Combined License Application Documents for Shearon Harris Nuclear Site, Units 2 and 3 Application

The U.S. Nuclear Regulatory Commission (NRC) considers public involvement in, and information about, our activities to be a cornerstone of strong, fair regulation of the nuclear industry. As such, the NRC believes that nuclear regulation should be transacted as openly and candidly as possible to maintain and enhance the public's confidence. Ensuring appropriate openness explicitly recognizes that the public must be informed about, and have a reasonable opportunity to participate meaningfully in, the NRC's regulatory processes. Toward that end, this page provides access to documents and correspondence related to the application that Progress Energy Carolinas, Inc. (PEC) submitted to obtain a combined license (COL) for two Westinghouse Advanced Passive 1000 (AP1000) pressurized-water reactors (PWRs) designated as Shearon Harris Nuclear Site, Units 2 & 3:

On this page:

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Reference Documents

In accordance with Title 10, Part 52, of the Code of Federal Regulations (10 CFR Part 52), "Licenses, Certifications, and Approvals for Nuclear Power Plants," a COL application may reference a standard design certification, an early site permit, both, or neither. Many COL applications have referenced an application for design certification, in accordance with 10 CFR 52.55(c). On that basis, PEC referenced Westinghouse's application to amend the AP1000 standard design certification and cited the following amended design control document (DCD) in its COL original application for Shearon Harris Nuclear Site, Units 2 & 3:

In Revision 1 to the Shearon Harris Units 2 and 3 COL application dated June 23, 2009 PEC updated the application to reflect that its application now incorporates by reference AP1000 DCD Revision 17.

To top of page

Application

The following table provides access to the COL Application that PEC submitted for Shearon Harris Nuclear Site, Units 2 & 3.

Some combined license applications were submitted with hyperlinks to various reference documents. Currently, the hyperlinks in those applications are not active. These hyperlinks represent an advanced feature that could be activated when the agency upgrades to web-based ADAMS, at which point these applications and documents such as the Final Safety Analysis Report and associated Technical/Topical Reports would be linked together. In the interim, and for those applications that do not have the hyperlink feature, the reference documents may be viewed under the Reference Documents section of the combined license application page. In addition, DVDs of the various documents are available by contacting the Public Document Room staff.

Part Description Revision
0 Cover Letter, Affidavits, etc Rev. 5*
Rev. 4
Rev. 3
Rev. 2
Rev. 1
Rev. 0
1 Administrative and Financial Information Rev. 2
Rev. 1
Rev. 0
2 Final Safety Analysis Report (FSAR) Rev. 4
Rev. 3
Rev. 2
Rev. 1
Rev. 0
3 Environmental Report Rev. 3
Rev. 2
Rev. 1
Rev. 0
4 Technical Specifications Rev. 3
Rev. 2
Rev. 1
Rev. 0
5 Emergency Plan Rev. 3
Rev. 2
Rev. 1
Rev. 0
6 Limited Work Authorization (LWA) [Not used. Reserved for applicants requesting.] Rev. 0
7 Departures and Exemption Requests Rev. 3
Rev. 2
Rev. 1
Rev. 0
8 [This Part contains safeguards information which is withheld from public availability]  
9 [This Part contains other information which is withheld from public availability]  
10 License Conditions and Inspection, Tests, Analyses and Acceptance Criteria (ITAAC) Rev. 5
Rev. 2
Rev. 1
Rev. 0
11 Quality Assurance Program Rev. 5

* A "roadmap" providing a discussion of the Revision 5 changes to the application was provided in a Progress Energy letter dated April 19, 2013.

To top of page

Applicant Documents

This section lists, in chronological order, the years in which PEC submitted documents to support the U.S. Nuclear Regulatory Commission (NRC) staff's review of PEC's application to obtain a combined license (COL) for Shearon Harris Nuclear Site, Units 2 & 3. You may click on a year in the list below to see a listing of the documents that were submitted in that year.

2000s: 2013 | 2012 | 2010 | 2009 | 2008

To top of page

NRC Documents

This section lists, in chronological order, the years in which the staff of the U.S. Nuclear Regulatory Commission (NRC) sent documents to PEC in association with PEC's application to obtain a combined license (COL) for Shearon Harris Nuclear Site, Units 2 & 3. You may click on a year in the list below to see a listing of the documents that were sent in that year.

2000s: 2011 | 2010 | 2009 | 2008

To top of page

Safety Evaluations

This section lists the Safety Evaluations that the NRC has issued in connection with its review of the COL application that PEC submitted for Shearon Harris Nuclear Site Units 2 & 3.

To top of page

Topical Reports

The NRC has issued no Topical Reports in connection with its review of the COL application that PEC submitted for Shearon Harris Nuclear Site Units 2 & 3.

To top of page