Application Review Schedule for Lost Creek

The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Lost Creek ISR, LLC submitted to obtain a license for its Lost Creek In Situ Recovery site.

Key Milestones Completion Date
Actual - A
Target - T
Application Tendered 10/30/07 – A
Application Withdrawn 2/29/08 – A
Application Resubmitted 3/20/08 – A
Acceptance Review
Acceptance Review Start
3/20/08 – A
Docketing Decision Letter Issued/Acceptance Review Complete
6/10/08 – A
Safety Review
Requests for Additional Information (RAIs) Issued to Applicant
11/6/08 – A
Final Safety Evaluation Report (SER) completed
8/5/11 – T
Environmental Review
RAIs Issued to Applicant
3/16/09 – A
Draft SEIS issued to EPA
12/11/09 – A
Public comment period
3/31/10 – A
Final SEIS issued to EPA
6/24/11 – A
License
Licensing Action Completed
8/5/11 – T

Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.