2008 - Comanche Peak Nuclear Power Plant, Units 3 and 4 Application

On this page:

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Applicant Documents

The following table provides access to the COL Application and other documents that Luminant submitted in 2008 for Comanche Peak Nuclear Power Plant, Units 3 & 4.

Date Description
12/18/08 Response to request for additional information on 2.4.13
11/10/08 Resolution of Docketing Issues Regarding COL Holder
11/06/08 Resolution of Docketing Issues Regarding FSAR Subsection 2.45.13
11/05/08 Resolution of Docketing Issues Regarding FSAR Subsections 2.5.1, 2.5.2, and 2.5.4
11/04/08 Resolution of Docketing Issues Regarding FSAR 2.5.4, 6.4.4, and the Emergency Plan
09/19/08 Comanche Peak Nuclear Power Plant, Units 3 and 4, Meteorological Data
09/19/08 Luminant transmittal letter for Comanche Peak COLA

See Application
05/31/08 Comanche Peak Power Plant - Golden-Cheeked Warbler Bird Survey Report

NRC Documents

The following table provides access to documents and correspondence that the NRC has issued in 2008 in connection with its review of the COL application that Luminant submitted for Comanche Peak Nuclear Power Plant, Units 3 & 4.

Date Description
12/12/08 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping
12/02/08 Notification for Docketing and Federal Register Notice
11/03/08 Acknowledgment of receipt of the Combined License Application for Comanche Peak, Units 3 and 4