Limerick Generating Station, Units 1 and 2 – License Renewal Application

On this page:
- Application Information
- License Renewal Review Schedule
- Project Managers for Limerick Generating Station, Units 1 and 2
Application Information:
License Renewal Review Schedule*
*These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.
| Milestones | Schedule Date | Actual Date |
|---|---|---|
| Receive license renewal application (LRA) | 06/22/11 | 06/22/11 |
| Publish Federal Register Notice (FRN) – LRA availability | 07/2011 | 07/26/11 |
| Publish FRN – acceptance/rejection and opportunity for hearing | 08/2011 | 08/24/11 |
| Publish FRN – environmental scoping meeting | 08/2011 | 08/26/11 |
| Public Meeting – License Renewal Overview and Environmental Scoping meeting | 09/22/11 | 09/22/11 |
| Audit – Scoping & Screening Methodology | 09/19-23/11 | 09/19-23/11 |
| Deadline for filing hearing requests and petitions for intervention | 10/24/11 | 10/24/11* |
| Environmental scoping period ends | 10/28/11 | 10/28/11 |
| Audit – Aging Management Programs | 10/03-14/11 | 10/03-14/11 |
| Audit – Environmental | 11/07-10/11 | 11/07-10/11 |
| Inspection – Regional | TBD | |
| Issue safety evaluation report (SER) with open items | 07/2012 | |
| Issue draft supplemental environmental impact statement (SEIS) | 08/2012 | |
| Publish FRN – draft SEIS available for comments | 08/2012 | |
| Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting | 09/2012 | |
| Public Meeting – draft SEIS meeting | 09/2012 | |
| End of draft SEIS comment period | 10/2012 | |
| Issue final SER | 01/2013 | |
| ACRS full committee meeting | 02/2013 | |
| Issue final SEIS | 02/2013 | |
| U.S. Environmental Protection Agency FRN Published – availability of final SEIS | 03/2013 | |
| Decision – Director, NRR (22 months if no hearing) | 04/2013 |
*Extended to 11/22/2011 for the Natural Resources Defense Council per Order of the Secretary of the Commission.
Project Managers for Limerick
| Limerick Generating Station, Units 1 and 2 PMs | |
|---|---|
| License Renewal (Safety) | Robert Kuntz |
| License Renewal (Environmental) | Leslie Perkins |
| Lead Power Plant | Rick Ennis |
Page Last Reviewed/Updated Thursday, April 19, 2012