U.S. EPR Application Review Schedule
The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the design certification application for the U.S. EPR.
Key Milestones |
Completion Date
Actual - A
Target (Rev 5) - T |
Application |
Received design certification application |
12/11/07 - A |
|
Acceptance Review |
Federal Register Notice (FRN) published for receipt and availability |
01/02/08 - A |
FRN published announcing acceptance |
02/25/08 - A |
Review schedule published (through Phase 6) |
03/26/08 - A |
|
Safety Review |
Suspended |
Phase 1 - Preliminary Safety Evaluation Report (SER) with Requests for Additional Information (RAIs) issued to applicant |
01/28/09 - A |
Phase 2 - SER with Open Items issued |
02/09/12 - A |
Phase 3 - Response to ACRS regarding SER with Open Items issued |
05/18/12 - A |
Phase 4 - Advanced SER with no Open Items issued |
|
Group A
|
09/30/14 - A |
Group B
|
TBD |
Group C
|
TBD |
Phase 5 - Response to ACRS regarding SER with no Open Items issued |
|
Phase 6 - Final SER issued |
TBD |
|
Rulemaking |
Issue proposed rule |
|
Issue final draft rule |
TBD |
Issue final rule |
|