Applicant Documents

The following table provides access to the COL Application and other documents that Detroit Edison Company submitted in 2008 for Fermi, Unit 3.

Date Description
11/11/08 Detroit Edison Company Submittal of Fermi 3 FSAR Section 2.4.13 Analysis
10/27/08 Detroit Edison Company Submittal of Response to NRC Acceptance Review Questions (Sections 2.5.2 and 2.5.4)
09/18/08 Detroit Edison Company transmittal letter for Fermi Unit 3 COLA

See Application

NRC Documents

The following table provides access to documents and correspondence that the NRC has issued in 2008 in connection with its review of the COL application that Detroit Edison Company submitted for Fermi, Unit 3.

Date Description
12/10/08 Fermi 3 Combined License Application Notice of Intent To Prepare an Environmental Impact Statement and Conduct Scoping Process
11/25/08 Acceptance for Docketing of the Detroit Edison Company Application for a Combined License for Fermi 3
10/10/08 Acknowledgement of Receipt of the Combined License Application for Fermi 3