Application Review Schedule for the Combined License Application for Shearon Harris Nuclear Site, Units 2 and 3
The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Progress Energy Carolinas, Inc. (PEC) submitted to obtain a combined license (COL) for two Westinghouse Advanced Passive 1000 (AP1000) pressurized-water reactors (PWRs) designated as Shearon Harris Nuclear Site, Units 2 and 3.
Detailed Review Schedule for COL Application: The schedule for the Westinghouse design certification amendment is currently under review. The design certification amendment schedule will affect the Shearon Harris SCOL combined license schedule for dependent sections such as Advanced SER with No Open Items, ACRS Review and Final SER Issuance. The posted Shearon Harris SCOL schedule does not currently reflect the necessary changes and will be updated after the Westinghouse schedule is revised.
| Key Milestones | Completion Date Actual - A Target - T |
|---|---|
| Application Tendered | 02/19/08 - A |
| Acceptance Review | |
Acceptance Review Start |
02/20/08 - A |
Docketing Decision Letter Issued/Acceptance
Review Complete |
04/17/08 - A |
Review Schedule Established/Schedule
Letter Issued to Applicant |
05/16/08 - A |
| Safety Review | |
Phase A - Requests for Additional Information
(RAIs) Issued to Applicant (Formerly Phases 1, 2, and 3) |
04/20/10 - A |
Phase B - Advanced Final Safety Evaluation
Report (SER) without Open Items (Formerly Phase 4) |
04/13 - T* |
Phase C - ACRS Review of Advanced Final
SER (Formerly Phase 5) |
07/13 - T* |
Phase D - Final SER (Formerly Phase 6) |
09/13 - T* |
| Environmental Review | |
Phase 1 - Environmental impact statement
(EIS) summary report issued |
11/18/08 - A |
Phase 2 - Draft EIS issued to EPA |
01/13 - T |
Phase 3 - Response to public comments
on draft EIS completed |
06/13 - T |
Phase 4 - Final EIS issued to EPA |
01/14 - T |
| Hearing | |
Commission or ASLB hold mandatory hearing |
|
| License | |
Commission decision on issuance of
COL application |
|
* Dates do not yet reflect the recent changes to the Westinghouse and Vogtle (reference COL) review schedules.
Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.