ROP Action Matrix Summary and Current Regulatory Oversight

The assessment program collects information from inspections and performance indicators (PIs) in order to enable the agency to arrive at objective conclusions about the licensee's safety performance. Based on this assessment information, the NRC determines the appropriate level of agency response, including supplemental inspection and pertinent regulatory actions ranging from management meetings up to and including orders for plant shutdown. The Action Matrix Summary listed below reflects overall plant performance and is updated regularly to reflect inputs from the most recent performance indicators and inspection findings. Security information is not publicly available and the associated performance indicators and inspection findings are not integrated into the Action Matrix Summary.

For those plants that are in the regulatory response column, degraded cornerstone column, multiple/repetitive degraded cornerstone column, and unacceptable performance column of the Action Matrix, notes are provided to explain the assessment inputs that direct the associated regulatory response. Additionally, information on the current level of inspection at each reactor unit (based on deviations from the Action Matrix, supplemental inspection status, etc.) is also found below with each site. For any licensee in the Licensee Response Column, the expected agency inspection is the baseline program.

The substantive cross-cutting issues are available on the ROP Substantive Cross Cutting Issues Summary page for each of the plants.

Current Regulatory Oversight Table

Region I | Region II | Region III | Region IV | Action Matrix Summary

Top of page Region I

Reactor Unit

Current Regulatory Oversight

Action Matrix Column

Beaver Valley 1

Baseline Inspection

Licensee Response Column 

Beaver Valley 2

Baseline Inspection

Licensee Response Column 

Calvert Cliffs 1

Baseline Inspection

Licensee Response Column 

Calvert Cliffs 2

Baseline Inspection

Licensee Response Column 

FitzPatrick

Baseline Inspection

Licensee Response Column 

Ginna

Baseline Inspection

and

An IP 95002 supplemental inspection will be performed.

Degraded Cornerstone Column

Ginna is in the Degraded Cornerstone Column due to two White findings in the Mitigating Systems Cornerstone (one originating in 1Q2009, and one originating in 4Q2009), and one White Performance Indicator (PI) in the Mitigating Systems Cornerstone originating in 3Q2009. The 1Q2009 White finding was related to inadequate implementation of the preventative maintenance program for the turbine-driven auxiliary feedwater (TDAFW) pump governor that led to a failure of the pump to operate properly during a surveillance test. The 4Q2009 White finding was related to inadequate corrective actions to prevent recurrence of corrosion which led to binding of the governor control valve and failure of the TDAFW pump. The White PI was related to exceeding the limit for Heat Removal Systems reliability.

Hope Creek 1

Baseline Inspection

Licensee Response Column 

Indian Point 2

Baseline Inspection

Licensee Response Column 

Indian Point 3

Baseline Inspection

and

An IP 95001 supplemental inspection will be performed.

Regulatory Response Column

Indian Point Unit 3 is in the Regulatory Response Column due to one White Performance Indicator (PI) in the Initiating Events Cornerstone originating in 3Q2009. The White PI was related to exceeding the limit for Unplanned Scrams per 7000 Critical Hours.

Limerick 1

Baseline Inspection

Licensee Response Column 

Limerick 2

Baseline Inspection

Licensee Response Column 

Millstone 2

Baseline Inspection

Licensee Response Column 

Millstone 3

Baseline Inspection

Licensee Response Column 

Nine Mile Point 1

Baseline Inspection

Licensee Response Column 

Nine Mile Point 2

Baseline Inspection

and

An IP 95001 supplemental inspection will be performed.

Regulatory Response Column

Nine Mile Point Unit 2 remained in the Regulatory Response Column due to one parallel White finding originating in 4Q2009. The White finding was associated with a previous White performance indicator (PI) in the Mitigating System cornerstone originating in 4Q2008 for Cooling Water System unavailability and reliability. The supplemental inspection for the White PI, completed on October 16, 2009, resulted in the parallel White finding based on NRC identified weaknesses in the licensee's root cause evaluation.

Oyster Creek

Baseline Inspection

and

An IP 95001 supplemental inspection will be performed.

Regulatory Response Column

Oyster Creek is in the Regulatory Response Column due to one White Performance Indicator (PI) in the Initiating Events cornerstone originating in 3Q2009. The White PI was related to exceeding the limit for Unplanned Scrams per 7000 Critical Hours. The PI has reverted to Green, so Oyster Creek will remain in the Regulatory Response Column until the supplemental inspection is completely succesfully.

Peach Bottom 2

Baseline Inspection

Licensee Response Column 

Peach Bottom 3

Baseline Inspection

Licensee Response Column 

Pilgrim 1

Baseline Inspection

Licensee Response Column 

Salem 1

Baseline Inspection

Licensee Response Column 

Salem 2

Baseline Inspection

Licensee Response Column 

Seabrook 1

Baseline Inspection

and

An IP 95001 supplemental inspection will be performed.

Regulatory Response Column

Seabrook is in the Regulatory Response Column due to one White finding in the Mitigating Systems Cornerstone. The final significance determination and follow-up assessment letter was issued on November 12, 2009, based upon an inspection completed in 3Q2009, and involved the failure to adequately control design changes implemented on the B Emergency Diesel Generator jacket water cooling system.

Susquehanna 1

Baseline Inspection

Licensee Response Column 

Susquehanna 2

Baseline Inspection

Licensee Response Column 

Three Mile Island 1

Baseline Inspection

Licensee Response Column 

Vermont Yankee

Baseline Inspection

Licensee Response Column 

 

Top of page Region II

Reactor Unit

Current Regulatory Oversight

Action Matrix Column

Browns Ferry 1

Baseline Inspection

Licensee Response Column 

Browns Ferry 2

Baseline Inspection

Licensee Response Column 

Browns Ferry 3

Baseline Inspection

Licensee Response Column 

Brunswick 1

Baseline Inspection

and

An IP 95001 supplemental inspection will be performed.

Regulatory Response Column

Brunswick Unit 1 is in the Regulatory Response Column due to one White finding in the Mitigating Systems Cornerstone originating in 2Q2009.

Brunswick 2

Baseline Inspection

and

An IP 95001 supplemental inspection will be performed.

Regulatory Response Column

Brunswick Unit 2 is in the Regulatory Response Column due to one White finding in the Mitigating Systems Cornerstone originating in 2Q2009.

Catawba 1

Baseline Inspection

Licensee Response Column 

Catawba 2

Baseline Inspection

Licensee Response Column 

Crystal River 3

Baseline Inspection

Licensee Response Column 

Farley 1

Baseline Inspection

and

IP 95001 supplemental inspections will be performed.

Regulatory Response Column

Farley Unit 1 is in the Regulatory Response Column due to one White finding in the Emergency Preparedness Cornerstone originating in 2Q2009. In addition, Farley Unit 1 has one White PI for the Emergency AC Power System in the Mitigating Systems Cornerstone.

Farley 2

Baseline Inspection

and

An IP 95001 supplemental inspection will be performed.

Regulatory Response Column

Farley Unit 2 is in the Regulatory Response Column due to one White finding in the Emergency Preparedness Cornerstone originating in 2Q2009.

Harris 1

Baseline Inspection

Licensee Response Column 

Hatch 1

Baseline Inspection

Licensee Response Column 

Hatch 2

Baseline Inspection

Licensee Response Column 

McGuire 1

Baseline Inspection

and

An IP 95001 supplemental inspection will be performed.

Regulatory Response Column

McGuire Unit 1 is in the Regulatory Response Column due to one White finding in the Mitigating Systems Cornerstone originating in 3Q2008. This finding is being held open, in accordance with IMC 0305, for greater than 4 quarters pending NRC completion of the IP 95001 supplemental inspection.

McGuire 2

Baseline Inspection

and

An IP 95001 supplemental inspection will be performed.

Regulatory Response Column

McGuire Unit 2 is in the Regulatory Response Column due to one White finding in the Mitigating Systems Cornerstone originating in 3Q2008. This finding is being held open, in accordance with IMC 0305, for greater than 4 quarters pending NRC completion of the IP 95001 supplemental inspection.

North Anna 1

Baseline Inspection

Licensee Response Column 

North Anna 2

Baseline Inspection

Licensee Response Column 

Oconee 1

Baseline Inspection

Licensee Response Column 

Oconee 2

Baseline Inspection

Licensee Response Column 

Oconee 3

Baseline Inspection

Licensee Response Column 

Robinson 2

Baseline Inspection

Licensee Response Column 

Saint Lucie 1

Baseline Inspection

Licensee Response Column 

Saint Lucie 2

Baseline Inspection

Licensee Response Column 

Sequoyah 1

Baseline Inspection

Licensee Response Column 

Sequoyah 2

Baseline Inspection

Licensee Response Column 

Summer

Baseline Inspection

Licensee Response Column 

Surry 1

Baseline Inspection

Licensee Response Column 

Surry 2

Baseline Inspection

Licensee Response Column 

Turkey Point 3

Baseline Inspection

Licensee Response Column 

Turkey Point 4

Baseline Inspection

Licensee Response Column 

Vogtle 1

Baseline Inspection

Licensee Response Column 

Vogtle 2

Baseline Inspection

Licensee Response Column 

Watts Bar 1

Baseline Inspection

Licensee Response Column 

 

Top of page Region III

Reactor Unit

Current Regulatory Oversight

Action Matrix Column

Braidwood 1

Baseline Inspection

and

An IP 95001 supplemental inspection will be performed.

Regulatory Response Column

Braidwood 1 is in the Regulatory Response Column due to one White finding in the Mitigating Systems Cornerstone originating in 4Q2009. The final significance determination letter was signed on February 25, 2010.

Braidwood 2

Baseline Inspection

Licensee Response Column 

Byron 1

Baseline Inspection

Licensee Response Column 

Byron 2

Baseline Inspection

Licensee Response Column 

Clinton

Baseline Inspection

Licensee Response Column 

D.C. Cook 1

Baseline Inspection

Licensee Response Column 

D.C. Cook 2

Baseline Inspection

Licensee Response Column 

Davis-Besse

Baseline Inspection

and

An IP 95001 supplemental inspection will be performed.

Regulatory Response Column

Davis-Besse is in the Regulatory Response Column due to one White finding in the Emergency Preparedness Cornerstone originating in 4Q2009. The final significance determination letter was signed on February 25, 2010.

Dresden 2

Baseline Inspection

Licensee Response Column 

Dresden 3

Baseline Inspection

and

An IP 95001 supplemental inspection will be performed.

Regulatory Response Column

Dresden Unit 3 is in the Regulatory Response Column due to one White finding in the Mitigating Systems Cornerstone originating in 3Q2009. The finding was documented in an inspection report issued on August 19, 2009 and the final significance determination letter was signed October 26, 2009.

Duane Arnold

Baseline Inspection

The IP 95001 supplemental inspection was completed on December 15, 2009, and the inspection report was issued on January 28, 2010 (ML100280210). Barring any additional greater than green inputs, Duane Arnold will transition to the Licensee Response Column at the end of 1Q2010.

Regulatory Response Column

Duane Arnold is in the Regulatory Response Column due to one White finding in the Mitigating Systems Cornerstone originating in 2Q2009. The final significance determination letter was issued June 9, 2009.

Fermi 2

Baseline Inspection

Licensee Response Column 

Kewaunee

Baseline Inspection

Licensee Response Column 

La Salle 1

Baseline Inspection

Licensee Response Column 

La Salle 2

Baseline Inspection

Licensee Response Column 

Monticello

Baseline Inspection

Licensee Response Column 

Palisades

Baseline Inspection

and

An IP 95001 supplemental inspection will be performed.

Regulatory Response Column

Palisades is in the Regulatory Response Column due to one White finding involving spent fuel pool plate degradation, originating in 4Q2009. The finding was originally documented as an Apparent Violation in an inspection report issued on December 9, 2009, and the final significance determination letter was issued on January 20, 2010.

Perry 1

Baseline Inspection

Licensee Response Column 

Point Beach 1

Baseline Inspection

Licensee Response Column 

Point Beach 2

Baseline Inspection

Licensee Response Column 

Prairie Island 1

Baseline Inspection

Licensee Response Column

Prairie Island 2

Baseline Inspection

and

An IP 95001 supplemental inspection will be performed.

Regulatory Response Column

Prairie Island
Unit 2 is in the Regulatory Response Column due to one White finding in the Mitigating Systems Cornerstone originating in 3Q2009. The Mitigating Systems finding was originally documented as an Apparent Violation in an inspection report issued on August 5, 2009, and the final significance determination letter was issued on September 3, 2009.

Quad Cities 1

Baseline Inspection

Licensee Response Column 

Quad Cities 2

Baseline Inspection

Licensee Response Column 

 

Top of page Region IV

Reactor Unit

Current Regulatory Oversight

Action Matrix Column

Arkansas Nuclear 1

Baseline Inspection

Licensee Response Column 

Arkansas Nuclear 2

Baseline Inspection

Licensee Response Column 

Callaway

Baseline Inspection

Licensee Response Column 

Columbia Generating Station

Baseline Inspection

and

An IP 95001 supplemental inspection will be performed.

Regulatory Response Column

Columbia Generating Station is in the Regulatory Response Column due to a White Unplanned Scrams per 7000 Critical Hours Performance Indicator.

Comanche Peak 1

Baseline Inspection

Licensee Response Column 

Comanche Peak 2

Baseline Inspection

Licensee Response Column 

Cooper

Baseline Inspection

Licensee Response Column 

Diablo Canyon 1

Baseline Inspection

Licensee Response Column 

Diablo Canyon 2

Baseline Inspection

Licensee Response Column 

Fort Calhoun

Baseline Inspection

Licensee Response Column 

Grand Gulf 1

Baseline Inspection

Licensee Response Column 

Palo Verde 1

Baseline Inspection

Licensee Response Column 

Palo Verde 2

Baseline Inspection

Licensee Response Column 

Palo Verde 3

Baseline Inspection

Licensee Response Column 

River Bend 1

Baseline Inspection

Licensee Response Column 

San Onofre 2

Baseline Inspection

Region IV has completed the IP 95001 supplemental inspection. Management is evaluating the results.

Regulatory Response Column

San Onofre Nuclear Generating Station, Unit 2 is in the Regulatory Response Column based on a White finding associated with the Mitigating Systems Cornerstone. The finding was issued on December 19, 2008, and involved the failure to establish appropriate instructions for replacement of a safety-related battery output breaker.

San Onofre 3

Baseline Inspection

Licensee Response Column 

South Texas 1

Baseline Inspection

Licensee Response Column 

South Texas 2

Baseline Inspection

Licensee Response Column 

Waterford 3

Baseline Inspection

Regulatory Response Column

Waterford 3 is in the Regulatory Response Column based on a White finding associated with the Mitigating Systems Cornerstone originating in 3Q2009. The final significance determination letter was issued on January 14, 2010 (ML100150660).

Wolf Creek 1

Baseline Inspection

Licensee Response Column 

 

Top of page Action Matrix Summary

Licensee Response Column

Regulatory Response Column

Degraded Cornerstone Column

Multiple/Repetitive Degraded Cornerstone Column

Unacceptable Performance Column

Arkansas Nuclear 1

Braidwood 1

Ginna

 

 

Arkansas Nuclear 2

Brunswick 1

 

 

 

Beaver Valley 1

Brunswick 2

 

 

 

Beaver Valley 2

Columbia Generating Station

 

 

 

Braidwood 2

Davis-Besse

 

 

 

Browns Ferry 1

Dresden 3

 

 

 

Browns Ferry 2

Duane Arnold

 

 

 

Browns Ferry 3

Farley 1

 

 

 

Byron 1

Farley 2

 

 

 

Byron 2

Indian Point 3

 

 

 

Callaway

McGuire 1

 

 

 

Calvert Cliffs 1

McGuire 2

 

 

 

Calvert Cliffs 2

Nine Mile Point 2

 

 

 

Catawba 1

Oyster Creek

 

 

 

Catawba 2

Palisades

 

 

 

Clinton

Prairie Island 2

 

 

 

Comanche Peak 1

San Onofre 2

 

 

 

Comanche Peak 2

Seabrook 1

 

 

 

Cooper

Waterford 3

 

 

 

Crystal River 3

 

 

 

 

D.C. Cook 1

 

 

 

 

D.C. Cook 2

 

 

 

 

Diablo Canyon 1

 

 

 

 

Diablo Canyon 2

 

 

 

 

Dresden 2

 

 

 

 

Fermi 2

 

 

 

 

FitzPatrick

 

 

 

 

Fort Calhoun

 

 

 

 

Grand Gulf 1

 

 

 

 

Harris 1

 

 

 

 

Hatch 1

 

 

 

 

Hatch 2

 

 

 

 

Hope Creek 1

 

 

 

 

Indian Point 2

 

 

 

 

Kewaunee

 

 

 

 

La Salle 1

 

 

 

 

La Salle 2

 

 

 

 

Limerick 1

 

 

 

 

Limerick 2

 

 

 

 

Millstone 2

 

 

 

 

Millstone 3

 

 

 

 

Monticello

 

 

 

 

Nine Mile Point 1

 

 

 

 

North Anna 1

 

 

 

 

North Anna 2

 

 

 

 

Oconee 1

 

 

 

 

Oconee 2

 

 

 

 

Oconee 3

 

 

 

 

Palo Verde 1

 

 

 

 

Palo Verde 2

 

 

 

 

Palo Verde 3

 

 

 

 

Peach Bottom 2

 

 

 

 

Peach Bottom 3

 

 

 

 

Perry 1

 

 

 

 

Pilgrim 1

 

 

 

 

Point Beach 1

 

 

 

 

Point Beach 2

 

 

 

 

Prairie Island 1

 

 

 

 

Quad Cities 1

 

 

 

 

Quad Cities 2

 

 

 

 

River Bend 1

 

 

 

 

Robinson 2

 

 

 

 

Saint Lucie 1

 

 

 

 

Saint Lucie 2

 

 

 

 

Salem 1

 

 

 

 

Salem 2

 

 

 

 

San Onofre 3

 

 

 

 

Sequoyah 1

 

 

 

 

Sequoyah 2

 

 

 

 

South Texas 1

 

 

 

 

South Texas 2

 

 

 

 

Summer

 

 

 

 

Surry 1

 

 

 

 

Surry 2

 

 

 

 

Susquehanna 1

 

 

 

 

Susquehanna 2

 

 

 

 

Three Mile Island 1

 

 

 

 

Turkey Point 3

 

 

 

 

Turkey Point 4

 

 

 

 

Vermont Yankee

 

 

 

 

Vogtle 1

 

 

 

 

Vogtle 2

 

 

 

 

Watts Bar 1

 

 

 

 

Wolf Creek 1

 

 

 

 

 

 

 

 

 

Top of pageTop of Page

 


Last modification: Feb 26, 2010