doesn't say do something now on your particular
20    plant, doing extrapolation is difficult for him.
21              Yes, in abstract, it's easy.  In the context of
22    all the other work he has to do, it's not so easy.
23              MR. LLOYD:  I guess the overall conclusion that
24    you can sort of make on this, and it's problems we have to
25    resolve, because we are in transition going from a
.                                                               160
 1    defense-in-depth deterministic sort of a mode into more of a
 2    risk mode as we deal with licensees, and it's hard to
 3    convert the deterministic guy to the risk side and it's hard
 4    to convert the risk side that the deterministic side has
 5    some merit and benefit.
 6              So we need to work on that.  I think there's lots
 7    of opportunities to reduce burden on licensees as far as
 8    reporting goes.  It would reduce burden on them and would,
 9    at the same time, reduce burden on us.  WE need to, I think,
10    focus our attention more on those DBIs that are truly risk
11    significant and the ones that aren't I think we could just
12    push to the wayside and move on.
13              Even though if you look at 1997, for example,
14    there were five ASP events, three of those ASP events were
15    design related.  So, granted, there weren't very many design
16    related problems, but nonetheless, they still occupied 60
17    percent plus of the ASP events that got reported during that
18    year.
19              So there is an impact and a need to look at design
20    issues.
21              I think the oversight process, the reporting
22    requirements, the changes that are being made there, what to
23    do with Part 50 and other regulations that we've got will
24    certainly be of benefit in burden reduction and our
25    definitions of what design basis really is and what should
.                                                               161
 1    be included in that definition would help to resolve some of
 2    these problems for the future.
 3              That concludes our presentation.  Thank you.
 4              MR. LEITCH:  Just one very specific comment, and I
 5    only mention this because it's one of those 1997 five DBIs
 6    that resulted in ASP.
 7              The synopsis of the Maine Yankee issue talks about
 8    reactor coolant.  My recollection of that problem is it was
 9    component cooling, not primary system, the system they
10    called primary component cooling.
11              I'm not sure if it's just the synopsis that's
12    wrong or if, in your calculation of the PRA number, that it
13    was analyzed improperly.
14              MR. LLOYD:  I'm not sure.  I'd have to look at it.
15              MR. LEITCH:  What I'm saying is it's one of the
16    five and it's one of the three of the five that are involved
17    in the DBI.  So it just may be interesting to go back and
18    look at that.  It may just skew your statistics if the
19    conclusion is wrong.
20              MR. LLOYD:  Okay.  I'll check on that.  Thank you.
21              DR. SEALE:  Any other comments from any member of
22    the committee?
23              DR. POWERS:  I would just comment again that on
24    the face of it, it looked to me like a pretty boring study,
25    turned out to have, I think, some real implications on how I
.                                                               162
 1    view the role of PRA.
 2              And though you may conclude that not much was
 3    found out of this, I think it provides some ammunition to
 4    confront critics of the PRA methodology here.
 5              So once again, we find that the AEOD scrutiny of
 6    the database is proving value in supporting our move to
 7    risk-informed regulation.
 8              And I think one of our obligations in our research
 9    report is to comment on how this change in organization has
10    affected or not affected our access to that kind of
11    information.
12              DR. SEALE:  Yes.  I think also that it's incumbent
13    upon us, when we have questions of this sort, to not slough
14    off the question and figure, well, there's not a place where
15    we could really find that out, because I think there is, if
16    we look hard enough.
17              These people are handling and looking at an awful
18    lot of data.  They are giving us -- they are getting a lot
19    of insight and we are remiss if we don't seek that insight
20    and make sure we use it in the specific cases where it's
21    applicable to any recommendations we may formulate.
22              I'm sure that we'll come back to see you again
23    about other things and I surely hope you will not be
24    hesitant in coming back to see us when you have something
25    else like this to report, because it is extremely valuable.
.                                                               163
 1              As Dana said, the first impression or the first
 2    move is to sort of say what's new, ho hum, but when you
 3    really get into the details, as George did there in looking
 4    at some of the specifics as to what all was included in
 5    these packagings that you did and so on, there's a lot of
 6    data there.
 7              DR. APOSTOLAKIS:  I think there is one piece of
 8    analysis you have to do that would really be valuable to
 9    this.  When you show this at CCDP, show the distribution of
10    the CDF, that's not enough. For how long?  That's important. 
11    For how long did this CCDP exist, because if it was the
12    result of a random failure of something, then I don't think
13    the comparison is meaningful.
14              Random failures occur all the time.  But if you
15    say, no, for the last five years, this is what it was, then
16    there is a problem with the PRA.  So these two pieces of
17    information.
18              DR. SEALE:  Well, again, I want to thank you very
19    much and I figure --
20              MR. LEITCH:  Just one further question.  I found
21    your report, pages 30 and 31, particularly insightful and
22    interesting.  I was just wondering if there's some synopsis
23    of this report that's shared with the industry.
24              MR. LLOYD:  The report was shared with industry. 
25    We have very minor comments back.  I think they supported
.                                                               164
 1    everything they saw in there.  NEI came back and thought it
 2    was good stuff.
 3              MR. LEITCH:  Thank you.
 4              MR. LLOYD:  And thought that it would help and
 5    also moving from this deterministic side into more of a
 6    risk-based side.
 7              MR. LEITCH:  Thank you.
 8              DR. APOSTOLAKIS:  It's a bad tradition, Mr.
 9    Leitch, of AEOD reports not being ready by anybody except
10    AEOD.  We have been complaining about it for a long time.
11              DR. SEALE:  Mr. Chairman, I'll give it back to
12    you.  Thanks again, fellows.
13              DR. POWERS:  I think I'd toss it right back to
14    you, sir.  We move on to the proposed final Regulatory Guide
15    10.93, endorsing NEI 9704, and the esteemed Professor Seale,
16    once again.  We'll move through this expeditiously.
17              DR. SEALE:  Okay.  I'm going to just go ahead and
18    ask our presenters to present.
19              DR. APOSTOLAKIS:  An experienced presenter does
20    not use all the viewgraphs.
21              MR. MAGRUDER:  I'm Stuart Magruder from NRR, a
22    project manager there.
23              MR. BELL:  And I'm Russell Bell, with NEI.  I'm
24    working with Stu and others on the design basis guidance or
25    interpreting the design bases as it's defined in 10 CFR
.                                                               165
 1    50.2.
 2              DR. APOSTOLAKIS:  Why is it plural, bases?
 3              MR. MAGRUDER:  There's a lot of bases that the
 4    plant is designed on.  That's a good -- it's a matter of
 5    semantics, it's a good question.
 6              MR. BELL:  Collectively, it's one design basis, I
 7    suppose you could say.
 8              DR. APOSTOLAKIS:  Is this the first time the
 9    committee is having a presentation from NEI and NRR at the
10    same time?
11              DR. KRESS:  No.  We've had them before.
12              DR. POWERS:  This has actually become fairly
13    common in connection with the regulatory guides.
14              DR. BONACA:  And you came here originally with
15    some disagreement, I remember.
16              MR. MAGRUDER:  Yes.  We briefed you last fall and
17    I'm happy to report that we have a positive outcome, I think
18    anyway.  We'll find out.
19              Very briefly, the objective here was to develop
20    guidance to clarify many of the issues that were presented
21    in the last discussion, a lot of different ideas about what
22    design bases meant and when to report when you're outside
23    the design bases.
24              So I'll get to a little bit of discussion here
25    about background and why we did this, but the bottom line is
.                                                               166
 1    we have a final reg guide enforcing industry developed
 2    guidance or joint staff and industry developed guidance, and
 3    we're seeking your approval to publish that guidance.
 4              DR. SEALE:  So you want a letter from us.
 5              MR. MAGRUDER:  Yes, sir.  For background
 6    information, this is the definition that appears in 50.2. 
 7    It was put there in 1968, I believe.  It's not been modified
 8    since then and we are not proposing to modify the
 9    definition.  We're just proposing to clarify it in our
10    guidance what it means.
11              DR. APOSTOLAKIS:  So plant configuration is not
12    part of the design basis.
13              MR. MAGRUDER:  That's correct.  Well, to the
14    extent that the plant is designed a certain way, but the
15    maintenance of that configuration or the control of the
16    configuration is not part of the design basis.
17              DR. APOSTOLAKIS:  So it's part of the licensing
18    basis?
19              MR. MAGRUDER:  Yes, I'd say so.
20              DR. APOSTOLAKIS:  So if I take a pump and move it
21    one foot to the right, design basis is the same, as long as
22    it does the functions and everything.
23              MR. MAGRUDER:  Yes, and we'll get to that.
24              DR. POWERS:  Well, you have to go through a 50.59
25    assessment on that.
.                                                               167
 1              MR. MAGRUDER:  You may have to.
 2              DR. APOSTOLAKIS:  But it is not covered --
 3              DR. POWERS:  You definitely have to go through it. 
 4    Now, whether you pass the 50.59 screen is the question.
 5              MR. MAGRUDER:  The screen, that's right.  That's
 6    right.
 7              DR. APOSTOLAKIS:  Move it by an inch.
 8              DR. POWERS:  If you move it by an inch, you still
 9    have to go through a 50.59 screen.
10              DR. APOSTOLAKIS:  But that has nothing to do with
11    the design basis.  It's the licensing basis.  I'm learning,
12    I'm learning.  Some of these things are obvious to you guys. 
13    Us academics are not too familiar with those things.
14              DR. BONACA:  By moving it an inch, you may cause
15    an increase in temperature because you're close to a wall
16    that will --
17              DR. APOSTOLAKIS:  I'm getting much more
18    information than I asked for.
19              DR. SEALE:  But none of it is coming from our
20    presenter.
21              DR. POWERS:  How about moving it an inch isn't
22    necessarily affecting its design basis?
23              MR. MAGRUDER:  A little bit of background, again,
24    on the relevance, why we are talking about this.  Obviously,
25    it's used in quite a few places in Part 50, as you see here.
.                                                               168
 1    I'll mention just a few of them.  50.59, it doesn't
 2    currently exist in the regulation.  However, the new
 3    regulation which will become effective early next year, it
 4    will be included in the discussion of which methods would be
 5    subject to 50.59 changes.
 6              And as was alluded to in their last presentation,
 7    it currently exists in the reporting requirements, but it
 8    will no longer exist when the rule is changed, when those
 9    rules are changed.
10              And as was discussed, the new reporting rules are
11    based more on sort of risk significance, but mostly on the
12    functionality of systems.
13              Also, most licensees, I should say, find it useful
14    to define what's design basis for understanding degraded and
15    non-conforming conditions.
16              Much of this background information was discussed
17    in the last presentation, so unless there's any questions
18    about that, I'll just skip this slide.
19              As you're aware, the staff and NEI have worked for
20    several years to develop guidance on the definition or
21    clarification on the definition.  We briefed the committee
22    last fall twice.  The first time we briefed you, we were in
23    disagreement with the industry on a couple points.
24              I think the briefing actually served as an impetus
25    to resolve some of those differences and we came back in
.                                                               169
 1    November and proposed to publish a draft guide for comment,
 2    which we did in -- well, after the Commission approved it,
 3    we published it in April of this year.
 4              As you can see, we got 11 comment letters, all
 5    supportive of the effort.
 6              MR. BELL:  I'm just so impressed with the NRC's
 7    graphics.
 8              DR. POWERS:  I find it remarkable that Region III
 9    felt an obligation to send in a comment letter.  Did you not
10    talk to the regions in developing your positions?
11              MR. MAGRUDER:  No.  As a matter of fact, I think
12    one of the reasons they chose to send in one was because
13    they had been actively participating.
14              DR. POWERS:  I see.
15              DR. SEALE:  As I recall, one of the Region III
16    people was pretty well involved in doing this process,
17    wasn't he?
18              MR. MAGRUDER:  We've gotten input from various
19    people from the regions, but yes.  We try to make sure that
20    we're grounded in reality and talk to the regions.
21              DR. POWERS:  We'll certainly expect NEI
22    presentations in the future to live up to the standard
23    that's being set here.
24              MR. BELL:  I'm not sure we can.
25              DR. APOSTOLAKIS:  Your first bullet says that
.                                                               170
 1    defense-in-depth is an important aspect of principal design
 2    criteria. You must have a definition of defense-in-depth
 3    someplace.
 4              MR. MAGRUDER:  I think that can be found in the
 5    research paper this morning.
 6              DR. POWERS:  The best answer you could possibly
 7    give.  Go on.
 8              DR. SEALE:  Keep going.
 9              MR. MAGRUDER:  The point here is we wanted to
10    clarify in the draft guide the guidance that NEI had and
11    just make it clear that defense-in-depth is kind of a higher
12    level idea than the specifics of the design of the plant.
13              DR. APOSTOLAKIS:  Higher than what?
14              MR. MAGRUDER:  It guides the detailed design of
15    the plant.
16              DR. APOSTOLAKIS:  And NEI felt defense-in-depth
17    was not important?
18              MR. MAGRUDER:  No.  Actually, I think after we
19    discussed it, they agreed with us and we no longer have an
20    exception, but when we were reviewing their draft guidance
21    at the time, we just thought it was important to point this
22    out.
23              DR. APOSTOLAKIS:  How can something that is not
24    well defined be important?
25              DR. SHACK:  It's like a safety margin.
.                                                               171
 1              DR. APOSTOLAKIS:  Oh, because we have another
 2    example.  I'm sorry.
 3              DR. POWERS:  I think if you look closely.
 4              DR. APOSTOLAKIS:  I think I'm listening to
 5    Professor Wallis too much.
 6              DR. POWERS:  I think if you look closely to Mr.
 7    Gidell's arguments, you will find out that, in fact, there
 8    are parts of any system that you cannot define, where you
 9    arrive at logical inconsistencies.
10              DR. APOSTOLAKIS:  Boy, how can I object to that?
11              DR. POWERS:  That's right.  Please continue.
12              DR. APOSTOLAKIS:  Because you know that that man
13    ended up being crazy.
14              DR. POWERS:  Because he kept looking for a
15    definition of defense-in-depth.
16              MR. MAGRUDER:  The second point there is a
17    clarification we put in the draft guide regarding the
18    relationship of design basis to the updated FSAR and we just
19    wanted to make sure that it was clear that -- two points,
20    actually.
21              One was that changes to design basis can occur for
22    various reasons, including licensees' initiated changes to
23    the plant, and the fact that we wanted to make sure that it
24    was clear that supporting design information is also
25    required to be in the FSAR, as discussed in 50.34.
.                                                               172
 1              Subsequently, as you will see, NEI updated their
 2    guidance document and they've alleviated our concerns in
 3    those two areas.  So we're proposing no exceptions in our
 4    final reg guide right now.
 5              This slide, I just wanted to kind of
 6    re-familiarize everyone with the major points of the
 7    guidance document.  These are kind of the crux of the issue
 8    here, the design basis function definition and design basis
 9    values.
10              It's more or less a rephrasing of the 50.2
11    definition.  I'll just point out that design basis functions
12    are those that are necessary to comply with basically our
13    requirements or are relied on in the safety analyses, and
14    the values are those values, the important phrase there,
15    reference bounds for design to meet design basis functional
16    requirements.  So that kind of puts a bound on which
17    functions and which values we're talking about.
18              DR. POWERS:  My recollection of 50.2 is imperfect
19    on the exact language.  Why did you feel a need to rephrase
20    it?
21              MR. MAGRUDER:  It's not quite the same language
22    and there's been -- this is not a perfect solution, either. 
23    I'm sure there will always be differences in interpretation,
24    but this is a little bit clearer, and the guidance document
25    actually provides quite a few examples from systems which
.                                                               173
 1    will hopefully help licensees and the staff understand
 2    what's design basis information and what's supporting
 3    information.
 4              And we're already at the summary, which is that we
 5    have reached a common understanding through many years of
 6    meetings with NEI and their task force, comprised of many
 7    utility representatives.  The public comments support the
 8    guidance and we are requesting a letter from the committee
 9    to publish it.
10              DR. APOSTOLAKIS:  I had a question -- go ahead.
11              MR. LEITCH:  You indicate here that you're
12    endorsing NEI 9704 Appendix B.  I guess I'm just curious. 
13    What is the total content of 9704?  Does it deal with issues
14    other than this or does that represent a remaining
15    difference of opinion?  Just what is the total scope of
16    9704?
17              MR. BELL:  It's worth explaining.  Thanks.  And by
18    the way, Mr. Chairman, I brought no slides, so I'll be
19    maximally expeditious.  Had I had a slide, I might have
20    addressed this question on it.
21              DR. SEALE:  Your reticence is duly noted.
22              MR. BELL:  Appendix B is that portion of a larger
23    document 9704 that deals with interpreting the definition of
24    design bases.  So Appendix B is where our interactions over
25    the last couple years have focused and it will be on that
.                                                               174
 1    appendix that the NRC endorsement covers.
 2              The rest of the document is called design basis
 3    program guidelines.  It dates back to an old NUMARC
 4    document, the NEI predecessor, back at a time when utilities
 5    were reconstituting their design bases and establishing
 6    programs for doing that, and NUMARC, at the time, produced a
 7    document to help people -- to write guidance for folks who
 8    wanted to reconstitute.
 9              So there's a lot of programmatic information in
10    there, where to look for this type of information and so
11    forth.
12              And really none of that -- all that is still
13    useful guidance, we think, we're not retracting it, but it
14    is not on point with the question of the interpretation of
15    this term.
16              So our interactions have focused on that appendix,
17    the interpretation of the term.
18              We plan to revise it, issue a Revision 1 that
19    incorporates the revised Appendix B and we'll do that as
20    soon as all the T's are crossed and the I's dotted on the
21    appendix.
22              MR. MAGRUDER:  Let me also point out, I skipped
23    over the background here, but in 1992, the Commission issued
24    a policy statement on design basis and endorsed, to some
25    extent, the 9012, the NUMARC 9012 document on design basis
.                                                               175
 1    reconstitution.
 2              We didn't specifically endorse their discussion of
 3    the definition of design basis, but the approach of
 4    reconstituting the design basis the Commission endorsed.
 5              DR. APOSTOLAKIS:  Is that what you quote here, the
 6    guidance outlines of framework to organize and correlate
 7    nuclear power plant design basis information?
 8              MR. MAGRUDER:  Yes.
 9              DR. APOSTOLAKIS:  Then I read, on the next page,
10    objective, the staff's objective is to develop guidance that
11    provides a clearer understanding of what constitutes design
12    basis information.  Correct?
13              MR. MAGRUDER:  Correct.
14              DR. APOSTOLAKIS:  So far I understand that we're
15    talking about facts.  Then I go down to defense-in-depth. 
16    These criteria provide part of the standard for judging the
17    adequacy of the plant's design basis.
18              Now, we're in a different domain here.  Adequacy. 
19    Why?  I thought it was only information.
20              MR. MAGRUDER:  I'm not sure.
21              DR. APOSTOLAKIS:  That's from your document.
22              MR. MAGRUDER:  I know.  I'm not sure what your
23    question is.
24              DR. APOSTOLAKIS:  The question, I thought, from
25    what the Commission said on your objectives, is to provide a
.                                                               176
 1    clearer understanding of what constitutes design basis
 2    information.
 3              MR. MAGRUDER:  Correct.
 4              DR. APOSTOLAKIS:  Not to evaluate the adequacy of
 5    that information.
 6              MR. MAGRUDER:  That's correct.
 7              DR. POWERS:  But the information that's part of
 8    the material used for evaluating the adequacy.
 9              DR. APOSTOLAKIS:  But not here.  This is not the
10    purpose of this guide, is it?
11              MR. MAGRUDER:  No.  The point was that
12    defense-in-depth -- and it's another attempt --
13              DR. APOSTOLAKIS:  So this is warning you that in
14    the future --
15              MR. MAGRUDER:  No.  It's another attempt to define
16    what defense-in-depth is and we're not saying that licensees
17    need to go back and review what's in their design now.
18              DR. APOSTOLAKIS:  I would be happy if you deleted
19    that sentence.  I mean, you have a lot on defense-in-depth,
20    where it says these criteria provide part of the standard
21    for judging the adequacy, that seems to be out of place
22    here.
23              You're not judging anybody's adequacy.
24              DR. POWERS:  But it is, the information that is
25    here is part of the judgment of the adequacy.
.                                                               177
 1    DR. APOSTOLAKIS:  But this regulatory guide does not address
 2    adequacy.
 3              MR. MAGRUDER:  No, it doesn't.
 4              DR. APOSTOLAKIS:  It just collates information.
 5              MR. MAGRUDER:  That's correct.
 6              DR. APOSTOLAKIS:  All of a sudden, adequacy is
 7    thrown in there.
 8              DR. POWERS:  No, it's not thrown in there.  You're
 9    misreading it.
10              DR. APOSTOLAKIS:  And my second question is why
11    didn't you use the definition that the Commission has given
12    to defense-in-depth?
13              MR. MAGRUDER:  We're not attempting to change that
14    definition.  All we're saying is that that definition should
15    be applied in evaluating design basis of the plant.
16              DR. APOSTOLAKIS:  Why didn't you use that
17    definition then in the white paper?
18              MR. MAGRUDER:  That's a good suggestion.
19              DR. APOSTOLAKIS:  Am I the only one who is
20    misunderstanding this paragraph?
21              DR. KRESS:  I thought the word --
22              DR. APOSTOLAKIS:  It's 107, it's under B,
23    discussion, page 7.  If you look at the objective, it says
24    clearer understanding of what constitutes design basis
25    information.  A clearer understanding will help the staff
.                                                               178
 1    and the industry implement the regulations that use the
 2    current design basis.
 3              So I thought it was just the facts.
 4              MR. MAGRUDER:  Yes.
 5              DR. APOSTOLAKIS:  This is what it is.  And at the
 6    bottom of the page, these criteria provide part of the
 7    standard for judging the adequacy of the plant's design
 8    basis.  Now, here or somewhere else.
 9              MR. MAGRUDER:  The criteria that we're referring
10    to is defense-in-depth, not --
11              DR. POWERS:  I think that's not true.  I think the
12    paragraph, the criteria they're speaking of, an earlier
13    sentence says the plant's principal design criteria.
14              MR. MAGRUDER:  Okay.  Thank you.  Right, which are
15    based on defense-in-depth principles.
16              DR. SEALE:  In this paragraph, it says especially
17    the general design criteria, and then the next sentence says
18    these criteria are required.  And then these criteria
19    provide.  So it's the GDC the criteria is referring to here,
20    I think.
21              DR. APOSTOLAKIS:  You are referring to the GDC.
22              MR. MAGRUDER:  Yes.
23              DR. APOSTOLAKIS:  All right.  If everyone thinks
24    that way, what the hell.  The majority is always wrong.
25              MR. MAGRUDER:  That was the intent.  I apologize
.                                                               179
 1    for the --
 2              DR. APOSTOLAKIS:  But I still don't understand why
 3    you don't use the Commission's white paper.
 4              MR. MAGRUDER:  That's a good suggestion.
 5              DR. APOSTOLAKIS:  Multiple barriers.
 6              DR. POWERS:  Because some of us would object, see.
 7              DR. APOSTOLAKIS:  No, no.
 8              DR. SEALE:  Anything else?  Okay.  I'm sure you
 9    can expect to get a letter from us.  Mr. Chairman, I'll give
10    it back to you.
11              DR. POWERS:  Fine.  Thank you, gentlemen.  I
12    enjoyed the presentation and the reading that you provided,
13    and congratulate you for a hard won success here.
14              MR. MAGRUDER:  Thank you.
15              MR. BELL:  Thank you.
16              DR. POWERS:  And look upon it as a chance where
17    we've collegially worked together to produce something that
18    I think, in the end, will benefit all concerned here.
19              DR. SEALE:  Yes.
20              DR. POWERS:  With that, I'm going to recess us
21    until 2:00, to resume the presentations.
22              [Whereupon, at 12:45 p.m., the meeting was
23    recessed, to reconvene this same day at 2:00 p.m.]
24
25
.                                                               180
 1                          AFTERNOON SESSION
 2                                                     [2:00 p.m.]
 3              DR. POWERS:  Let's go back into session.  We are
 4    now going to move to the subject for the future, which is
 5    the AP1000 standard plant design.
 6              The esteemed Dr. Sly Kress will lead us through
 7    this discussion.
 8              DR. KRESS:  That's literally and true.  This is a
 9    discussion of the AP1000.  As most of you know, Westinghouse
10    plans to increase the power of the AP600 up to 1000
11    megawatts electrical and to seek certification thereof.
12              The NRC review of this is planned to be done in
13    there phases, which you'll hear about what those three are
14    today, I'm pretty sure.  The phase one part is already
15    complete and I think we will hear more about what the phase
16    one is and the results of the NRC review.
17              But essentially it was to -- the phase one was
18    just to identify the review issues and identify the
19    informational needs that NRC will need to make their review
20    and estimate the resources and schedules.
21              But also as part of this phase one review,
22    Westinghouse submitted what they called fundamental
23    assumptions for the review.  There were five of these and I
24    think NRC might have added a sixth one.  But I'm not sure,
25    but I hope we hear what these five assumptions were at least
.                                                               181
 1    and what the staff -- what their initial response is to
 2    them.
 3              I'm not sure whether we'll get to that or not, but
 4    with that, I will turn it over to the NRR staff.  I don't
 5    know who.
 6              MR. GRIMES:  Yes.  I will introduce Jerry Wilson,
 7    who is the Senior Standardization Policy Analyst in the
 8    License Renewal and Standardization Branch.
 9    My name is Chris Grimes, and I'm the Chief of the License
10    Renewal and Standardization Branch.  And Dave Matthews will
11    be joining us as time permits.
12              Jerry is going to provide the briefing today and
13    respond to your questions.
14              MR. WILSON:  Thank you, Chris and Dr. Kress.  I
15    believe you all have a copy of the handouts.  I'm going to
16    do an overview.  If there is something particular the
17    committee would like to hear, feel free to interrupt me.
18              By way of background, in January this year, the
19    NRC certified the AP600.  At that point in time, we felt
20    that we had finished with our design certification efforts. 
21    It had been an effort starting in 1987.  But unbeknownst to
22    us and as Dr. Kress said, Westinghouse was designing a 1000
23    megawatt version of their advanced passive design and were
24    thinking of seeking design certification.
25              But they wanted to know in advance what the scope
.                                                               182
 1    of a review of the 1000 megawatt version would be and what
 2    it would cost them, and so they came in and asked for a
 3    pre-application review.
 4              Now, very quickly, what they are proposing to do
 5    is increase the power, but minimize the changes to the AP600
 6    design, and I have identified what I think are the major
 7    changes to the design here in this slide.
 8              But their goal is to minimize the changes in the
 9    design, thereby minimizing the amount of review if they
10    chose to come in for design certification.
11              DR. KRESS:  They're going to increase the fuel
12    length by two feet, is it?
13              MR. WILSON:  Yes, that's correct.  They are going
14    to their 14-foot length.
15              DR. KRESS:  Have they had experience with a
16    14-foot fuel before?
17              MR. WILSON:  Yes.  It's been used in --
18              DR. SEALE:  South Texas.
19              MR. WILSON:  Thank you.  That is my understanding.
20              DR. SEALE:  The problem, though, is that they have
21    a seven percent increase in fuel assembly length and a 20
22    percent increase in the linear heat rating.
23              DR. KRESS:  Which means they're going to put in
24    more enrichment.
25              MR. WILSON:  I don't know that detail.
.                                                               183
 1              DR. KRESS:  I don't know how you do that without
 2    --
 3              DR. SEALE:  Well, whatever, they're going to have
 4    to pull more heat out of the fuel.
 5              DR. KRESS:  Of course, yes.
 6              DR. SEALE:  And that's getting you back up into
 7    the range of the forced circulation PWRs.
 8              DR. KRESS:  Of course, this will be part of the
 9    later review.  This is incidental.
10              DR. SEALE:  I appreciate that.
11              DR. KRESS:  This is incidental to this particular
12    review.
13              MR. WILSON:  That's correct.
14              DR. WALLIS:  The last slide, presumably, this also
15    goes along with changes in the core makeup tank sizes and
16    the water storage tank, injection water storage tank.  All
17    of those other things, most presumably get bigger.
18              MR. WILSON:  Yes, sir.  As you recall, there was a
19    tank up on --
20              DR. WALLIS:  All kinds of things get bigger.
21              MR. WILSON:  -- top of containment and there was
22    an assumption that that was seven days --
23              DR. WALLIS:  So many things get bigger besides
24    just the list you have here.
25              MR. WILSON:  Yes.  There's a lot of other things.
.                                                               184
 1              MR. LEITCH:  I also notice, not on your slide, but
 2    on the handout that we got previously, that hot leg
 3    temperature is increasing from 600 to 615 degrees.  Is there
 4    experience operating -- I suppose it's Inconel 690 tubing at
 5    615 degrees?
 6              MR. WILSON:  I don't know.
 7              MR. LEITCH:  That's just a curiosity.  All those
 8    questions will come later.
 9              MR. WILSON:  Yes.
10              DR. SEALE:  Other people have had problems with
11    605, though.
12              MR. LEITCH:  Yes.  Yes.  615 seems a little --
13              DR. SEALE:  Ambitious.
14              MR. LEITCH:  -- on the high side, to me.
15              MR. WILSON:  Earlier, Dr. Kress had mentioned
16    there were five assumptions that Westinghouse had made and
17    those form the basis for how they see the application going
18    forward.  I've listed them here in this slide.
19              First of all, Westinghouse believes that
20    approximately 80 percent of the information that was
21    certified in AP600 could come forward and be part of the
22    AP1000 application with no change, except changing the name
23    from AP600 to AP1000, and, therefore, the staff would not
24    have to re-review that information.
25              DR. POWERS:  My suspicion is that if I went
.                                                               185
 1    through and did a count, and I haven't, that 80 percent is
 2    about right, but if I weighed it for the areas that provoke
 3    some controversy and took some substantial amount of
 4    discussion, I wouldn't come up with the same percentage.
 5              MR. WILSON:  You're correct.  That 80 percent is
 6    volume of the application.  Also, Westinghouse believes that
 7    the testing that they did for AP600 would be sufficient to
 8    support an application for AP1000, so that there would be no
 9    need for further testing.
10              DR. KRESS:  Now, when they say that, do they --
11    they don't imply that their scaling analysis is still valid,
12    do they?  It's not part of that.  That's not an implication
13    of that.
14              MR. WILSON:  No.  That they would have to provide
15    -- and we addressed that in our letter back and they've also
16    acknowledged that, that they are going to have to do further
17    scaling to demonstrate that.
18              Also, they plan to use the analytical codes from
19    AP600, with minor modifications for the AP1000 review.  They
20    claim that a portion of the level one PRA would not have to
21    be redone, and they want to defer selective design
22    activities.
23              And what this gets at is that when we did the
24    AP600 review, Westinghouse did the structural design,
25    seismic analysis, and piping design.  What they're proposing
.                                                               186
 1    for the AP1000 is to use design acceptance criteria for
 2    those three areas rather than actual design information.
 3              Now, this is a policy matter.  As some members
 4    know, the Commission allowed use of design acceptance
 5    criteria in certain areas for the ABWR and System 80+ and
 6    AP600 designs, but this is breaking new ground and the staff
 7    ought to look at that and we would make a recommendation to
 8    the Commission on that and the Commission would have to
 9    decide.
10              DR. KRESS:  I think from the standpoint of the
11    ACRS, that we probably ought to focus on the second, third
12    and fourth bullets up there.
13              MR. WILSON:  Let me get back to that point a
14    little bit later in the presentation.
15              And, finally, Westinghouse had said that they plan
16    to use the same codes and standards for AP600, for AP1000 as
17    they did for AP600, with some limited exceptions that they
18    would notify us about.
19              And with that, Westinghouse came in and met with
20    the staff and asked for a pre-application review to
21    determine scope and cost.  Now, this is not a typical
22    pre-application review assessment he staff has done in the
23    past.  Normally, when we say pre-application review, we have
24    an application in hand and the staff is making a
25    determination as to whether it's sufficiently complete to
.                                                               187
 1    proceed to the actual review.
 2              In this particular case, Westinghouse is asking
 3    us, well, if we did do the review, what would it cost us,
 4    what would be the scope of that review.
 5              So this is much different.  It's the first time,
 6    to my recollection, we've done something like that.
 7              So we agreed, Mr. Collins, the Director of NRR,
 8    agreed to proceed in kind of a two-step process, which, by
 9    the way, Westinghouse will be billed for this effort.  So
10    Westinghouse requested to start phase one on May 4 and then
11    on May 31, they sent in a letter identifying the issues that
12    they think need to be evaluated to make this determination
13    as to what the scope of an actual review would be, and those
14    are the issues we just went through.
15              And then, a surprise, as you mentioned, the ACRS
16    sent a letter on phase one.  I want to thank the committee
17    for that.  In my 25 years here at the NRC, it's the first
18    time I've received a letter on one of my projects without
19    asking.  Always something new.
20              DR. SEALE:  It shows interest and concern.
21              MR. WILSON:  Thank you very much.  And the staff
22    reviewed Westinghouse's letter and the ACRS letter and we
23    sent back our results of the phase one effort in a letter
24    dated July 27, which I believe the committee has seen, where
25    we addressed those issues, the information we believe we
.                                                               188
 1    need in order to evaluate those issues, and estimates of
 2    staff effort to evaluate those issues.
 3              And I will say right now it was very difficult and
 4    you should understand there's a lot of uncertainty with
 5    those estimates.
 6              The staff is good at identifying safety issues and
 7    evaluating safety issues, but we're not very good at
 8    estimating how much effort it will take to resolve them.  So
 9    it's just an estimate.
10              In that letter, we told Westinghouse that if we're
11    going to proceed to phase two, you need to let us know,
12    first of all, and, second of all, you need to provide us the
13    information to prioritize that effort.
14              Our situation is that the pre-application review
15    is not budgeted in our budget and if we decide to add this
16    work on, we're going to have to do some prioritization
17    effort.
18              So Westinghouse has just sent in a letter, it's
19    dated yesterday, and they've asked us to proceed with phase
20    two and they have identified the issues that they have
21    decided to proceed with.
22              So as you may recall from the NRC's letter, we
23    provided estimates in a rather detailed breakdown, with the
24    idea being that it's a menu and Westinghouse can decide on
25    which issues they wish to proceed on.
.                                                               189
 1              So what Westinghouse has told us is that they want
 2    to proceed on codes and testing, as you might imagine, this
 3    is not an important issue in terms of the scope of review,
 4    but long lead time, depending on the outcome.
 5              They also want us to proceed on this issue of
 6    getting okay on use of design acceptance criteria rather
 7    than detailed design information in the areas of piping,
 8    structural design and seismic analysis.  And, finally, this
 9    issue that I referred to in the letter as exemptions, which
10    primarily deals with the use of the same codes on AP1000
11    that we used in AP600.
12              So those are the four areas that Westinghouse has
13    asked us to proceed with.
14              DR. KRESS:  It's interesting they left off the
15    PRA.
16              MR. WILSON:  Well, in the PRA, they were only
17    making the claim that a portion of it could be used.  They
18    acknowledged that parts of level one would have to be
19    requantified and all of level two would have to be redone,
20    and so the gain was rather small and from the staff's
21    perspective, what we would have to go through to come to
22    agreement was a significant effort.
23              So from my perspective, it wasn't cost beneficial
24    to investigate this area.  So I would see the whole PRA
25    review being deferred to phase three.
.                                                               190
 1              DR. KRESS:  I see.
 2              MR. WILSON:  That's what I think will happen.  On
 3    the first item, on the actual volume of the application,
 4    Westinghouse is still interested in getting agreement on
 5    that, but for cost reasons, they are going to defer that
 6    till later on.
 7              So the question is now before NRR and the
 8    executive team in NRR will be meeting here in the near
 9    future and making a determination as to whether we can add
10    this to our workload.
11              What does that mean to ACRS?  Well, if they decide
12    to proceed and do phase two in fiscal year 2001, staff would
13    initiate its review, notify the ACRS that we are doing that,
14    and make a request for both a subcommittee and a full
15    committee meeting with ACRS.  We would want ACRS' views on
16    our results or, more specifically, our conclusions on these
17    four issues.
18              Our intent is to also seek agreement with the
19    Commission before we officially respond to Westinghouse. 
20    Once again, this is all based on an assumption if we
21    proceed, and that's going to be determined and it's going to
22    be determined on our budget and priorities of our workload.
23              And if we proceed and answer those questions, then
24    Westinghouse will make a determination as to whether they
25    will actually come in with a design certification
.                                                               191
 1    application.
 2              DR. KRESS:  At this point, you haven't established
 3    a position on these four issue assumptions.  You've just
 4    told them what information you think you need in order to
 5    make that assessment.
 6              MR. WILSON:  I would say that we agree that these
 7    are the appropriate issues.
 8              DR. KRESS:  You agree that those are the
 9    appropriate issues.
10              MR. WILSON:  Issues that need to be evaluated to
11    determine the scope.
12              And with that, I'm available for questions.
13              DR. SEALE:  As I recall, that letter, there were
14    some comments with regard to the containment that was in the
15    letter we sent to you, but I guess that's later down the
16    road that they want to get into that.
17              MR. WILSON:  That's correct.  We reviewed your
18    letter and we felt that the issues identified by
19    Westinghouse were sufficient to make the phase two
20    determination.  One of the items that ACRS identified, I
21    don't think there's any dispute with either Westinghouse or
22    the staff that these need to be evaluated, but many of them
23    would come up in the actual design certification review.
24              And I would note, and I know the committee hasn't
25    had a chance to see this letter, because it just came in the
.                                                               192
 1    door, but I've skimmed it and in the letter, Westinghouse
 2    identifies the --addresses the items that ACRS has
 3    identified and states which phase of the review they plan to
 4    address those issues.
 5              DR. SEALE:  There is one aspect that troubles me
 6    and that is that the implication is, in the way that it's
 7    phrased, that somehow you are committing yourself to a
 8    position on some pretty crucial questions, particularly the
 9    adequacy of the current test base, before we go through and
10    do the full examination of what the design is going to look
11    like.
12              And certainly some of the problems we had with the
13    600 megawatt containment shell are in spades when you go to
14    1000.  It's bigger, the concerns about stratification and
15    those other things are at least as serious and perhaps more,
16    and so I guess my concern is any commitment like that is a
17    tentative one only and I assume everybody understands that.
18              MR. WILSON:  Yes.  I share your concerns.  I
19    believe the staff recognizes it's going to be a difficult
20    evaluation.  It's an important one, from Westinghouse's
21    perspective, though, and so --
22              DR. SEALE:  Sure.
23              MR. WILSON:  So the staff is assuming that, if
24    workload permits us to proceed, we're going to look
25    carefully at this.  And while this hasn't been determined by
.                                                               193
 1    the staff, I suspect that we would have some sort of a
 2    qualification.
 3              But in order to address Westinghouse's request,
 4    we, both the staff and ACRS, should try to give the best
 5    answer we can given the information they provide and based
 6    on that, if new information surfaces that Westinghouse
 7    didn't provide us in phase two that we learn during the
 8    actual review, well, then that reopens the question.
 9              DR. SEALE:  Okay.
10              MR. WILSON:  I think that's how you have to couch
11    it.
12              DR. BONACA:  In the past, Westinghouse and also
13    the other vendors went through this kind of upgrades of
14    power plants, comprehensive changes for the existing plants. 
15    They went from certain designs to an expanded design.
16              Are you looking at ones that went through those
17    changes?  I remember, at that time, they identified, the NRC
18    identified the most important issues that were being raised
19    by changing the size and the power out of the plant.
20              I would expect a lot of those kind of inputs or
21    assessments would be applicable to this effort.  Am I
22    correct?  There's a lot of history behind power -- upgrades
23    of power plants.
24              MR. WILSON:  Yes, but the power up-rates I'm
25    familiar with are --
.                                                               194
 1              DR. BONACA:  Well, I'm not talking about rates. 
 2    I'm talking about where you're changing really the design
 3    here, going from 600 megawatt electric, which is the
 4    original design that Westinghouse use to have, for example,
 5    for Connecticut Yankee, to a Seabrook design that is 1100. 
 6    There was an item by item comparison being made of all those
 7    issues and which ones -- experience put out which ones were
 8    the most important or the ones that were missed and were
 9    very important.
10              MR. GRIMES:  Dr. Bonaca, I will try to address
11    that, because I recall that time.  I would argue that the
12    process that we went through when we made the transition
13    from what we now call the middle aged plants to the newer
14    vintages was basically the same process that Jerry described
15    that we've gone through here in terms of reflecting on the
16    most recent technology that we have in the AP600 safety
17    evaluation and how we would extrapolate that knowledge base.
18              In those days, what we did was we reflected on the
19    strength of the standard review plan that was relatively new
20    at that time and we determined whether or not we were
21    comfortable that we had the right standard review plan
22    approach for the larger newer plants.
23              DR. BONACA:  I just was asking if that review that
24    you're quoting now would in any way help to look at this
25    right now, to understand what are the areas where you should
.                                                               195
 1    focus the most.
 2              MR. GRIMES:  If there was some kind of checklist
 3    or record that explained the logic that we went through to
 4    review the standard review plan, unfortunately, I've
 5    discovered that we spend more time going back trying to find
 6    the records than we do resurrecting the corporate knowledge,
 7    in some cases anyhow.
 8              DR. BONACA:  I'm saying there are some issues that
 9    were important at that time that turned out to be no issues. 
10    Some other issues that were not viewed as important turned
11    out to be big issues and I think there is some lessons
12    learned there that one might -- and I just was wondering if
13    you were looking for those and if they would help you in any
14    way.
15              That's all I was suggesting.
16              MR. WILSON:  We haven't gone back and done that.
17              DR. KRESS:  One of the items I'm particularly
18    interested in, one of the issue items, is the use of the
19    codes, the NOTRA and the other codes that they use in the
20    deterministic analysis.
21              The thing I would be interested in is clearly this
22    kind of power up-rate of this magnitude with the changes
23    that are being made in the design of the core and the
24    systems is going to result in decreasing the margins, these
25    Chapter 15 type margins.
.                                                               196
 1              The question I would have is you've got these
 2    codes that are usually based on Appendix K like analysis,
 3    that have built-in conservatisms and built-in biases, but
 4    how will you know, using those, when you've eaten up too
 5    much of your margin with respect to the figures of merit?
 6              How will you make that determination in a review? 
 7    This is not a question of whether the codes are applicable
 8    or not, but how would you make a determination that those
 9    codes, using those codes, you still haven't eroded your
10    margins too far?
11              MR. WILSON:  It's a judgment issue and I'm sure
12    that the staff is going to have to consider that and be
13    ready to discuss it with the committee when we come back
14    with our conclusions.
15              I know, in skimming Westinghouse's letter on phase
16    two, that they plan to address both the adequacy of using
17    the code and margins discussion.
18              DR. KRESS:  Are there any other questions that
19    members have?
20              DR. POWERS:  On this area of codes, I've known a
21    couple of code builders in my lifetime.
22              DR. KRESS:  You certainly have.
23              DR. POWERS:  And codes are never static.  So when
24    they say we're going to use the same codes, with limited
25    modifications, do we know what that means?  Typically, these
.                                                               197
 1    codes are always -- I mean, they've gone to modifications
 2    now in the two and three decimal point range.
 3              Would they really be using exactly the same code
 4    that they used for AP600?
 5              MR. WILSON:  I understand the question you're
 6    asking, and we don't know that yet.  I think until they make
 7    their submittals, we'll know that level of detail.
 8              What Westinghouse is proposing is that the
 9    information they feel is sufficient for us to make that
10    evaluation, they will have that available by the first of
11    November.
12              DR. POWERS:  The other question that comes up is
13    that the NRC itself did some experimental work in connection
14    with its review of the AP600, notably some work done at the
15    ROSA facility.
16              I was in a briefing on the status of the research
17    program a couple of weeks ago and the speaker from RES stood
18    up and listed down all of the experimental facilities that
19    they no longer had access to now and the ones that he
20    anticipated they would not have access to in the near
21    future.
22              One of those was the ROSA facility.  But are we
23    confident that as part of this phase two process, do you
24    interact with the RES people to see if they feel like they
25    could use whatever data they got from the ROSA facility for
.                                                               198
 1    evaluating a 1000 or do they feel they would have to do
 2    additional experiments?
 3              MR. WILSON:  I don't think we'll be ready to
 4    determine that until we see Westinghouse's proposal.
 5              DR. KRESS:  We think that will involve some sort
 6    of new scaling analysis, at least a scaling to the 1000.
 7              MR. GRIMES:  If I could offer this.  I would
 8    expect that we would want to fully engage the research staff
 9    in phase two in assisting us in determining what the needs
10    are going to be based on their advice.
11              So I would expect that they would be involved to
12    the extent that they give us feedback that suggests that
13    there may be a need for additional -- in their view,
14    additional testing, then we need to have a dialogue with
15    Westinghouse to find out whether they agree or disagree and
16    if so, who is going to do it and those sorts of things.
17              DR. POWERS:  But it will happen.
18              MR. GRIMES:  Yes.
19              DR. POWERS:  And it's something not to put off,
20    because I think decisions are being made on the retirement
21    of facilities left and right, right now.  And NRC no longer
22    makes -- NRC itself doesn't make the decision anymore.  It's
23    in the hands of other people.
24              DR. KRESS:  The codes we're talking about, NOTRA,
25    COBRA TRAC, LOFTRAN and WGOTHIC, I think, as best I
.                                                               199
 1    remember.
 2              The LOFTRAN is a neutronics code and I don't see
 3    how they can get this power upgrade without increasing the
 4    enrichment.  Has that been thought about yet?  I haven't
 5    seen what their full proposal is to get their power up-rate,
 6    but I can't see how they can do it without enriching --
 7    increasing their enrichment, and I worry a little bit about
 8    --
 9              MR. WILSON:  Staff doesn't have that level of
10    information yet.
11              DR. KRESS:  You don't have that detail either yet. 
12    That's something for later, I guess.
13              MR. WILSON:  Yes.
14              DR. POWERS:  It seems to me, enrichment, I think,
15    bothers me less than the issues of going to higher burn-up,
16    which I don't think we recognized so fully when we did 600.
17              Now we understand that not only enrichments of 62
18    gigawatt days -- I mean, burn-ups of 62 gigawatt days per
19    ton are possible, but we have to think in terms of 75 as a
20    possibility on that, and those things -- that seems like a
21    bigger stretch for existing codes than just the enrichment
22    issues, as long as you stay below five percent.
23              DR. KRESS:  I'm not even sure they could stay
24    below five percent and get the up-rate.  That's why it was
25    bothering me, because our database is five percent.
.                                                               200
 1              DR. SEALE:  But the linear heat rating is no
 2    higher than it is in some of the forced convection PWRs. 
 3    And so the product of enrichment times flux is comparable. 
 4    That's what the linear heat rating is.
 5              DR. KRESS:  Of course.
 6              DR. SEALE:  So that's not the problem.  The
 7    problem, it strikes me anyway, is whether you can get 20
 8    percent more heat out of those fuel bundles with a natural
 9    circulation --
10              DR. POWERS:  Bigger driving force, Bob.
11              DR. KRESS:  That will be one of the issues, of
12    course.
13              MR. GRIMES:  I would like to point out the nature
14    of your dialogue illustrates the extent to which the staff
15    is put into a position of trying to make an assessment about
16    whether or not we have a good enough idea about what's going
17    to be involved in the review to start it with a reasonable
18    expectation of the projected level of effort and impact on
19    resources, but not get into so much detail that we actually
20    perform the review itself.
21              Obviously, Westinghouse has come to a conclusion
22    that they can squeeze enough heat out of a core that's two
23    feet longer and still maintain some semblance of the design
24    advantages of the AP600, that they've got a marketing
25    strategy that says they should get a return on that
.                                                               201
 1    investment.
 2              So we will be very interested to explore some of
 3    these details, but we're going to have to leave some of that
 4    to phase three.  Otherwise, we won't have anything left to
 5    charge them for.
 6              DR. POWERS:  So you have your own marketing
 7    strategy here.
 8              DR. SEALE:  The thing that bothers me is that I --
 9    and you've made it clear, that any promises are conditional
10    in the sense that if it's necessary to do some testing,
11    presumably that can be -- I mean, they can make the decision
12    at that time.
13              But it's hard when -- if they get into this thing
14    on the basis of one assumption and then partway down the
15    road, after you've done some of these analyses, you suddenly
16    decide they do need something else.
17              DR. KRESS:  I think that's a chance they take.
18              DR. SEALE:  And I guess, you know, they're big
19    boys and -- but on the other hand, I hope they're not
20    unrealistic.
21              DR. UHRIG:  I was just going to comment that I
22    thought the testing was paid for by NRC, the ROSA facility. 
23    Am I correct on that?
24              DR. KRESS:  The ROSA was, but it's not likely that
25    will be redone.
.                                                               202
 1              DR. POWERS:  I mean testing paid for by the NRC
 2    has a strange --
 3              DR. UHRIG:  Well, it came out of the research
 4    budget, I should say.
 5              DR. POWERS:  But in the end, that comes out of --
 6              DR. KRESS:  It comes out of the industry.
 7              DR. POWERS:  -- Westinghouse's hide here
 8    someplace.
 9              DR. KRESS:  Somehow or other, yes.
10              DR. UHRIG:  Well, it came out of the industry
11    side.
12              DR. BONACA:  I just have a question.  I have not
13    been part of the certification of AP600, so I confess
14    ignorance about the specifics of that.  Testing for AP600,
15    what specific portion was it?  Was it containment and the
16    passive systems?
17              DR. KRESS:  They had a combination of all those,
18    passive systems, containment, the primary system and two
19    different facilities and the NRC had one and the other one.
20              It's a complicated -- it's a pretty extensive test
21    program.
22              DR. UHRIG:  They also tested the ECCS system, the
23    passive system.
24              DR. BONACA:  So the core design was a pretty
25    radical departure from the one we know for --
.                                                               203
 1              DR. KRESS:  It wasn't a real radical departure
 2    from a normal core.
 3              DR. BONACA:  Going back, I wonder how much of this
 4    core that is 14 feet high, as the Texas Project, is
 5    different from that project, I really wonder.
 6              DR. SEALE:  We don't know yet.
 7              DR. BONACA:  So how much of that they will rely
 8    on, whether they will call it proven.
 9              DR. KRESS:  I guess that remains to be seen.
10              DR. POWERS:  What you, I think, safely predict is
11    that it's not going to be something radical.  I mean, I
12    don't think we're talking about fluted rods here and things
13    like that.
14              DR. KRESS:  No, no, no.  It will be the same.
15              DR. BONACA:  I would say that, for example, 615
16    degrees seems high and I wouldn't expect that temperature at
17    the Texas Project.
18              So what other features may be -- all the fuel, for
19    example, they were able to pull out a lot of power from
20    pretty aggressive designs for core implants by having the
21    integral mixers and getting a lot of D&B margin on those and
22    I wonder how much of that they'll rely on for this.  It will
23    be interesting to know --
24              DR. KRESS:  That would be interesting.
25              DR. BONACA:  -- if that would facilitate the
.                                                               204
 1    review.
 2              DR. KRESS:  We will be interested in continuing
 3    this interaction and dialogue on this.  Are you looking for
 4    a letter form us on this phase one part?
 5              MR. WILSON:  I believe that we have, in effect,
 6    received the committee's views on phase one, from the NRC
 7    staff's perspective, that was sufficient.  So it's up to you
 8    whether you want to write another letter or not, but we
 9    don't need one.
10    DR. KRESS:  We are generally reluctant to comment on things
11    like schedules and scope and dollars, but if we have
12    comments about or feelings about the five assumptions, would
13    that be of use to you if we commented on those?
14              MR. WILSON:  Yes.
15              MR. GRIMES:  I would like to specifically ask that
16    -- understand that we are interested in what particular
17    technical issues you feel might be troublesome during the
18    phase three review and your challenges, to see whether or
19    not you can characterize the nature of the issues and how
20    they need to be addressed in such a way as to not intimidate
21    Westinghouse from wanting to pursue phase three.
22              DR. KRESS:  Don't want to discourage them.
23              DR. WALLIS:  Can I ask about the codes?  We had
24    some problems with code documentation in AP600.  And even if
25    the results are believable when you look at the experiments,
.                                                               205
 1    there is a credibility issue when the code documentation is
 2    not impressive, let's say.
 3              I just don't know how much we're going to go into
 4    that issue with AP1000.
 5              MR. WILSON:  At the phase two review, determining
 6    whether or not those codes are acceptable for use in doing
 7    the actual analyses, I suspect we won't get into
 8    documentation very much.  But if we proceeded to design
 9    certification, I would assume we would get into that issue.
10              DR. WALLIS:  That's what bothered me with AP600,
11    is we went through all these phases and at the very end of
12    the process, decided to look into the details of the
13    documentation and this gave some of us some qualms.
14              That shouldn't wait till the end.
15              DR. POWERS:  I think Graham has hit upon one thing
16    that you do want to bear in mind, maybe attach it as a
17    codicil under estimates that you're giving Westinghouse, is
18    it really does hinge on having a good quality application
19    and that's the documentation in the application.  And
20    certainly I think this committee spent a lot of time, a lot
21    of its time with -- was delayed in the last one because of
22    documentation issues.
23              To the extent that they can --
24              MR. WILSON:  From the staff's perspective, quality
25    documentation effects the length and cost of our review.
.                                                               206
 1              DR. POWERS:  That's right.
 2              DR. SEALE:  From the point of view of -- the one
 3    thing that could help the most that's pure paper product and
 4    hence probably the easiest thing to get at this stage, if
 5    you guys -- if they could really nail it on the scaling
 6    analysis, so we don't go through this agony we went through
 7    on the AP600, but really tie it down, it strikes me that
 8    would probably be the most constructive thing you could do
 9    early on to resolve all of these questions about the codes,
10    utility of tests and everything else.
11              MR. WILSON:  Well, they're going to have to, in
12    your words, really nail it in order to persuade the staff
13    that no further testing is necessary.
14              DR. KRESS:  I guess we'll turn it back to you, Mr.
15    Chairman.
16              DR. POWERS:  Thank you.  It's always exciting to
17    see new plants coming out.  I was excited about that.
18              At this point, I think we can dispense with the
19    transcription.
20              [Whereupon, at 2:40 p.m., the recorded portion of
21    the meeting was concluded.]
22
23
24
25

 

Page Last Reviewed/Updated Tuesday, July 12, 2016