Application Review Schedule for the Combined License Application for Turkey Point, Units 6 and 7

The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Florida Power and Light Company (FPL) submitted to obtain a combined license (COL) for two Westinghouse Advanced Passive 1000 (AP1000) pressurized-water reactors (PWRs) designated as Turkey Point, Units 6 and 7.

Key Milestones Completion Date
Actual - A
Target - T
Application Tendered 06/30/09 - A
Acceptance Review
Acceptance Review Start
06/30/09 - A
Docketing Decision Letter Issued/Acceptance Review Complete
09/04/09 - A
Review Schedule Established/Schedule Letter Issued to Applicant
05/28/10 - A
Safety Review
Phase A - Requests for Additional Information (RAIs) and Supplemental RAIs
06/30/15 - T
Phase B - Advance Final safety evaluation report (SER) without Open Items
01/29/16 - T
Phase C - ACRS Review of Advance Final SER
05/30/16 - T
Phase D - Final SER
10/31/16 - T
Environmental Review
Phase 1 - Environmental impact statement (EIS) scoping summary report issued
12/10 - A
Phase 2 - Draft EIS issued to EPA
February 2015 - T
Phase 3 - Final EIS issued to EPA
February 2016 - T
Hearing
Commission or ASLB hold mandatory hearing
Schedule Under
Review
License
Commission decision on issuance of COL application
 

Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.