Limerick Generating Station, Units 1 and 2 – License Renewal Application

Photo of Limerick Generating  Station, Units 1 and 2

On this page:

Application Information:

To top of page

License Renewal Review Schedule*

*These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.

To top of page

Milestones Schedule Date Actual Date
Receive license renewal application (LRA) 06/22/11 06/22/11
Publish Federal Register Notice (FRN) – LRA availability 07/2011 07/26/11
Publish FRN – acceptance/rejection and opportunity for hearing 08/2011 08/24/11
Publish FRN – environmental scoping meeting 08/2011 08/26/11
Public Meeting – License Renewal Overview and Environmental Scoping meeting 09/22/11 09/22/11
Audit – Scoping & Screening Methodology 09/19-23/11 09/19-23/11
Deadline for filing hearing requests and petitions for intervention 10/24/11 10/24/11*
Environmental scoping period ends 10/28/11 10/28/11
Audit – Aging Management Programs 10/03-14/11 10/03-14/11
Audit – Environmental 11/07-10/11 11/07-10/11
Inspection – Regional TBD  
Issue safety evaluation report (SER) with open items 07/2012  
Issue draft supplemental environmental impact statement (SEIS) 08/2012  
Publish FRN – draft SEIS available for comments 08/2012  
Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting 09/2012  
Public Meeting – draft SEIS meeting 09/2012  
End of draft SEIS comment period 10/2012  
Issue final SER 01/2013  
ACRS full committee meeting 02/2013  
Issue final SEIS 02/2013  
U.S. Environmental Protection Agency FRN Published – availability of final SEIS 03/2013  
Decision – Director, NRR (22 months if no hearing) 04/2013  

*Extended to 11/22/2011 for the Natural Resources Defense Council per Order of the Secretary of the Commission.

To top of page

Project Managers for Limerick

Limerick Generating Station, Units 1 and 2 PMs
License Renewal (Safety) Robert Kuntz
License Renewal (Environmental) Leslie Perkins
Lead Power Plant Rick Ennis

To top of page